Power generator - missions
Download
Report
Transcript Power generator - missions
Energy
PAD Logistic – January
1er avril 2017
1 - ENERGY/ ELECTRICITY
Safety
Risks :
- Electrification
- Electrocution
- Fire
- Equipment damages
Supply
Power supply sources :
- City power (local grid)
- Power generator
- Battery kit with solar
Sources d’appoint :
- Power generator
- Battery kit
- UPS (Inverter all-in-one)
Your role as a logisitician :
- Prevent accidents
- Protect appliances
1er avril 2017
Your role as a logisitician :
- Insure electrical availability (Quantity
and quality)
- Improve electrical usage
2
1.1 ELECTRICAL SAFETY
1er avril 2017
3
Quick Assessment
Use the table to make quick assessment of installations :
- At your arrival
- When renting a new place
Available on kitlog online
Useful to do a quick assessment
of the 5 essential safety rules
If the building is noted :
• 0 to 3 / 10 : Building need emergency works, HQ advisor must be notified
• 4 to 7 / 10 : Works are to be planned. It is necessary to plan adapted
budgets to perform it during the next 6 months
• 8 to 10 / 10 : The building is at minimum standard level. You can plan small
works to improve user’s safety conditions
1er avril 2017
4
Basic safety rule #1
No possibilty of direct contact = 1 pt
That happens especially with
detached switches and outlets,
when an equipment is removed
and not replaced, on bad
connection of two wires
If you notice nude wires or any
possibility of direct contact, you
have to make works to avoid them
1er avril 2017
5
Basic safety rule #1
As a vehicle, an electrical installation need a maintenance
That must be planned and budgeted :
City apartment
300 à 500 €
1er avril 2017
Individual building
1000 €
Isolated Compound
1500 €
6
Basic safety rule #2
No electricity more close than 1,5 m from water
No wire, socket, switch or electrical equipment of any kind
That concerns bathrooms,
kitchens, any room with tap, …
And also water dispensor !
Because of possible leackage
Water
Computer
UPS
Photocopier
1er avril 2017
7
Basic safety rule #2
Whatever skills or countries, a local electrician is able to create a
new socket outlet and to disconnect and seal the old one.
Do not wait the incident
or somebody obliges you to do it !
=> Remove these items from water immediately
1er avril 2017
8
Basic safety rule #3
Electrical panel (switch board) = 3pts
Building must have an electrical switch board
Correctly fixed, without signs of burn
With adapted protections
1pt
1er avril 2017
2pt
=> 1pt
=> 1pt
=> 1pt
3pt
9
Basic safety rule #3
All equipement must be protected
by circuit breaker or fuses
If you don’t have any circuit-breaker or
fuses on your building, your situation is
an emergency. You have to contact an
electrician to make works, or the HQ
referent at least
If you have, make a test : switch all
them off and verify if some equipment
still supplied. If yes, that means that
they are not protected. You have to
contact an electrician to make works
1er avril 2017
10
Basic safety rule #4
Size of cables = 1 pt
1er avril 2017
11
Basic safety rule #4
Wires have to respect minimum standard sizes
An under-sized cable if hot, and can burn. If you don’t have any
electrical notion, but you touch a wire and you feel it is hot, it is
not normal ! and you have to change it.
That mainly happens with heavy equipment (boilers, heaters, air
conditioning, …), with long wires, and with overload multi-plugs.
Wire undersized is the first cause of fire starts !
Please refer to electrical and saftey guidelines
to choose the size of wires.
1er avril 2017
12
Basic safety rule #5
Equipment using water or made of a steel frame
must be connect to the earth = 2 pts
To verify it, you can buy an outlet tester =>
If you don’t have earth connection on
heavy equipment and equipment with
steel frame, you must contact an electrician to install it.
Be careful if you want to verify it without tester : to have an earth
cable in you socket outlet don’t mean that this cable is connecter to
this earth.
If you don’t have earth connection on your building, the minimum
protection you can install is a differential circuit breaker
1er avril 2017
13
Basic safety rule #General
If you have any doubt, don’t touch…
…and ask a local electrician or the HQ
Most of the time, send a picture will be enough to :
Identify and evaluate the problem
Explain what works to do and how
Plan incoming costs, …
To not care of installation maintenance is like
transform maintenance operation in renewal
operation
Renewal costs are often heavy and can not be
taken in charge by the mission
1er avril 2017
14
1.2 ELECTRICAL SUPPPLY
Production & extra sources
1er avril 2017
15
Minimum setup regarding the context
GREEN
MAIN
SOURCE
ORANGE
RED
BLACK
LOCAL GRID OR POWER GENERATOR
OPTIONNAL
SECONDARY
SOURCE
YELLOW
IF
GOOD LOCAL
GRID
POWER
GENERATOR
POWER GENERATOR
OR
OR
BATTERY KIT WITH SOLAR
BATTERY KIT
NB : Hibernation room must be supplied
with a battery kit
NIGHT
LIGHTING
1er avril 2017
OBLIGATION
16
Panneaux de raccordement
Local Grid
• Power sheddings (power cuts)
Identify the shedding length and frequency
Keep in mind : A battery need need 4 to 8hr of charging
Obligation to have an emergency power source
• Fluctuations
Buld intensity fluctuations, Fluorescent bulds what not works
correctly, UPS beeping when bulds still illuminated, …
Small stabilizer on Equipment to protect
Heavy stabilizer on the full building
• Voltage peaks (surges)
Surge protector :
1er avril 2017
17
Power generator
0 kVA
6 kVA
12 kVA
Power (1 kVA = 0.8 kW)
3000 to 3600 RPM
1500 to 1800 RPM
Single phase
3-Phase
1 – Evaluate the necessary power => Diagnosis tool on kit log
2 – Check the type of connection to city power and choose the same generator, if not possible
Generator 3-phase with Building Single phase => Works to plan
Generator Single phase with Building 3-Phase => Heavy works to plan
3 – Make it validate before to buy
1er avril 2017
18
Power Generator
Frequent Problems
Mainly caused by …
Voltage fluctuation
Overload
Overload on one phase (3-phase only)
Alternator regulator problem
Permanent low voltage
Alternator problem
Low voltage shutdown
or High Temperature shutdown
Overload
Bad ventilation
Fuel leaks
Bad fuel quality
Obligations :
=> Dispose the logbook next to the generator
=> Stand at attention about fuel consumption
Recommendations :
=> Oil change every 250 hours
=> Heavy maintenance each 2500 to 3000 hours
=> Maximum life length 12 000 hours with good maintenance
1er avril 2017
19
Battery kit
Local purchase
HQ purchase
Size
Max power
Small
2,5 kVA
700 W during 8 h
Medium
3,6 kVA
1 000 W during 8 h
Standard price : 0,40 à 0,5 € / VA
Large
7,2 kVA
1 500 W during 8 h
Warning, charging time are often very long
(>8hrs) because chargers are not powerful
1er avril 2017
runtime
Main sold as all-in one product
- Charger / Inverter
- Batteries
- Maintenance 12 month
- Installation and connexion
20
Ressources
Local electricians
Kit-Log online
[email protected]
1er avril 2017
21
Keep in mind
Almost nothing can be done without a energy supply :
=> have a proper back-up
Do not forget the maintenance of your equipment and installations
Security and good environment practices are the same everywhere
in the world
While buying equipment:
• Take time to assess your needs
• Take into account total life-cycle cost (fuel, maintenance, disposal…)
and not only initial cost
Anticipate your works and costs
More details on the kit log
Contact : [email protected]
1er avril 2017
22