Westchester Master Plan Faculty Council 12-7
Download
Report
Transcript Westchester Master Plan Faculty Council 12-7
Westchester Master Plan
William J. McGrath
Senior Vice President and
Chief Administrative Officer
Lisa Bardill Moscaritolo
Dean for Students
Westchester
December 7, 2012
Master Plan Goals
•
•
•
•
Transform Pleasantville into a beautiful suburban
residential campus.
Migrate the Briarcliff programs onto Pleasantville.
Enrich our community-friendly and environmentallysensitive campus.
Reduce dependence on automobiles and improve
pedestrian circulation in and around campus.
2
A Vision for Campus Life
• Increase the critical mass of students in residence to
enhance campus life
• Leverage the bucolic landscape by creating grassy
quads and landscaped pedestrian pathways to
provide more central gathering spaces
• Enrich co-curricular programming through LivingLearning Communities
3
A Vision for Campus Life
Building Momentum
• Continued strong demand for student housing
• Growth of existing programs in nursing,
communications, the environment, criminal justice
• Expanding our impact on Pleasantville as a “college
town”
4
A Vision for Campus Life
• Transformed Housing and Campus Life Model –
Living Learning Communities
•
•
•
•
•
•
•
•
Focused on Academic Achievement
First year and Sophomore Housing
Faculty mentoring, advisors, and tutors
Theme housing – curricular (student interest) and cocurricular (faculty interest)
Food kiosks/branded concepts in common spaces
Study/Program space
Classrooms
Welcome Desks
5
A Vision for Campus Life
New Housing Model
•
•
•
Create mix of unit types to
meet market demand while
fostering student
development
Accommodate living-learning
program opportunities
Provide expanded services
to improve residential and
student life experience (Pace
Perk, added dining option)
Faculty/Staff
Apartment
Classrooms
Food/Common
Area
Study Lounges
6
New Residence Halls in the Core of Campus
7
Enriching the Athletics Program
8
Beautiful Campus Green and Landscaped
Pedestrian Pathways
9
Relocate and Enhance Environmental Center
10
Where We Are Today
•
•
•
•
•
•
100 % Schematic Designs are complete
Prioritized Academic Space in Westchester
Completed the State Environmental Quality Review
(SEQR) process
Mount Pleasant Planning Board issued and adopted
a findings statement on the Final Environmental
Impact Statement
Financial Feasibility Study complete
Board of Trustees approved the continuation of the
Regulatory Approval Process
11
Next Steps
•
•
•
•
•
•
•
Complete Design Development Phase – Feb 2013
Issue RFP for Construction Manager Firm – Jan 2013
Submit Site Plan Application to Planning Board – Jan 2013
Complete Zoning Petition Process with Town Board – March
2013
Seek approval from Board of Trustees to begin construction –
May 2013
Complete Construction Documents for Phase 1 A projects
June/July 2013
Begin Construction – August 2013
12
Preliminary Development Schedule
Task Name
Start
Finish
2013
2014
2015
2016
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Environmental Center Relocation &
Reconstruction
8/5/2013
2/28/2014
Residence Hall A
3/31/2014 8/14/2015
Kessel Renovation/Construction
12/8/2014 8/14/2015
Residence Hall B
4/13/2015 8/12/2016
Baseball Field and Softball Field
6/15/2014 12/19/2014
Multipurpose Field
1/9/2015
6/15/215
Field House
1/9/2015
8/7/215
Central Campus Site Work (campus
green)
9/30/2013 6/17/2016
13
14