Pres- WGR- NPRR264
Download
Report
Transcript Pres- WGR- NPRR264
Generator Re-Interconnection
Using the IA Procedure
WMS
09 February 2011
Needed: Rational Procedure for ReInterconnecting Generation Resources
Re-interconnecting Generation Resources adds value
CREZ Transmission Plan economics depended in part on
re-interconnecting constrained WGRs
Transmission operations and planning could benefit
from multiple generation interconnections
Horse Hollow Gen Tie demonstrates value
Need a procedure for reliable re-interconnection
without imposing unnecessary costs
Stakeholder Review of the Market
Implications
Joint ROS/WMS Task Force: Market benefits from
generation, regardless of technology, responding to
price signals by changing its delivery point
TAC voted unanimously to:
Grandfather Generation Resources using earliest SGIA
Minimize transmission costs for a new interconnection
Re-Interconnect via the Gen Interconnect procedure
Similar to process for evaluating asynchronous ties
ERCOT’s Latest Proposal is Ambiguous
Links a Generation Resource’s “grandfathered” date to the
Point of Interconnection (POI) defined in its SGIA
A change in Transmission Facilities , by definition is a new POI
ERCOT pointed out in the June 09 RPG meeting, a new
interconnection could be as trivial as changing connection
from a 138kV bus to a 345 kV bus at the same station
Alternative reading is that all re-interconnections require
upgrading to current code
A case specific determination of performance required at
the new POI makes more sense
At least better define “new POI”
ERCOT’s Proposal Undermines
Grandfathering
Substituting “Protocols and Other Binding Documents” for
SGIA suggests generators will face new requirements
Transmission upgrades could have the same effect as
changing POI; would Generators be required to retrofit
then?
Which studies support VRT & Voltage Support retrofits?
Grandfathering should remain in effect unless a need is
demonstrated
Re-Interconnection Should be Studied
for Impacts before Requiring Retrofits
Re-interconnection should follow the Generation
Interconnection or Change Procedure
Provides Generator a degree of certainty
Any upgrades needed can be provided most
economically
Studies could be funded by generator similar to SSI
approach now under consideration
Offers a way around the tipping point problem while
preserving open access
References
Point of Interconnection (POI)
Depends on the Transmission Facilities
“The location(s) where a Generation Entity’s
interconnection Facilities connect to the Transmission
Facilities as reflected in the Standard Generation
Interconnection Agreement (SGIA) between a
Generation Entity and a Tranmission [sic] Service
Provider (TSP) or the location(s) where Load
interconnects to the TSP Facilities.” NP Section 2
CREZ Plan Design Assumes
Re-Interconnection
“The estimated cost of this plan [Scenario 2] is $4.93
billion. One-line diagrams depicting this plan are
provided in Appendix A. All of the components of this
plan are listed in Appendix B. Based on production-cost
modeling, the expected average annual wind
curtailment is 2.31%, with a total wind generation of
64,031 GWh. In this plan, 820 MW of existing wind
generation was moved to a new interconnection
location.” P. 24 CREZ Transmission Optimization Study
Benefits Noted in MIG TF White Paper
“MIGs are desirable in that they have the capability of
reducing prices in some areas and offer additional
operational flexibility to ERCOT;”
“The group determined that ERCOT must also have
the right to direct the Generation Resource… to
connect to the grid or to change connections in order
to use a specific interconnection point during
emergencies.”
10