ERCOTs Interconnection Process

Download Report

Transcript ERCOTs Interconnection Process

ERCOT’s Interconnection
Process
John Adams
Principal Engineer
PV & Storage Workshop
October 15, 2012
Entities involved in the Generation Interconnection Process
in ERCOT
Technical
Consultant
Developer
ERCOT
Financer
2
TSP
For the ERCOT its 1-2-3-4
1) Screening Study
2) Full Interconnection Studies
3) Interconnection agreement
4) Review design for protocol compliance
3
November 14, 2011
Screening Study
4
November 14, 2011
Full Interconnection Studies
5
November 14, 2011
Interconnection Agreement signed
6
November 14, 2011
Review Design for Protocol Compliance
7
November 14, 2011
What is currently checked in 16.5 review
•
•
•
•
•
•
•
•
•
•
Confirm design will produce ±0.95 Power factor reactive at all MW
levels between LSL and HSL Protocol section 8.1.1.2.1.4.
Power System Stabilizer or equivalent is included in the design:
Protocol section 3.15.3[4]
Unit will provide frequency response: Protocol 8.5.1.1 and 8.5.1.3
Unit will dynamically provide voltage regulation: Protocol section 3.15
Breaker interruption capability is suitable to fault duty
Transient voltage ride through per Protocols and operating guides:
Operating Guide section 2.9
AVR is included in the design, and it can be operated in voltage control
mode. Protocol section (3.15.3 & 3.15 [5])
Unit can respond to changes in the voltage profile. Protocol 3.15
Reactive capability is based upon the ability to deliver to the HIGH side
of the step-up transformer. Protocol section (3.15 [3])
Unit is able to receive control signals from its QSE in an upward and
downward direction. (Normally referred to as AGC; Protocol section
8.1.1.2.1.1 and 8.1.1.4.1(7-8))
•
Date
8
Meeting Title (optional)
Timeline summary
Interconnection
Request
Submission
Schedule
FIS
scoping
meeting
Screening
Study
Complete
10
90
Initiate Screening
Study
180
5
FIS
Notice
FIS
Complete
60
(~300)
10
180
Study
review
Complete
FIS
Scope
Set
Sync and
Energization
Checklist
IA
Signed
60
7
NPRR 408
Compliance
Check
As per ERCOT Planning Guide Section 5
Time in Days
9
Generation Interconnection Process in ERCOT
Perform the Screening study (Steady State):
• Discuss possible Points of Interconnections with the
Developer
• Model the system in PSSE using the latest Steady State
Working Group Case
• TARA Contingency Analysis
• Complete the study in 90 days
10
Screening Study Approach
• First Contingency Incremental Transfer Capability
(FCITC) approach, unit under study ramped up from 0120% and constraint and associated violation listed
• Contingency analysis for thermal violations with nearby
Natural Gas units ramped up (Base Case)
• Two standard dispatches executed, summer peak and
low load with wind adjusted up on nearby generators
Load
West Wind
Coast Wind
Nearby
Conventional
Nearby Wind
Sum Peak
Max
SSWG*
SSWG*
100%
95% for Coastal 80%
for West
Low Load
Min
70%
90%
100%
95% for Coastal 80%
for West
• Include all generation with signed Interconnection
Agreements in the vicinity
11
Scheduling the Full Interconnection Study
• 180 days to evaluate completed Screening Study
Results
• Notify all the Transmission Service Providers (TSP)
(Transmission Owners Gen Interconnection List) of the
project under study
• Include lead TSP and Developer to discuss the study
results and chalk out the data requirements, timelines,
protocols
• Draft a scope of the Steady State, Dynamic ,Short Circuit
TSP
and Facility studies to be performed
ERCOT
Screening Study
TSP
Full
Interconnection
Study
Steady State
Stability
Short Circuit
Facilities
12
Full Interconnection Study (FIS) and timelines
• Approximately 300 days for the TSP to complete the FIS
• ERCOT provides comments and reviews to the
completed studies (10 day review period)
• 180 days allowed for the Resource Entity (Developer) to
sign a Interconnection Agreement after the completion of
the comments period
• 60 days for ERCOT to perform compliance checks once
the IA is signed (NPRR 408)
• Compliance tests to be performed by the unit before
synchronization and energization (7 days)
13