Content of the presentation
1)
2)
3)
4)
NCSA Project outputs
What did we achieve?
Where we are now?
How we intend to end?
1) NCSA Project outputs
“original in project document”

Three stocktaking & gap identification
reports of the three thematic areas:
 Desertification.
 Biodiversity.
 Climate change.



Synergy and prioritization report.
In-depth studies report.
Capacity Development Action plan.
------------------------------------------- Management of PMU
 Awareness raising (Bezra and others)
2) What did we achieve?






Three thematic reports ( biodiversity- climate
change – desertification).
Nationalization of MDG 7.
Synergy and prioritization report.
In-depth studies of 5 cross cutting capacity
constrains ( draft ready for consultation) .
Implementation of Bezra summer/school campaign.
Development of CB2 project proposal “mainstreaming
of the global environment in national development plans and
policies by strengthening the monitoring and reporting system
for multilateral environmental agreements in Egypt”
3) Where we are now?





Consultation of in-depth studies Review of
in-depth studies by panel of advisors
Development of the action plan .
Two consultation workshops (National &
Donors) for discussion of the action plan.
High level endorsement of the action plan.
Preparation of Environmental awareness
campaign (Protecting our Global
Environment – our right) in cooperation with
El Sawy culture Wheel.
4) How we intend to end?




Finalizing & printing of the in-depth studies report
(end of May 2007)
Production of the capacity development action plan
that links the 3 conventions with possible funding
sources ( end of july – August 2007)
Conduct & evaluate the Environmental awareness
campaign with El Sawy culture Wheel ( end of june
2007) .
Production of NCSA process report (final project report
indicating the experience & lessons learned)( September
2007).