IEC TC57 WG14
Scott Neumann
December 8, 2005
IEC TC57 WG14
• Developing IEC 61968
• Focus is to describe the information exchanges between
systems (i.e. A2A and B2B) related to distribution
operations
• Defines integration between a variety of systems including
network management, outage management, work
management, asset management, SCADA, metering, call
handling, …
• IEC 61968-1 architecture specification is transport
independent
• XML used to format message payloads
• Messages defined using nouns and verbs
• Recognizes request/reply and publish/subscribe
messaging paradigms
2
IEC 61968
3
IEC 61968 Documents
Part 1: Architecture
Part 2: Glossary
Part 3: Network Operation
Part 4: Network and Asset Management
Part 5: Operational Planning and Optimization
Part 6: Maintenance and Construction
Part 7: Network Extension Planning
Part 8: Customer Inquiry
Part 9: Meter reading and Control
Part 10: Systems External to, but Supportive of, Distribution
Management
Part 11: Common Information Model (extensions)
Part 12: Use Cases
4
IEC 61968
• Extends the 61968 package of the CIM, where
the core CIM is defined by IEC 61970-301
• Integration defined using XML messages
• Messages have a header and a payload
• Header identifies a noun and a verb
• Payload uses CIM-derived type definitions as
described using XML Schema
• Can be used for SOA implementations
5
CIM Packages
Generation
LoadModel
Outage
Protection
SCADA
Assets
Meas
Wires
Financial
ERP
Support
61968
Consumer
Energy
Scheduling
Topology
Commercial
Transactions
Core
Domain
6
Reservation
CIM Extensions
• Modeling of electrical distribution,
extending Wires package
• Added 61968 package to CIM:
•
•
•
•
•
Assets
Consumer
Documentation
Work
ERP_Support (leverages OAG)
7
Use Cases
8
IEC 61968 Messages
• Message has header, with optional request, reply and
payload sections
• Header includes information such as a verb, noun,
timestamps, revision, source, replyAddress, …
• Supports request/reply, publish/subscribe and point-topoint messaging
9
IEC 61968 Messages
10
Message Verbs
Request/Reply:
• CREATE
• CHANGE (UPDATE)
• CANCEL
• CLOSE
• DELETE
• GET
• SHOW
• REPLY
Publish/Subscribe:
• CREATED
• CHANGED (UPDATED)
• CANCELED
• CLOSED
• DELETED
• SUBSCRIBE
• UNSUBSCRIBE
11
Example Message Nouns
•
•
•
•
•
•
•
NetworkDataSet
NetworkChangeSet
LoadDataSet
OperationalRestriction
SafetyDocument
SwitchingSchedule
OutageReport
12
•
•
•
•
•
•
•
•
TroubleTicket
PlannedOutage
OutageNotice
Work
Schedule
AcessPermit
OneCallRequest
…
Steps in Defining Messages
• Generate XML Schema complex types
from the CIM (once)
• Develop use cases
• For each use case, identify message
sequences in terms of verbs and nouns
• For each message define XML Schema,
identifying necessary payload content in
terms of references to CIM complex types
13
Customer Meter Data Sets
14
Status
• Last meeting held October 2005 in St. Louis,
attended by 19 persons
• Next meeting to be held January 2006 in
Switzerland
• Parts 1 and 3 have been completed, but will be
updated to reflect agreed use of XML Schema
• Most work is currently being done on parts 4, 6,
9 and 12
• Need to get WG14 CIM changes stabilized into
base CIM
15
References
• Official CIM web site is at http://wg14.com
(same as http://www.cimuser.com), site is
supported and maintained by UISOL
• IEC documents available from
http://www.iec.ch
16