Demo Link and the LOC Status Report
Download
Report
Transcript Demo Link and the LOC Status Report
Demo Link and the LOC
Status Report
1.
2.
3.
4.
Demo Link status
LOC2 status
Irradiation tests on optical fiber
Summary
Vitaliy for
the SMU team
1
Demo Link status
The idea:
The status:
Use the GOL to construct an optical link to read out the
staves under development.
Provide a Giga-bit optical link that develops together with
the detector and front-end ASICs.
Provide a test vehicle to study system and integration
issues at an early stage.
Demo Links can be quickly constructed with LOC or GBTx
when they become available in 2009/2010.
These demo links will lead a baseline design for final
production, installation evaluations and will provide links
for reliability studies before the production begins.
Next page.
The plan:
J. Ye, Dept. of
Demo Link and LOC report at UCSC
2
The status
Block diagram. The interface boards can be
changed with the stave development.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
3
The status
Design and layout
All documents (schematics, layouts) available online:
http://www.physics.smu.edu/~lab17/GTOM/welcome.htm
The GOL and TLK carrier boards sent for fab.+assembly on 8/6.
SFP+/VL
GOL
SFP+/VL
GOL carrier board
J. Ye, Dept. of
Demo Link and LOC report at UCSC
TLK
TLK carrier board
4
The plan:
Currently layout the two interface boards.
FPGA code development when all boards are out
for fabrication and assembly.
8/25 – 9/5: debugging at SMU.
9/10, 11: first test at LBNL.
May need a few integration tests and
modifications of the interface boards.
Will provide boards to interested groups for
system level studies by the end of this year.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
5
LOC2 status
Design status:
Currently carry out post layout simulations on key
components to define the speed of LOC2.
Still in discussion with people in Inner Detector and in LAr
trying to make LOC2 best fit the needs in both readout. In
ID, we need to work more closely with people who develop
the (supper-) module-controller to understand the input to
LOC2. We may make use of the fact that the output of MC
is already 8B/10B encoded to maximize the use of the
bandwidth.
Current simulations show a 5 Gbps LOC2 hopeful.
Details in the following pages.
The plan:
after the status report.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
6
LOC2 Block diagram and challenging spots:
Cntrl/Config
Clk_ref
PLL
+ clks
Data
16 bit Input register
LVDS to LVCMOS
16 LVDS
27-1 PRBS
2:1 MUX
to 8 bit
Latch
8B/10B
Comma
10 bit
2:1 MUX
Even bits shift register
Odd bits shift register
MUX
Cntrl
config
CML
driver
Serial output to
Versatile Link
Critical components:
1. PLL. VCO, the first stage divider speed. Architecture choice: reliability, jitter, implementation.
2. Static D-flip-flop. The building block of the divider, and the shift register speed.
3. CML driver.
Inverter: basic unit of a CMOS circuit. Study the PMOS/NMOS ratio, circuit speed.
We may move the 8B/10B encoder out of LOC2 to better interface ID and LAr. That is,
we may design dedicated interface chips for LOC’s applications. This is in discussion right
now and will be finalized soon.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
7
The inverter
PMOS/NMOS ratio adjusted to
have the same 10 and 01
delays.
The ratio: n*(1.9/1.4)
where n = 1,2,3,4…
Basic layout, multi-finer layout
checked to optimize speed. The
delay is about 32~35 ps (drive
itself), corresponding to a
frequency of about 30 GHz.
Agree with Peregrine’s tech
notes, and comparable with
speeds achieved in 0.13 to 0.15
micron bulk CMOS technology.
(We only use RN/RP transistor
which have been tested. We
may be able to use IN/IP
transistors are faster, and may
be comparable with 0.13um
process.)
J. Ye, Dept. of
schematics
Demo Link and LOC report at UCSC
layout
.
8
The D-flip-flop (DFF)
We started out with the C2MOS type of DFF used in GOL, but moved to the TGDFF: ~20%
faster, and at least the same SEE immunity (Ramanarayanan, Upenn).
Different transistor size, single finger and multi-finger layouts are checked. The total delay is
292 ps (slowest or the S-S corner). This indicates a 5 Gbps serializer possible, because the
time needed for a basic unit (DFF+mux) is 400 ps.
Mostly singlefinger layout
multi-finger layout
schematics
J. Ye, Dept. of
Demo Link and LOC report at UCSC
9
Differential Ring oscillator VCO
VCO Frequence Vs VCTRL
6
5
4
3
2
1
0
0.8
1.3
1.8
2.3
VCTRL
We choose this 4-stage VCO, a similar structure as in the GOL.
Schematic level simulation indicates that a maximum frequency of
5.5GHz can be reached (the typical-typical corner) . We need 2.5 GHz
from post layout for 5 Gbps data transmission with a 50% duty cycle.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
10
The divider in the first stage
The first stage divider in the PLL provides the bit
clock, loading clock to the serializing unit. This first
stage has to run at 2.5 GHz for 5 Gbps data rate.
A two-arm serializer requires a divid-by-5 first stage.
This is challenging at 2.5 GHz and it is being
studied.
A (jitter improved) four-arm serializer requires a
divid-by-2 first stage, which is a DFF + Inverter. Our
TGDFF(292ps, S-S) + Inverter(35ps, T-T) leaves us
a good margin to run at 2.5 GHz.
But we prefer the two-arm serializer for its simplicity.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
11
LOC2 work plan, near future
Finalize the structure: with 8B/10B encoder or move
the encoder out. With the latter, dedicated interface
chips will be designed to best cope with the input
data and maximize the use of the link bandwidth.
Post layout studies on all the critical components
and understand the speed of LOC2. At this moment,
5 Gbps is hopeful.
Careful studies on the PLL, mostly the RJ, or phase
noise.
A design review (1st), Oct./Nov. time frame, at BNL
or CERN on the critical parts. Get help from the
community on things we may have overlooked,
misunderstand, etc.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
12
LOC2 work plan, till April 2009
After the 1st design review, we will move on to
Complete PLL and clock unit design.
Complete the serializer design.
Implement the 8B/10B and 64B/66B Encoders, or design the
interface chips.
Implement the control/config unit.
Implement the CML driver.
We aim for the 2nd design review, Jan./Feb. 2009, on the whole
chip or chip set.
We aim for the April 09 submission, and the tests in lab July 09.
We will provide demo-link and system design document for
groups that are interested in using this chip in the fall of 2009.
Full evaluation of LOC2, including irradiation tests are planned to
take place in the fall of 2009.
Reference: GBTx is planned to be available end of 2009.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
13
Irradiation tests on optical fiber
To complete a rad-tol optical link system, one
needs to identify rad-tol components such as
VCSEL, fiber and PINs. This part of the work
is now the Versatile Project. At SMU, we
identified a 10G fiber and performed several
tests on the fiber.
The report here consists:
Results from ATLAS LAr.
Narrow down to Germanium doped GRIN fiber.
Preliminary tests.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
14
Results from ATLAS LAr
Ref: Nucl. Phys. B, Proc. Suppl. 78 (1999) 719-24 Irradiation
studies of multimode optical fibres for use in ATLAS front-end links
POF: Plasma Optics Fiber,
Germanium doped.
From the production
qualification tests: see
next page.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
15
Results from ATLAS LAr
From ATLAS LAr fiber selection:
Germanium doped MM fiber from Plasma Optical Fibres have been found to
withstand radiations over 800~Gy(Si) and 2 × 1013cm-2 (1-MeV equivalent
in Si) with less than 0.1~dB/m attenuation.
The fiber batch used for the production of the optical cables was verified
using a Co-60 source.
Two 5 cm diameter rolls with 100~m of fiber each were irradiated with a dose
rate of 150 Gy/hr.
After 1 hour of irradiation the transmission loss over the 100 m was less than
10% or less than -0.005 dB/m.
Immediately after 2 hours irradiation (300 Gy) the loss was -0.04 dB/m, but it
improved to -0.015 dB/1m within 10 minutes, indicating a fast annealing
process was taking place.
The optical loss was measured to be -0.135 dB/m immediatly after the total
dose reached 2.8 kGy. Within 1 hour annealing at room temperature, the loss
was reduced to -0.1 dB/m, satisfying the requirement we set for radiation
induced optical power loss. We expect the actual loss in real ATLAS
environment is much less than -0.1 dB/m due to the fast annealing process.
Because there are only a few meters of fiber that is actually at the FEB
location, we estimate a maximum optical power loss due to radiation to be
less than 1 dB, well within the 10 dB power margin we have.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
16
Narrow down to Germanium doped GRIN
fiber
Ref: IEEE Trans. On Nuclear Science, Vol. 54, No. 4, Aug. 2007,
Low-Dose Radiation-Induces Attenuation at InfraRed
Wavelengths for P-Doped, Ge-Doped and Pure Silica-Core
Optical Fibers
850 nm
J. Ye, Dept. of
1300 nm
Demo Link and LOC report at UCSC
17
Preliminary tests
Gamma (Co-60) and Proton (230 MeV) tests
•
•
•
•
Fiber under proton test
J. Ye, Dept. of
Demo Link and LOC report at UCSC
Infinicor SX+
50/250m/1.6mm MM.
10G fiber from Corning.
Germanium doped.
Very small light loss at
low flux (dose rate).
Big loss at high flux but
anneals very quickly
(within 1 hour) back.
18
Preliminary tests
Co-60 at BNL, dose rate: 30 krad/hr.
Fiber: Corning Infinicor SX+ 50/125
MM fiber, 45 m under irradiation.
Total RIA: 0.04 dB/m after 1.4 Mrad.
Annealing effects observed.
More annealing results will follow
once we get our equipment back to
SMU.
Run
#
Dose (krad)
Accumulated
dose (krad)
fibre RIA
(dB)
Accumulated
RIA (dB)
Ref. fiber
(dB)
Accumulated
ref. fiber (dB)
1
133.00
133.00
-1.05
-1.05
-0.10
-0.10
2
700.00
833.00
-0.79
-1.84
0.01
-0.09
3
573.00
1405.00
-0.07
-1.91
0.00
-0.09
J. Ye, Dept. of
Demo Link and LOC report at UCSC
19
Conclusion on fiber (preliminary)
Corning Infinicor SX+ 50/125 MM fibers from
different production batches, packaging companies
were irradiated with gamma (Co-60) and proton
(230 MeV). More tests with higher dose rate and
total dose are to be carried out by Oxford group to
reach 50 Mrads.
Careful data analysis, especially on annealing
effects, needs to be carried out.
More tests, especially neutron or proton may be
needed to study possible NIEL effect, or to confirm
that the lack of it.
Preliminary results indicate that this fiber may be
suitable for ID upgrade.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
20
Summary
The GOL based demo link will be constructed and put to use in
Sept./Oct. time frame. This demo link will be used to perform
many system level studies on the Giga-bit optical link. Demo
links based on LOC or GBTx will follow. This exercise will lead to
a baseline design for the upgrade of optical readout.
The LOC2 design is on track for a user chip in 2009. It is hopeful
to achieve 5 Gbps speed. We need to work more closely with
upstream ASIC developers to define the interface.
R&D work in the frame of Versatile Link project is on-going to
identify components for a rad-tol optical link. At least one type of
fiber (Corning Infinicor SX+ 50/125 MM ) has been tested with
gamma and proton and the preliminary results indicate that this
fiber may be suitable for the ID upgrade.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
21
Backup slides
J. Ye, Dept. of
Demo Link and LOC report at UCSC
22
Block diagram
Cntrl
config
Clk_ref
PLL
+ clks
Data
16 bit Input register
LVDS to LVCMOS
16 LVDS
27-1 PRBS
2:1 MUX
to 8 bit
Latch
8B/10B
Comma
10 bit
2:1 MUX
Even bits shift register
Odd bits shift register
MUX
Input
Cntrl/Config
CML
driver
Serial output to
Versatile Link
Output
The preliminary LOC2 block diagram
Parallel
data
LOC
VL
fiber
Parallel
data
GBTx
VL
fiber
System implementation
J. Ye, Dept. of
Demo Link and LOC report at UCSC
23
Design considerations
Implement measures to address lessons learned
from LOC1: period jitter from the serializer; control
PLL RJ; output driver quality.
Conservative circuit units (static D-flip-flop, majority
voting) are used to reduce SEE cross section.
We would like to take advantage of the Versatile
Link development, and move the optical interface
from LOC to VL.
LOC2 should have the basic but complete functions
as a “user” chip so that groups outside of SMU can
use it to implement in their systems.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
24
Key features
A Serializer at 3.2 Gbps, goal: push it up to 5 Gbps (ref. GBTx
at 5 Gbps);
Differential data input, 16 bit LVDS;
Differential parallel data rate reference clock input;
Data sampling at the rising or falling edge of the reference clock;
Internal 27-1 PRBS;
Differential electrical output (CML), to be coupled to the
Versatile Link input;
Compatible with commercial GBE receivers (8B/10B encoder).
The receiver can be FPGA based. This will greatly help in the
demo-link and the ROD designs;
Single 2.5 voltage power supply.
J. Ye, Dept. of
Demo Link and LOC report at UCSC
25