Interstate 405 Improvement Project Schedule and Key Milestones
Download
Report
Transcript Interstate 405 Improvement Project Schedule and Key Milestones
Orange County Transportation Authority
Measure M2 M2020 Update
and
Select Project Highlights
Orange County Business Council
Infrastructure Committee
December 9, 2014
M2020 Plan
Accelerates M2 programs and projects between
now and 2020
o
o
o
o
Complete/award construction for 14 freeway
projects, environmentally clear remaining nine
Invest nearly $1.2 billion of funding for local
street and road improvements
Increase Metrolink passenger rail capacity,
expand rail options including fixed guideways
Continues investment in environmental
programs
2
M2020 Plan - Major Projects
3
Santa Ana/Garden Grove Streetcar
M2 Project S – Transit Extensions to Metrolink
4
SA/GG Streetcar Next Steps
• Project Management Consultant Services – Proposals due December 2, 2014
• Design Request for Proposals - 2nd Quarter 2015
Type of Service
Scope of Activities
Anticipated Schedule for ReleaseDuration
Project Management/ Construction
Management Consultant
Oversee engineering and construction
activities on behalf of Orange County
Transportation Authority
2014-2019
Design/Engineering
Through Final Design, including Rightof-Way
2015-2017
Construction
Capital, vehicles, utilities
2017-2019
Operations and Maintenance
Operations and Maintenance
Contract(s)
2018
5
Status of Continued Project Work
Caltrans Project Preferred Alternative
(PA) is Alternative 3 – Addition of
General Purpose (GP) Lane and Highoccupancy Toll (HOT) Lane
OCTA will build Phase 1 of the PA which
is the single GP lane designated in
Measure M2 as Project K
Caltrans will implement Phase 2 of the
PA which is the HOT lane, including the
SR-73/I-405 HOT connector
6
Phase 1 Improvement
Approximately 14 mile corridor
Rebuilds 17 overcrossing bridges to
county “Master Plan” standards
Improves on/off ramps for access
Adds bike lanes and sidewalks to arterial
crossings
Maintains or improves existing
soundwalls
Constructs additional soundwalls
$1.3 Billion (total project cost)
7
Environmental and D-B Procurement
Description
Caltrans PA Recommendation
Signed Final Environmental Document
Notice of Determination/Record of Decision
Issue D-B Industry Outreach Letter
Issue D-B RFQ
Issue D-B Draft RFP
Issue D-B RFP
Current Schedule
July 2014
February 2015
May 2015
October 2014
November 2014
March 2015
August 2015
D-B Award
April 2016
D-B Notice to Proceed
June 2016
Design/Construction
2016 to 2021
8