Regional Policy
Download
Report
Transcript Regional Policy
Ex post evaluation
2007-2014 of ERDF and CF:
State of play
DG Regional and Urban Policy
Brussels, 15 January 2015
1
Regional
Cohesion
Policy
Policy
Overview of work packages
No. Work package
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Responsible in REGIO evaluation unit
Data collection and quality assessment
Daniele Vidoni
Synthesis
Kai Stryczynski
Support to SMEs – Increasing Research and Innovation in SMEs Marielle Riché
and SME development
Financial instruments for enterprise support
Daniel Mouqué
Support to Large Enterprises
Daniel Mouqué
Transport
Jan-Marek Ziolkowski
Environment
Anette Holtmann
Modelling the effects of transport projects
Postponed
Energy efficiency
Patty Simou
Culture and Tourism
Samuele Dossi
Urban development and Social Infrastructures
Samuele Dossi
European Territorial Cooperation
David Alba
Delivery system (covers also the ESF)
Ivanka Lakova
Geography of expenditure
Alida Staicu
Effect on GDP etc
Modelling: QUEST, Rhomolo,
Daniel Mouqué
Regional Discontinuity Design,
Daniele Vidoni
Propensity Score Matching
Kai Stryczynski
Communication
2015
Regional
Policy
WP 1: Synthesis
• Two interim deliverables:
• - Macroeconomic situation
• - Regional developments
• Ultimate use for synthesis report in 2016
3
Regional
Policy
WP 2: Support to SME: research &
Innovation and SME development
• Started July 2014, inception report accepted by Steering
group last September
• Consultant: CSIL (IT), CSES (UK), ZEW (DE)
• First intermediate report to be examined on 23 January:
-
Establish the main instruments funded in 50 programmes: context,
funding, logic of intervention, beneficiary SMEs, effectiveness
Pilot case study: Puglia + proposal for 7 other case studies
Proposal for 7 policy instruments (in view of 3 theorie-based
evaluations)
In parallel: literature review (rationale for public support, evidence)
4
Regional
Policy
WP 2: Support to SME: research &
Innovation and SME development
Next steps:
• April: seminar on case studies' findings (MA, SMEs &
external experts)
• May: 8 case studies
• October: 3 theory-based impact evaluations on 3 policy
instruments
• January 2016: final report
Contact: Marielle Riché
5
Regional
Policy
WP 3: Financial instruments
• Equity, loan and guarantee instruments – support to
enterprise only
• First draft stocktaking report being finalised. Covers 12 MSs
which account for 92% of support (BE, CZ, DK, DE, ES, FR,
HU, IT, LT, PL, PO, UK)
• Will select 9 representative case study OPs to examine initial
performance, using theory of change evaluation.
• Seminar in July, final report in November.
6
Regional
Policy
WP 4: Support to large enterprises
• Large enterprises as defined in EU law
• First draft stocktaking report being finalised. Covers 8 MSs
which account for 75% of support (PO, DE, PT, ES, HU, IT,
CZ, AT)
• Will select 8 representative case study OPs to examine initial
performance, using theory of change evaluation
• Seminar in July, final report in November.
7
Regional
Policy
WP 5: Transport
Consultant – AECOM + KPMG Italy
• Kick-off in December 2014
• 1st Interim report – April 2015 (cohesion policy contribution +
review of financial analysis)
• 2nd Interim report – August 2015 (10 major project case
studies + 6 MS case studies + draft catalogue of challenges)
• Seminar – October 2015 (to discuss and develop findings
from the case studies)
• Final report – December, 2015 (draft in November 2015)
8
Regional
Policy
WP 6: Environment
Analysis of Cohesion Policy contribution in 2007-2013 for environmental
infrastructure projects (drinking water, wastewater and waste).
Consultant – COWI
• Kick-off in December 2014 and list of 40 major projects provided by the
Commission
• Inception report: 28 January 2015 (detailed methodology, selection of 20
projects for task 2)
• Interim report by mid-March (cohesion policy contribution, review of
financial analysis for 20 major projects, verifying the correctness of
assumptions for operational projects and proposal for 2 pilot case studies)
• All ten case studies by mid-August and catalogue of challenges by midSeptember
• Seminar (to discuss and verify findings) in October 2015
• Final Report in December 2015
9
Regional
Policy
WP 8: Energy Efficiency
Consultant – Ramboll / Institute for European Environmental Policy
•
•
•
•
•
•
Kick-off : 13 November 2014
Inception report: 09.01.2015 (detailed methodology, proposal for case
study pilot)
Interim report (Literature review / Review of ERDF/CF measures, finalised
pilot case study) by mid April 2015
Remaining case studies to be submitted as they are completed, the latest
by mid June 2015
Seminar (to discuss and verify findings) in June 2015
Final Report by the end of August 2015
10
Regional
Policy
WP 9: Culture and Tourism
Consultant – IRS, CSIL BOP Consulting
•
•
•
•
•
•
•
Kick-off : 21 August 2014
Inception report: December 2014 (detailed methodology, proposal for
Survey to Managing Authorities)
Interim report (Literature review / Data analysis and sampling / survey of
selected programmes) by January 2015
Pilot Case study (Regional Strategy) and 2 min—case studies (project
level) by February 2015
Six case studies and 12 mini-case studies, by May 2015
Seminar (to discuss and verify findings) in September 2015
Final Report by the end of October 2015
11
Regional
Policy
WP 10: Urban Development and
Social Infrastructures
Consultant – METIS
•
•
•
•
•
Kick-off : November 2014
Inception report: December 2014 (detailed methodology, proposal for
Survey to projects Implementation Bodies)
Interim report (Distribution of Investments and reported outputs /
Analysis of OPs and AIRs) by April 2015
Survey to project Implementation Bodies
Final Report by the end of September 2015
12
Regional
Policy
WP 11: ETC
Consultant – ADE
•
•
•
•
•
Kick-off : 8 January 2014
Inception report: 12 February 2015 (detailed methodology, proposal for
case study pilot)
Interim report (Completion of Task 1 and case study selection) by mid
May 2015
2nd Interim report (Completion of Task 2-4) by mid November 2015
Seminar (to discuss and verify findings) in mid December 2015
Final Report mid March 2016
•
Contact: David Alba
•
13
Regional
Policy
WP 12: Delivery Systems (1/2)
• Delivery System is defined as:
programming, project selection, compliance with EU & national
law, financial man't & control, monitoring, evaluation, reporting
• Main focus : the OP level, how well (i) it translates strategic guidelines
into results delivered by the policy and (ii) in terms of:
accountability, regularity, results, timeliness, responsiveness, cost
• TA's performance for reinforcing administrative capacity is assessed
•
Data and evidence collection through: structured interviews, websurvey, case studies.
14
Regional
Policy
WP 12: Delivery Systems (2/2)
Consultant – KPMG (DE) / Prognos
•
•
•
•
•
•
•
•
A 16-months contract
Kick-off on 18 November 2014
Inception report submitted 18 December 2014 (in progress)
1st Interim report 4 March 2015
2nd Interim report by June 2015
3rd and 4th Interim reports by mid-September and mid-October 2015, respectively
Draft final report by January 2016
Final Report by the end March 2016
•
Contact: Ivanka Lakova
15
Regional
Policy
WP 13: Geography of expenditure
Consultant – The Vienna Institute for International Economic Studies &
Ismeri Europa
•
•
•
•
•
•
•
8 months contract
Kick-off on 21 January 2015
Inception report by the end of January 2015 (detailed methodology for each task)
1st Interim report (Database & proposed methodology for estimates) by the end of
April 2015
2nd Interim report (Database & maps & user's manual) by the end of June 2015
Draft final report by the end of July 2015 (2nd Interim Report + additional sections on
tasks 5&6)
Final Report by the end of August 2015
16
Regional
Policy
WP 14c / 14d:
Effect on GDP etc
• Two low value contracts with econometric approaches signed
• - regression discontinuity design (G Pellegrini)
• - Propensity score matching (D Bondonio)
• Questions:
• - Effect of SF on GDP and other variables on a regional level
• - Attempt to capture effect of different aid intensity on regions
Regional
Policy
Gentle reminder:
Have you finished new evaluations?
• - Finished in 2013 or 2014,
• - Please send them to us: [email protected]
• - Title and weblink is enough!
• Use:
• - for ex post evaluation 2007 – 2013
• - library of evaluations on INFOREGIO
18
Regional
Policy