Operational experience and field tests on islanding events caused
Download
Report
Transcript Operational experience and field tests on islanding events caused
Frankfurt (Germany), 6-9 June 2011
Operational experience and field tests on
islanding events caused by large
photovoltaic plants
PV in Spain:
Basically Large plants connected to MV or HV
Mainly in rural areas (generation exceeds consumption)
3,000 MW in 2007 and 2008
Operational experience:
Islanding behaviour during network maintenance or faults
Overvoltages in PV plants, causing damages (CIRED 2009)
Field tests in large PV plants connected to Iberdrola’s
networks, to reproduce both cases.
F.J. Pazos – Spain – Session 4 – Paper 0184
Frankfurt (Germany), 6-9 June 2011
Islanding events
Experience:
Dangerous work conditions
Impossibility of network operation or maintenance
Failure of network automation
Damaged inverters
F.J. Pazos – Spain – Session 4 – Paper 0184
Frankfurt (Germany), 6-9 June 2011
Dangerous work conditions
Failure of anti-islanding
protections during
maintenance of a MV/LV
substation
Safety golden rules:
1. Isolate working area
2. Lock isolation
3. Voltage verification…
Increased risk: electric arc
across a switch (2) not
designed for load breaking.
F.J. Pazos – Spain – Session 4 – Paper 0184
132/20 KV SUBSTATION
1. Open circuit breaker
2. Open and lock switch
PV 1
PV 2
3. Voltage
verification
in the
working
area
Frankfurt (Germany), 6-9 June 2011
Impossibility of network operation or maintenance
Solution for dangerous work conditions:
Additional voltage absence verification, before MV
switching.
Consequence:
Maintenance works could not be carried out
No access to switching devices within PV plants
Dispersed PV plants, several km away from the
working area
F.J. Pazos – Spain – Session 4 – Paper 0184
Frankfurt (Germany), 6-9 June 2011
Failure of network automation
Breakers with synchronism or voltage absence
verification cannot close
Voltage in the islanding network looses
synchronism with the network
Normal service cannot be restored
Further actions to identify and disconnect voltage
source.
F.J. Pazos – Spain – Session 4 – Paper 0184
Frankfurt (Germany), 6-9 June 2011
Damaged inverters
Breakers without voltage verification
Frequent case:
Breakers will close although PV is still generating
Overcurrent, harmful for inverter IGBT.
Some cases of fatal damages, affecting up to 100% of
the inverters of a large PV plant.
Earth fault in MV feeder (difficult to detect in LV)
Followed by fast reclosing (from 0.4 to a few sec.)
Solution:
Extremely fast internal overcurrent protection in
inverters.
F.J. Pazos – Spain – Session 4 – Paper 0184
Frankfurt (Germany), 6-9 June 2011
Voltage & frequency
during islanding
Field tests
ISLANDING
F.J. Pazos – Spain – Session 4 – Paper 0184
Islanding events have to do
with the interaction between
inverters and loads.
The system tends to find
a stable point, mainly by
voltage adjustment (not
so much by frequency)
Possible with some
generation-consumption
imbalance (10%)
They can last long time.
Frankfurt (Germany), 6-9 June 2011
Field tests
Failure of anti-islanding systems due to
interaction between several inverters
Actual field situation is not represented by
laboratory tests.
Failures with several inverters of the same brand
Failures with several inverters of different brands
5 inverter brands tested
From several countries
With different anti-islanding methods (passive and
active)
F.J. Pazos – Spain – Session 4 – Paper 0184
Frankfurt (Germany), 6-9 June 2011
Solution: COORDINATION
Coordination between protections:
Included in the inverters (active or passive methods)
Protections of the point of coupling (relays)
Communication based protections
Fast: intertripping
Slow: based on telecontrol
New developments
Coordination of requirements from Transmission and
Distribution System Operators
TSO: delayed or insensitive trip to prevent instability
DSO: fast and certain trip, to prevent damages or
affecting power quality
F.J. Pazos – Spain – Session 4 – Paper 0184
Frankfurt (Germany), 6-9 June 2011
Solution: COORDINATION
Coordination between inverter manufacturers (standards)
Improve anti-islanding tests
In more real conditions (several inverters in parallel)
DC power
source
(PV)
DC power
source
(PV)
VDC
PDC/2
VDC
PDC/2
EUT
(inverter)
1
Similar
micro gen
erator
F.J. Pazos – Spain – Session 4 – Paper 0184
Frankfurt (Germany), 6-9 June 2011
Proposal: Segmentation
DER connected to MV/HV, give priority to system stability
FRT capabilities
Passive protections (internal or at the point of coupling)
Communication based protections.
In general, telecontrol for safe maintenance works
Occasionally: intertripping.
DER connected to LV: give priority to safety and lower
communication requirements
Telecontrol by means of smart meters with internal switch
With FRT
Fast active and multi-inverter methods when telecontrol is
not available.
Without FRT
F.J. Pazos – Spain – Session 4 – Paper 0184
Frankfurt (Germany), 6-9 June 2011
Thank you
for your attention
F.J. Pazos – Spain – Session 4 – Paper 0184