Transcript Slide 1

Field Trial of Power
Electronics LV Power
Regulator in a Utility System
April 20, 2015
B. A. (Brian) McMillan, P. Eng.
Vice-President – Distribution Electrical Systems
Greater Sudbury Hydro
Mr. Robert McFetridge
Director of technical Sales
Gridco Systems
Who is Greater Sudbury Hydro and Why is the Grid
Modernization Important to Us
Who Is GSHI
Municipally owned Local Distribution Company (LDC)
47,500 Customers.
No Generation, No Transmission
Why Is the Smart Grid Important to Us?
Winter peak 200 MW …. Summer peak 175 MW
Existing
11 MW of combined heat and power generation
1.6 MW of landfill gas generation
Applications
Renewable Energy Standard Offer Program - 120 MW of wind and 20 MW solar
Feed in Tariff – 35.8 MW of solar farms and 2 MW of small rooftops.
Total applications and builds to date 190.4 MW
Typical load on a sunny, windy May Saturday afternoon – 80 to 90 MW. The
potential exists for more than 100% renewable generation penetration.
Constraints - Boundary Conditions
Used with permission of EPRI – thanks to Jeff Smith
Constraints - Boundary Conditions
Used with permission of EPRI – thanks to Jeff Smith
Constraints – How Will The Primary Problems Appear?
Used with permission of EPRI – thanks to Jeff Smith
Constraints – How Will The Secondary Problems Appear?
Used with permission of EPRI – thanks to Jeff Smith
Increasing PV Penetration and the “Missing Regulation
Zone”
Managing Voltage – What’s in the Distribution Engineers Toolbox?
MV Capacitor, Voltage Regulator
Manage Z - Conductor size...
Manage Z - Conductor length...
Reduce I - Load splitting by three phasing...
MITIGATION -- Secondary Voltage Control
MITIGATION – Power Factor Control and Harmonics Control
Power Factor -- Two Control Modes
Set the desired load side power factor…
Set up to 5 Kvars of capacitive or inductive reactive power
Harmonics Control -- Two Control Actions
Enable Load Side Voltage Harmonic control or…
Enable Source Side Current Harmonic control or..
Both
MITIGATION – Balancing Available IPR Resources
Limited Power Allocation is Required When Enabling Functions
Voltage Control
Power Factor Correction
Harmonics Control
Demonstration Project -- Feeder Selection and
Deployment Description
Site selected with high PV penetration
and readily accessible OH pole location.
Customers seeing 252 volts before
deployment. NR_Canada participation!
LV Power Regulator install at Greater Sudbury Hydro Inc.
Simple installation using standard techniques
OH LV Power Regulator (Close-up)
SCADA Integration
XFMR
Side
IPR-50
Load
Side
GSH IPR-50 Voltage Regulation Performance.
24 Hours After Installation, 30s Snapshots of RMS Values
Unit installed
and powered
up in BYPASS
mode
Unit
switched
into ACTIVE
mode with
240V load
voltage set
point
Load Voltage being
precisely regulated
to 240V set point
during both forward
and reverse power
flow
Load Voltage set
point changed to
235V and then back
to 240V
Unit toggled into
BYPASS, ACTIVE and
back to BYPASS
mode
Unit left in BYPASS
mode
Source/Load
voltage at +5% of
nominal
Source voltage above
+5% of nominal
Intermittent
Reverse power flow
(~ 15 kW)
Reverse power flow
(~ 20 kW)
Issues? – It’s a Demo!
When is less than 50 kVA not less than 50 kVA?
Voltage Regulation near zero load crossing.
Harmonics “problem”, high THD, at low loads.
Summary
The IPR is delivering stable voltage regulation for both forward
and reverse power flow
Successful SCADA integration is providing new visibility and
control at Grid Edge
PF regulation provides VAR support local to loads
This new technology provides a new tool for GSH Distribution
Engineering to achieve key Smart Grid objectives
Thank you for Your Kind Attention!
Mr. Robert McFetridge
Director of Technical Sales
Gridco Systems
Cell: 919-901-9940
E-mail: [email protected]
Brian McMillan, P. Eng.,
Vice-President Distribution Electrical Systems
Greater Sudbury Hydro Inc.
Cell: 705-688-6286
E-mail: [email protected]