Open Pit Planning and Design - Supplemental Teaching Resources
Download
Report
Transcript Open Pit Planning and Design - Supplemental Teaching Resources
Open Pit Planning and Design
The Standard Approach for Open
Pit
©2007 Dr. B. C. Paul
The Ajo Open Pit in Arizona
They mined around the
barren core
Lacks Clear Steps and Has A Lot of
Interaction – Computers Almost a
Necessity
In general need to know
you have a large ore
reserve close enough to
the surface to be open pit
mined
Generally comes from
geologic data
– Open pit designs normally
represent ore reserves and
geology as a block model
Slice and dice the ore
reserve up into small blocks
that sit end to end and on
top of each other
Building Block Models
Start by specifying block dimensions
Look at drill and sampling data for how
continuous the mineralization is
– Use computer routines to estimate the ore
grade of the blocks using samples
– One of the most popular is Kriging (also
polygonal and IDS)
Most going to study how interpolation is done in this
class. (You’ll be given a block model to work with)
Determine the Minable Ore Reserve
Assume economics for material removal
Look at geology for how steep the pit slopes can
stand without sliding in
Have the computer analyze the largest set of
blocks that can be removed without taking stuff
that looses money
– This set measures the size of the pit that can ultimately
be mined (called the Ultimate Pit)
Too complex to visualize
– Done with either a Floating Cone Miner or LearchGrossman computer routine
Sequencing
Considering the need to work from top down
and the grade of the ore
– Calculate a series starting with richest ore and
working down in grade over time
Usually accomplished with modified
computer routines
Getting best ore early in life greatly
improves the NPV of the project
Developing a Practical Layout
With a series of nested pit shells as a guide
design a set of pits that follows the guides
but has benches, and roads required for
practical mining.
Pick Equipment Fleets
Work on intermediate and short term
equipment schedules to execute the over-all
plan