SEM Weekly Market Call
Download
Report
Transcript SEM Weekly Market Call
Single Entry Model (SEM)
Weekly Market Call
August 31, 2009
Matt Mereness
http://nodal.ercot.com
1
Antitrust Admonition
ANTITRUST ADMONITION
ERCOT strictly prohibits Market Participants and their employees who are
participating in ERCOT activities from using their participation in ERCOT activities
as a forum for engaging in practices or communications that violate the antitrust
laws. The ERCOT Board has approved guidelines for members of ERCOT
Committees, Subcommittees and Working Groups to be reviewed and followed by
each Market Participant attending ERCOT meetings. If you have not received a
copy of these Guidelines, copies are available at the Client Relations desk. Please
remember your ongoing obligation to comply with all applicable laws, including the
antitrust laws.
DISCLAIMER
All presentations and materials submitted by Market Participants or any other Entity
to ERCOT staff for this meeting are received and posted with the acknowledgement
that the information will be considered public in accordance with the ERCOT
Websites Content Management Operating Procedure.
http://nodal.ercot.com
2
SEM Weekly Market Call Agenda
• Antitrust Admonition
• SEM Go-Live Q&A
• Reference only– SEM Go-Live Update
– Market Testing Update
– Readiness Dashboards
– SEM Go-Live Criteria and Approval
– FAQ/ Open Issues
– Appendix/Supporting Info
–
–
–
–
–
What is SEM?
Go-Live timeline and activities
Training overview and sign-up
Readiness metrics related to training and testing
Communication mailbox and SEM Market Call Schedule
http://nodal.ercot.com
3
Day 1
•
User access questions
– USA or MP can re-set passwords
• ERCOT on the phone 512.248.3800 (opt 3)
– Confirming user set-up
• All user requests received by noon Friday were to be set-up
•
Connectivity
– Some user reporting when using https://gateway.ercot.com they are redirected to old URL and prompted for SecureID
• ERCOT loaded production gateway to different site
• If MP’s network server DNS has not refreshed, it is going to old IP address resolution
• Production can be accessed, but old URL requires FOB key until DNS is refreshed
•
Summary for first 5 hours of SEM
– Averaging 8-10 market users
– No statistics as to whether model has been downloaded
http://nodal.ercot.com
4
SEM Go-Live Update
•
What is ERCOT doing this week?
– Completed performance and tuning
– Implementing final configurations
– Roll-out of TML Links
– Loading model into production systems
•
Training
– Reminder of one make-up class scheduled so far – Sept 29-Oct 1
– Sign up using LMS - https://www.ercottraining.com/lms/default.asp
•
Communications during the week –
– Regular call today
– Special call on SEM Go-Live –
• Monday 1pm, ERCOT will host WebEx to troubleshoot user access issues
• Voluntary call (no roll call)
– Regular call next Thursday, Sept 3
http://nodal.ercot.com
5
Market Testing Update
Test Sandbox Environment Update:
•
Will be taken offline tonight
•
Remain off-line during at least the first week of production
•
Test/Sandbox system will come back for training later in September
– Final date TBD
http://nodal.ercot.com
6
FAQ- Access questions
•
Currently production system is not online and available to TSPs (early deployment of links,
but full function on 8/31/09 an 8am
•
Final list of Production Users being set-up tomorrow afternoon
– Any new user requests needed by noon Friday, Aug 28
•
Reminder- TSP USA initiates creation of NMMS account. User will receive a new user name
and initial password. Please use caution when typing the new password (or removing the
trailing space when pasting.) You will be prompted to change your password. If there are
any issues with this initial log in, you will receive an error message. At this point, you must
request a password reset.
– The password can be reset by:
1) Emailing the ERCOT Helpdesk, [email protected] or calling at 248-6800 option 3.
2) Or contacting your USA – they can reset your password. To reset: in MPIM, select modify to
the individual account. There is a check box to reset password. Select the box and email will
be sent with new password.
•
USAs were contacted directly with instructions on how to assign the roles for SEM Go-Live
• Two roles are applicable for NMMS:
– NMMS Remote Users (access to production environment to submit NOMCRs)
– NMMS_SEMFILE_DOCS (to allow the ability for certain TSP users to
download the full network CIM file)
http://nodal.ercot.com
7
NMMS Access on Aug 31, 2009
1) NOMCRs / SAMRs
(Report Explorer)
TSP
TML
2) CIM network file
download capability
3) NMMS Production
(also SOTE / MOTE)
(links to Citrix Gateway)
Citrix
Gateway
http://nodal.ercot.com
NMMS Production
(also SOTE / MOTE)
8
Each TSP Company Folder
will contain all
Network Model Changes
Daily zip files
NMMS Access on Aug 31, 2009
https://tml.ercot.com
http://nodal.ercot.com
9
Roll-call and Q&A
•
Roll-call
•
Production environment URL
– URL- https://gateway.ercot.com
•
Important Reminder(s):
– Go-Live Aug 31 will be 8am
– Production access granted from MP USAs
– Production issues should be sent to [email protected] and [email protected]
– Re-set password can come from HelpDesk 512.248.6800 or your USA
– Make up training class
•
Enroll at https://www.ercottraining.com/lms/default.asp
– Populated CIM file request (8/31/09 Go-Live Model)
•
Posted in TML Production 8/31
– Special call on SEM Go-Live –
•
•
Monday 1pm, ERCOT will host WebEx to troubleshoot user access issues
Voluntary call (no roll call)
•
Questions and Answers
•
Next Weekly Market Call- Sep 3, 2009
http://nodal.ercot.com
10
• Appendix/Supporting Info
–
–
–
–
–
What is SEM?
Readiness Criteria
Go-Live timeline and activities
Training overview and sign-up
Dates/ methods to test submissions of NOMCRs
http://nodal.ercot.com
11
SEM Go-Live Overview
•
Single Entry Model (SEM) Go-Live is the switchover on Aug 31, 2009 for
TSP submissions of network operations model change requests
– from “Service Request” submissions via TML
– to “NOMCR” submissions via the NMMS
• System of record for model changes becomes NOMCRs on 8/31//09
• System of record for Network operations Model for reliability and dispatch remains
Zonal/Genesys system until Dec 2010
TSP
Current Activity
TSP
Aug 31, 2009
Submit Modeling
Change via Service Request
Submit Modeling Change via
NOMCR/NMMS Tool
(includes ICCP)
ERCOT Uploads
Svc Request
into Zonal
Genesys Model
Full
Copy
ERCOT Copies/Converts
Zonal Model “seed”
Into Nodal
NMMS Model
Data Consistency Checks are run to
ensure model synchronization/fidelity
http://nodal.ercot.com
ERCOT Incrementally
ERCOT uploads
Converts NOMCR
NOMCR
Incr.
Into Svc Req
Into Nodal
NOMCR
Uploads into Zonal
NMMS Model to
Genesys Model
support nodal testing
Periodic checks are run to
ensure model synchronization/fidelity
12
Current Network Operations Model Maintenance for TSPs
TSP
Submits Service
Request to
Change Model
ERCOT Zonal EMMS Model
(system of record through 12/1/2010)
Periodic full copy and conversion of model
(zonal seed used for nodal systems)
ERCOT Nodal NMMS Model
(nodal testing model- CIM file for EMS/MMS/etc)
13
After 8/31/2009: SEM Go-Live
Network Operations Model Maintenance for TSP
Nodal Go-Live
12/1/2010
ERCOT Zonal EMMS Model
(system of record through 12/1/2010)
ERCOT enters NOMCRs into zonal model
TSP
Submits Model
Change Request
(NOMCR)
ERCOT Nodal NMMS Model
(nodal testing model- CIM file for EMS/MMS/etc)
ERCOT runs consistency checks to ensure
models are aligned and maintained
14
NMMS
Model
System of
Record
Network Operations Model Maintenance for Resource & QSE
(today and post 8/31/09)
Nodal Go-Live
12/1/2010
ERCOT Zonal EMMS Model
(system of record through 12/1/2010)
ERCOT enters into zonal model
ERCOT Nodal NMMS Model
(nodal testing model- CIM file for EMS/MMS/etc)
QSE
Submits ICCP Change
via Service Request
RE
Submits RARF
(Resource Asset Reg Form)
via Service Request
ERCOT process
15
NMMS
Model
System of
Record
SEM Go-Live Market Engagement Dashboard (as of 8/27/2009)
Notes- ERCOT working one TSP to catch-up on final testing/training
- TSP has signed up for Sep 29th make-up training
- ERCOT will support this TSP (and any other TSP) with assistance in submission of NOMCRs
http://nodal.ercot.com
16
Overall SEM Go-Live ERCOT/Market Criteria Dashboard
Summary of Criteria from TAC-approved SEM Go-Live Procedure
(http://nodal.ercot.com/readiness/golive/index.html )
Go-Live timeline and activities (continued)
•
Communication
– May 6th ERCOT began TSP outreach through Wholesale Client Services
• TDSP/TO associations sent to 23 TOs
• Solicit training headcount from TOs (pre and post Go-Live)
• Good response from TOs
http://nodal.ercot.com
18
Go-Live timeline and activities (continued)
•
Communication and Calendar
– May 15- Market Notice sent for SEM Kick-off call to occur
– May 28- SEM Kick-off WebEx 10:00-11:30am
•
•
•
•
•
Go-Live timelines and activities for June - August 2009
Training overview and sign-up
Dates and access methods to test submissions of NOMCRs
Readiness metrics related to training and testing
Communications mailbox and SEM market call schedule
– June 4- Start weekly Thursday SEM Calls at 2-3pm (through go-live/August)
•
•
•
•
•
Company attendance is recorded
ERCOT provide updates on testing and training
Highlight issues or Frequently Asked Questions
Open Question/Answer session for TSPs
Meetings will be posted on ERCOT calendar at http://www.ercot.com/committees/nodal/eds/
– June 8- Testing environment available to TSPs (through Aug 10)
– June 22- Weekly classroom training for 6-weeks (through July 30)
http://nodal.ercot.com
19
Training Overview and Sign-Up (continued)
• Classroom schedule for the 3-day class
•
•
•
One class per week for 6 weeks
Start 1pm Tuesday / End noon Thursday
• Trainees can stay in Lab Thursday afternoon for Q&A
If schedule fills up, ERCOT will shorten class to 2-days for the overbooked weeks
• June 23-25, June 30- July 2
• July 7- 9, 14-16, 21-23, 28-30
• Next 4 slides show summary of training format and equipment
•
Full training outline in Appendix (no change from last month)
• Note that testing/training will only include Level 1 Validation
•
•
•
•
•
Level 1 – Automatic by the system upon submitting.
Level 2 – Visual by the N/W Model Coordinator
Level 3 – Power flow run on the one NOMCR.
Level 4 – Power flow run on all NOMCRs for that day.
Level 5 – Power flow run on the AREVA system.
http://nodal.ercot.com
20
Training (continued)
Training (continued)
Training (continued)
Training (continued)
Training Overview and Sign-Up (continued)
• Sign-up for access to test environment starts today
•
•
•
System access begins June 8th
Email request to [email protected]
Test environment requires a valid digital certificate (production or nodaltest)
- Digital certificates are to be coordinate with your company’s USA
- Include in email:
Employee NameTSP/Company NameDUNSEmail addressAlternate/Centralized Email address for status changePrimary phoneAlternate phone-
http://nodal.ercot.com
25
Open Issues / Responses
•
How can I configure Citrix to allow me to export/import CIM files?
Steps:
1) While Citrix and the application are open, there should be a Citrix icon in your
taskbar (the ‘Citrix Connection Center’)
2) Double click the icon
3) Click ‘File Security’
4) Click ‘Full Access’
http://nodal.ercot.com
26
Go-Live timeline and activities (continued)
– Transition periods:
• June 1- Aug 30, 2009 (objective to minimize SvcReq during this period)
– Submit changes as far in advance as possible
– No equipment name changes (defer until after SEM Go-Live 8/31/09)
• Aug 15-30, 2009
– Two weeks no submissions, except for emergency changes
• Aug 31, 2009 - Feb 2010 (NOMCRs for any/all network changes)
– After 8/31/09 TSPs will work to validate the network model and align
to their in-house systems
– Initially the NOMCR timeline will align with zonal timeline
» 30-day lead-time, compliant with current zonal database schedule
» Status is tracked and communicated via system emails
– Any SRs that did not go into zonal production will be converted by
ERCOT to NOMCRs for verification/submission by TSPs in Sept
– In 2010 TSPs gradually transition to NodalProtocols(3.10) 90-day
timeline submission requirements
http://nodal.ercot.com
27