Commissioning STATUS
Download
Report
Transcript Commissioning STATUS
Virgo Commissioning progress
ILIAS, Nov 13th 2006
Matteo Barsuglia
on behalf of the Commissioning Team
1
Outline
July-August
Main problem: thermal lensing
Main activities:
Lock acquisition improvements & automatic alignment
Noise hunting: recover good sensitivity after the shutdown
Thermal lensing
Data takings: WSR-1 (Sept 8th-11th)
Upgrades (September-October)
Faraday isolation optimization
Acoustic isolation laser laboratory
Matching improvements
Actuators noise reduction
Detection Brewster replacement
Frequency noise see Matt’s talk
WSR-5 (last week-end)
Future steps
2
Thermal lensing
Still the main concern (Lock acquisition long
and more difficult / Noise couplings?)
20 min
Why?
Absorption in the input mirrors seems
to be part of the problem (x4-x10
with respect to the design)
Also thermal lensing in the Faraday?
Dynamics of the fields inside the
interferometer not understood
Simulation ongoing (Finesse, darkF,
Matlab)
Diagnostics through optical spectrum
analyzer
Phase camera in a few months
Thermal compensation in > 1 year
3
Thermal lensing: last week results/1
4
Thermal sensing: last week results/2
20 min
6.7 W input: old matching
5
Thermal sensing: last week results/2
6.7 W input
Matching
activity
20 min
6.7 W input: old matching
Stored power
increase ~
10%
100 sec
6
Thermal sensing: last week results/2
6.7 W input
Matching
activity
20 min
6.7 W input: old matching
Stored power
increase ~
10%
100 sec
5.4 W input
Laser power
reduction
(19%)
7
Thermal sensing: last week results/2
6.7 W input
Matching
activity
20 min
6.7 W input: old matching
Stored power
increase ~
10%
100 sec
5.4 W input
Laser power
reduction
(19%)
5 W input
Stored power
reduction ~ 10%
Laser power
reduction
(25%)
8
Automatic alignment
14 d.o.f. controlled
8 with high gain (~3 Hz), 6 with low gain (~10 mHz)
Power recycling automatic alignment critical during lock acquisition
8 wavefront signals, 6 DC signals (common end mirrors, NI, WI)
Future steps: better filtering, enlarge BW, find demodulated signal for common end
9
WSR-1 sensitivity
WSR-1
C7
C7
WSR-1
10
WSR-1 noise budget
11
Faraday isolation optimization
Faraday isolation ~ 100, expected 10,000
Small key Allen found attached to the rotator isolation 10,000 in air
In vacuum isolation ~ 1000
Remote adjustment planned
Some signals improved – no clear improvements in the sensitivity
Power recycling
alignment
12
Brewster detection replacement
Detection
Brewster
window
B1 sensitive to detection Brewster vibrations
Wrong Brewster – too small (80 mm instead
110 mm)
New window installed in October
New tests on going
13
Acoustic enclosure laser lab
to the
vacuum
chamber
14
Acoustic enclosure laser lab
Actenuation 3-4 for both benches
Less than expected try to find
shortcuts
Problems with turbulent air flux
Temporary solved using apertures
(final solution: silenced door)
15
Clapping tests detection lab
Actions planned for detection bench and end benches
16
Noise at high frequency
Oscillator phase noise OK
Shot noise
Almost at the measured value
Difference with design
Stored power 300 W
(500W design)
T_OMC = 0.8 (1 design)
Calibration: ~ 40%
uncertainty
Frequency noise
See Matt’s talk
17
Control noises
18
Power recycling noise
BW ~ 40 Hz, cut-off 200 Hz
Power recycling coupling changes by
factor 10
Mechanism not understood
Actions:
Understand the coupling mechanism
Switch to B2
Understand the noise of the error
signal (B2_3f_ACp)
19
B2_3f error signal / switch to B2
B2_3f limited by read-out noise from ~ 50-100 Hz
~50 mW when ITF locked ~70 mW during lock acquisition - max power
B2_3f signals strongly depressed by the use of the 3rd harmonics demodulation
B2 gives a better SNR (1st harmonic demodulation)
Switch already tried but never worked for long time periods
20
Actuators noise
DSP
Emphasis
DeEmphasis
G
DAC
CoilDriver
21
Detection bench noise/2
Transfer function zBenchITF output
Several structures already present in
the ITF output excited
C7
22
Detection bench noise
Actuators
noise
C7
23
WSR-5 sensitivity
C7
24
Sensitivity to weather conditions
Red curve: 2.7 Mpc -(wind+sea)
Red curve = 2.7 Mpc-(wind+sea)
25
Suspension improvements
Use 4 locking signals for the
position control of 4 mirrors
in the beam direction
WE
1.
2.
LVDT
ACC
+
GOALS:
reduce use of noisy sensors
do not use ACC where tilt
dominates with no reinjection
of seismic noise
WI
PR
NI
NE
BS
f
3f
I
CARM
I
PRCL
DARM
f
MICH I,Q
26
Future steps
Noise hunting
B2 switch – power recycling control noise improvements
Detection bench actuators noise reduction
Diffused light mitigation
Detection bench
External injection bench
Mirror centering/coils balancing
Suspension control improvements
Global inverted pendulum suspension control
Vertical inertial damping
New SSFS (common mode servo) board
Acoustic isolation detection laboratory and end benches
Continue WSR program (data taking each ~3 weeks)
Long run (a few months) before end of S5
27