Project Schedule and Budget

Download Report

Transcript Project Schedule and Budget

ILMF Parts Database
System Specifications and Overview
Eric Dahlenburg
Contact: [email protected]
3/31/2016
Eric Dahlenburg
Project Goal
• Implement a server based Microsoft Access
database to track all parts not stocked in the
Federal Stock system.
• Storage of all parts into centrally located and
indexed storage bins within the ILMF
3/31/2016
Eric Dahlenburg
1
Specific Project Goals
• Eliminate unnecessary purchase of
duplicate parts
• Efficient use of outside parts budget
• Sharing of repair parts among technicians
• Increase delivery time of parts, through reuse and sharing
• Elimination of stockpiled parts from work
areas
3/31/2016
Eric Dahlenburg
2
Specific needs
Database will be capable of:
• Listing parts by 2 different Part Numbers
• Querying parts by nomenclature
• Querying parts by part number(s)
• Querying parts by stocking technician
• Record will contain a “Comment” and “Quantity”
field
• Users will not be able to modify any record except
for“Quantity” and “Comment” fields (for security)
3/31/2016
Eric Dahlenburg
3
Additional Needs Requested
Add “Research Tools” links to the interface for
• Approved Parts List (APL)
• Modcomp Approved Parts List
• View LPS Drawings
• Haystack (Federal Stock research site)
• Resistor/ Capacitor identification information
• Mil-spec to Manufacture IC conversion
information
• NTE Semiconductor cross-reference
3/31/2016
Eric Dahlenburg
4
Needs Added Based on Beta Testing
• Add “Self-Service” link for parts entry
• Add “Feedback/ Bug” report link
• Add a query that reports what parts have gone
below a user specified re-order quantity
3/31/2016
Eric Dahlenburg
5
Parts Database Project Gantt Chart
Actual M/S Project file can be seen here
3/31/2016
Eric Dahlenburg
6
Project Budget- ILMF Parts Database
Labor
Determine Needs Analysis
Create Development Database
Enter parts into database
Debug Development database
Develop Training/ Production DB
Technician Training
Project Close out
Assemble and Install Parts Bins
Hours
Total Hours:
Used to Date
56
56
40
40
80
80
40
24
40
8
8
8
296
View M/S Excel file here
184
Materials
Quantity Unit Price Total
Used to Date
WY499113- Rotating Drawer System
3
$429.00
$1,287.00
$1,287.00
WY499114- Rotating Drawer System
3
$429.00
$1,287.00
$1,287.00
WY499115- Rotating Drawer System
2
$429.00
$858.00
$858.00
Shipping
$50.00
$50.00
$50.00
Total Materials:
$3,482.00
Project Totals
Billable Rate, Hourly
Labor Margin %
Materials
Labor SubTotal
Labor Margin
$50.00
33.00%
$3,482.00
$14,800.00
$4,884.00
Total Labor
$19,684.00
Project Total:
$23,166.00
3/31/2016
Eric Dahlenburg
$3,482.00
Used to Date
7
$12,682.00
BUDGET
REMAINING
$10,484.00
Project Completion Estimates
3/31/2016
Eric Dahlenburg
8
Interface Mock-up with Added Needs
3/31/2016
Eric Dahlenburg
9
Table Keys and Relationships
3/31/2016
Eric Dahlenburg
10
Table Structure
PARTS
TABLE
PART_TYPE TABLE
UNIT TABLE
EMPLOYEE TABLE
3/31/2016
Eric Dahlenburg
11
Work to be completed
ILMF Parts Database
Completion Date
•
•
•
•
Beta Database debugged and
promoted as Production
database
10-18-2006
Technicians are trained on
Production database
10-25-2006
Feedback is collected and
database tweaked as required
10-25-2006
Project Closure/ Client
Acceptance
10-26-2006
3/31/2016
Eric Dahlenburg
12
Closing Summary
• On-Track for all milestones, with project closure
scheduled for 10-26-2006
• Training will be developed concurrently with
development database
• Interface will be user friendly, with canned
queries. This user- friendly design will ease
training demands.
• Interface will incorporate client requested
resource links
• Project is expected to be on-time and on or under
budget
3/31/2016
Eric Dahlenburg
13