Digitizer Status
Download
Report
Transcript Digitizer Status
Digitizer Status
Tilecal Institute Meeting
03-02-18
03-02-18
C.Bohm, K.Jon-And
Outline
• The TTCrx grounding problem
• The BCID readout problem
• Production time schedule
03-02-18
C.Bohm, K.Jon-And
The TTC grounding problem
• Some missing ground connections on the TTC-rx gave
rise to intermittent errors.
•Problem not discovered in Stockholm due to low read
out rate of test bench.
•After grounding the open inputs the faults disappear.
•Action:
•4 open inputs must be grounded on all boards
•A new Stockholm test bench is being built to discover
these kind of errors
03-02-18
C.Bohm, K.Jon-And
Action plan:
• Fix 700 not mounted boards.
• Print a modified pattern onto already manufactured
boards using thick film techniques, then mount the
boards as usual. Procedure should be verified within a
week.
• Fix 1400 already mounted boards. A more difficult
problem. Done partly at our institute in parallel with testing
above 700 boards, partly by a vendor:
03-02-18
C.Bohm, K.Jon-And
Repair plan of mounted boards
1.
Desolder TTCrx from the boards. Done in our institute. Rather
easy, 2 minutes per board (in total about 50 hours).
2. Remove solder. Done in our institute. More difficult, 6 minutes per
TTCrx (in total about 140 hours).
3. Print grounding pattern on bottom of TTCrx. 30 seconds per board.
Done by us at M A Kapslingsteknik.
4. Harden the conductive paste in a nitrogen oven. At Ericsson once
per day. Done by M A Kapslingsteknik.
5. Reballing the TTCrx. 9 at a time into the oven. Done by M A
Kapslingsteknik.
6. Remounting the TTCrx. Perhaps 10 minutes per board. Done by us
in collaboration with SMD production, our mounting vendor (in
total about 240 hours).
03-02-18
C.Bohm, K.Jon-And
Two persons at our institute work half time about 11 weeks.
BCID read out problems
•At the recent TileCal expert week it was found that the BCID
readings were unreliable.
This was found to be due to set-up and hold time violations
which occurred since the output timing of the TTCrx chip was
changed between different batches.
In the electronics meeting 4 different remedies were suggested:
Change of a clock driver to a faster component (“driver
solution”)
Resistor delay clk_des_1 (not preferred)
Capacitor delay clk_des_1 (not preferred)
Replace clk_des_1 with clk (“clock solution”)
03-02-18
C.Bohm, K.Jon-And
Comparison of ”driver” and ”clock” solution
”Driver”-solution
”Clock”-solution
•Recent tests indicate time
budget is safe. Time margin
in worst case w.r.t. TTCrx
clock is 1.3 ns.
•Safe timing solution.
•Some more tests are needed,
e.g. with LV and temperature
variations.
•Patch not as clean as for
driver.
•Incompatible with Sthlm
link interface used in Sthlm.
Takes 1 month to change
interface.
•Clean easy ”patch” (change
a component).
•New components have to be
burnt-in
and radiation tested.
03-02-18
C.Bohm, K.Jon-And
Tentative time schedules
3/3
Decision of BCID solution
”Driver”-solution
”Clock”-solution”
14/3: 20 boards QC and sent to
”expert week”.
7/3: 20 boards to ”expert week”
before QC
21/3: 20 boards to C-F if OK.
11/4: 20 QC boards to C-F.
24/3: 20 ”printed” boards to C-F
14/4: 20 ”printed” boards to C-F
14/4: 50 boards to C-F
5/5: 50 boards to C-F
21/4: 50 boards to C-F
11/5: 50 boards to C-F
28/4 … 100 boards per week.
18/5 … 100 boards per week.
N.B. These are AGRESSIVE time schedules.
03-02-18
C.Bohm, K.Jon-And