Kick off meeting star project
Download
Report
Transcript Kick off meeting star project
Kick off meeting star project
Infrastructure MDS
Contents
Surroundings
Import procedures
Local arrangements
MDS premises
PARAMARIBO STATION
Southwestern edge of
the capital
10km from the coast
Height terrace: 13m
West side
South side
East side
Front side (north)
METEO
LOT
Instrument platform
Import procedures
Extern
– Prepare export
– Send invoice (as soon as possible)
Local
– request for duty free import (about 3 weeks)
– Broker (about 2 weeks)
– installation
Contenst Invoice
Research project
Addressee: Meteorological service
Who paid (not the MDS - this is very
important)
Temporary or definite import (in 1st case a
deposit has to be paid- this can be a huge
figure)
Local arrangements
SAHO requests duty free import (2-3 weeks)
Broker clears goods (1-2 weeks)
Broker delivers goods at MDS
It is important, that the sender sends the
invoice and the bill of loading in time to save
storage money.
POWER
Power may be a problem
There is a structural power shortage in town.
Power interruptions occur at least one time a week
It could take long to install a 360V power line
Hence, Request for power line should at an early
stage.
(Installation is a pre-paid bussiness)