The Roads to New Hampshire`s Future
Download
Report
Transcript The Roads to New Hampshire`s Future
The Roads to
New Hampshire’s Future
Mission
Transportation excellence
enhancing the
quality of life in New Hampshire
Strategic Direction – 4 Step Approach
•
•
•
•
Preserve Existing Infrastructure – bridges, roads
Maintain Mobility
Improve Safety
Support the Economy
Transportation Factoids
• Roads in need of repair cost each NH motorist an
average of $330 annually in extra vehicle
operating costs - $300 million statewide.
• China invested last year; $108B or 9% of GDP into
Transportation Infrastructure, vs. USA will spend
1.7% GDP, with Canada 4%. GDP
• – Message is USA continues to lag behind
competing countries.
• NH “Highway Fund” includes gas tax “road toll”,
registrations and court fines:
• NH “Turnpike Fund is a separate fund (Enterprise
Account)
Key Facts About DOT
1,650 permanent employees (FY14) – 20% steady decrease since 1992
Responsible for:
• 2,143 State Bridges
• State Red List – 145 (8%)
• State Near Red List – 261
• 1,685 Municipal Bridges
• Municipal Red List – 353 (21%)
• All bridges are inspected at least once every two years
• State red list bridges are inspected twice every year
• Municipal red list bridges are inspected once every year
• 4,559 centerline miles of roadway maintained (additional 290 town
maintained)
• 8,868 lane-miles of roadway maintained
• Annual paving totals 200-300 miles per year (40,000 tons asphalt)
• Maintain 100,000 highway signs
2015 - 2024
Ten Year Transportation Plan
Governors Advisory
Commission on Intermodal
Transportation
(GACIT)
GACIT Process
– DRAFT Plan, Financially Constrained
•
Work in progress
– Public Hearing Input
•
Regional priorities and needs
– GACIT Recommendation to Governor –
December 2013
– Governor Recommendation to Legislature –
January 2014
– Legislative approval – June 2014
I-93 Funding
NH’s #1 Priority
No Current Financing Plan
• $250 M Unfunded Remaining Needs Not in Ten Year Plan – Capacity
Improvements Exit 3 NB to I-293 split (excl. Exit 5)
• Financial plan delivered to FHWA – remaining I-93 project in
jeopardy without statement of legislative intent to fully fund project
• Environmental Permits lapse in 2020
• Exit 4A – not funded
• Continuing Negative Impact on Ten Year Plan – 2030
Prioritizing Resources
NH Road System (4,559 mi)
1.
2.
3.
National Highway System
(NHS)(790 mi-18%)
•
Turnpikes
•
Interstates
•
Select US Routes
•
Select State Numbered Routes
US Routes and State Numbered
Routes (2,799 mi – 61%)
Unnumbered State Roads
(970 mi-21%)
New Hampshire Pavement Conditions: 1996-2016
ADDITIONAL $12M PER YEAR NEEDED
1. Influenced by additional ARRA funding
2. 2004 data is not included due to known
problems with the data collection vehicle.
Average Price of Asphalt Cement
1992 to 2012
The cost of asphalt cement increased 460% over this
period
Diesel, gasoline, road salt increases…..
Statewide Pavement Condition
(4,559 total centerline miles 299 unrated)
19 % good condition - 828 miles
44 % fair condition - 1,867 miles
37 % poor condition - 1,565 miles
$615 million would be needed to bring all poor
condition pavements to good condition (not
including drainage, guard rail & bridges)
$3.7 billion is the estimated total value of the
state-owned pavements
Pavements are the State’s most valuable asset
other than land and bridges
4,559 Miles
•
The DOT Maintained road network would
stretch from Concord, NH to Anchorage, AK
Anchorage, AK
A VERY LONG DRIVE!
Concord, NH
Poor Road Conditions
Lake Watson, Yukon
Anchorage, AK
Concord, NH
Fargo, ND
Would your car survive?
4
NH Bridge Condition
Red List – Bridges where one or more major
structural element is rated as poor
condition or worse, or require weight limit
posting.
Near Red List – Bridges where one or more
major structural element is rated as fair
condition.
Good – Bridges where no major structural
element is rated as fair or poor.
New Hampshire Red List Bridges
Total Number of State owned bridges in 2011 = 2,143
Additional Investment of $15m per year would repair as many as
10 bridges depending on size and conditions
2012: 11 Municipal Bridges Closed
Status and Estimated Costs – State Red List
• Ten Year Plan rehab/replace 98 of the 140 State Red List
bridges.
• $680 M (2012 dollars) to rehabilitate or replace the current
State Red List bridges.
• 100 State bridges were replaced last 10 yrs.
• Current 10-Year Plan, 98 State bridges to be replaced =10/yr.
• +200 years to replace all 2,143 State bridges.
• $7.82 Billion is the estimated total value of the state-owned
bridges
Turnpike System Overview
•
•
•
•
•
3 Turnpike Segments
89 Miles Long
170 Bridges
10 Toll Facilities
Enterprise Fund – All Turnpike
revenue must be used on the System
• Turnpike Revenue pays for:
– Operating & Maintenance Costs
– Debt Service
– R&R Work
– Capital Improvements
• FY12 $108.7M transactions and $116.6M toll revenue
1
Proposed
Turnpike Expanded Capital Program
Unfunded Projects in Current Capital Program form HB 391 – Session 2009 Authorization:
• Bedford ORT - $18M (FY15 Adv)
• Dover End of N-D Project - $80M (FY14 Adv)
Proposed Expanded Capital Program
• Bow-Concord: I-93 Widening (I-89 to I-393) - $195M (FY18 Adv)
• Nashua-Bedford: FEET Widening (Exit 8 to I-293) - $70M (FY17 Adv)
• Manchester: Reconstruction of Exit 6 & FEET Widening - $88M (FY17 Adv)
• Manchester: New Interchange at Exit 7 - $54M (FY 18 Adv)
• Spaulding Turnpike Toll Facilities (ORT or AET) - $15M (FY16 Adv)
• Spaulding Turnpike Maintenance Facilities - $8M (FY14 Adv)
• Turnpike Administration Building - $7M (FY15 Adv)
• Nashua-Bedford ITS Infrastructure - $4M (FY15 Adv)
• Merrimack Exit 12 Toll Plaza Removal - $2M (FY15 Adv)
Potential to create 14,000
jobs* over a ten year
period
• Sarah Mildred Long Bridge ($2M Annual Capital Contribution) - $18M (FY14 Start)
• TYP 2013-2022 includes PE & ROW for Bow-Concord ($13.0M) and for Manchester Exit 6 & 7
($14.0M)
*Reference: Transportation Infrastructure
Report 2011 – Building America’s Future:
Falling Apart & Falling Behind
FUNDING OUTLOOK
54
Challenges Ahead
• Federal Reauthorization MAP-21 expires
September 2014
• Shrinking revenue from fuel efficient vehicles
and less miles traveled due to recession
• One-time solutions–Not Sustainable Funding
• Rising Costs - Petroleum based business
Increased Fuel Efficiency = Less HWY Revenue
DOT FUNDING SOURCES
• Highway Fund (road toll tax a.k.a. gas tax,
motor vehicle fees, court fees, misc.) $260 m/
year)
• -$48 m deficit FY16, -$105 m FY17
Operating Budget
• Federal Aid ($143 m/year) – Capital Budget
• General Funds: Aeronautics, Rail, Transit
($900,000/year)
• Turnpike Fund: Turnpikes only (subject to
covenants to bondholders): $117m/year tolls
One-time Non-Sustainable Operating
Funding
• FY 06-07
Surplus from Highway Fund
• FY 08-09
Bonding $60m
• FY 10-11
Registration Surcharge $90m
I-95 Transfer $50m
• FY 12-13
I-95 Transfer $52m
• FY 14 -15
I-95 Transfer $ 30m
• FY 16 -17
Deficit -$48m & - $105m
Summary
• $22m / yr. : Complete I-93 widening project $250m
• $15m / yr. : Red List Bridge additional funding
• $12m /yr. : Road Paving to repair poor roads
• $35m / yr. : Maintenance & Operations of entire
transportation system
• $20 / yr. : Municipal Road & Bridge Repair
The Roads to
New Hampshire’s Future
In light of the recent Global Competitiveness Report rankings from the World Economic Forum on
infrastructure quality which has listed the United States at 25th place—down from 9th place in
2009—such a major disruption to federal transportation investment will produce serious losses that
threaten the gradual macroeconomic recovery seen in the last few years.
Investments in Transportation
Legend
GT = Gas Tax
DT = Diesel Tax
GT= 19.6 cents
DT= 19.6 cents
GT= 31.5 cents
DT= 32.7 cents
GT= 32.3 cents
DT= 31.0 cents
GT= 26.5 cents
DT= 26.5 cents
GT=49.3 cents
DT=54.9 cents
GT= 33.0 cents
DT= 33.0 cents
Transportation Briefing
Rep. David B. Campbell (D –
Nashua)
2013 Red List Bridges
145 State Owned Bridges
353 Municipal & Other Owned Bridges
Pavement Conditions
2000
2010
Red = Poor Condition
Transportation Briefing
Rep. David B. Campbell (D –
Nashua)