Buffalo Ridge Incremental Generation Outlet (BRIGO) Transmission

Download Report

Transcript Buffalo Ridge Incremental Generation Outlet (BRIGO) Transmission

Buffalo Ridge Incremental
Generation Outlet (BRIGO)
Transmission Study
Presentation to National Wind
Coordinating Committee
June 22, 2005
W Grivna, PE of Xcel Energy
R Gonzalez, PE of Excel Engineering, Inc.
Outline
•
•
•
•
•
•
•
Study Purpose/Goals
Background
Participants
Analysis
Results
Conclusions/Recommendations
Next Steps
Study Purpose/Goals
• Determine feasibility of increasing Buffalo Ridge
area generation outlet…
• by several hundred MW…
• through “modest” (presumably 115 kV-class)
improvements…
• that could be relatively quickly implemented…
• while plans for future long-range regional
transmission projects continue their evolution.
Background
• Buffalo Ridge is the premier wind resource in
MN/SD
• Transmission improvements under way to increase
outlet capacity to 825 MW
• Further interest confirmed by MISO & WAPA
interconn queues
• Xcel Energy has had specific MW & Energy %
mandates
• All other Minnesota power suppliers now also
have renewable energy obligations
• Result: Intense interest in wind development on
the Ridge
Transmission map of Buffalo
Ridge Area
Study Participants
• Sponsor: Xcel Energy
• Technical & Economic Analyses performed
by Xcel Energy
Reviewers/technical support:
(MAPP MB SPG)
•
•
•
•
•
•
•
•
•
•
•
Western Area Power Administration
Otter Tail Power
Missouri River Energy Services
MISO
Marshall Municipal Utilities
Great River Energy
East River Electric Power Cooperative
Alliant Energy
State regulators (MN/ND/SD)
Energy Policy Groups (Wind on the Wires)
IPPs
Analysis
• Powerflow: Concentrate on 2007, summer offpeak condition
– System intact
– First contingency (“n-1”)
• Requirement: satisfy applicable voltage and
loading criteria
• Identify “existing system” (post-825 MW
additions) outlet limits for Buffalo Ridge
Mpls/St Paul deliveries
• Formulate transmission options
• Test Options’ performance
– Electrical
– Financial
Cost versus Outlet for Options
Complications
•
•
•
•
•
•
•
Reactive power requirements/Voltage Stability
Power and Energy losses
Load-serving considerations
Constructability
MISO-WAPA interface
North Dakota Export (NDEX) interface
Geographic extent of Ridge
Results
• All Options can achieve 300-500 MW of
incremental outlet
• Some Options require extensive additional
improvements
– Line reconductors & rebuilds
– Transformer replacements
– Shunt capacitor additions
• Incremental energy losses are high (25 – 30%)
• The “best” Options all include a second
(independent) Fenton-Nobles Co 115 kV outlet
path to the new 345 kV
Conclusions/Recommendations
• Implement “Option 31A”
–
–
–
–
–
2nd Nobles Co 345/115 kV transformer
2nd Nobles Co-Fenton 115 kV line
Lake Yankton-Marshall 115 kV line
Several shunt capacitor banks
Misc reconductors, equipment upgrades
• Capable of providing 300 - 500 MW of
incremental outlet (beyond 825 MW level) at
reasonable cost
• Provides some incidental load-serving benefits
Map of Option 31A
Next Steps
• Coordinate & confirm compatibility with likely
long-range plans & identified projects
– CapX
– Big Stone 2
– MISO NW Exploratory
• Address adaptation to specific proposed wind gen
projects
• (Need “Yankee fix” if MWs on north Ridge
exceed critical level)
• Coordinate with MISO stability study results
• Initiate permitting process