Inspection and
Testing
Approved for Public Release
1
Introduction
• All materials and services supplied to
Electric Boat must be inspected and tested
in accordance with Purchase Order
invoked specifications, drawings, standard
clauses, etc.
– Determine if supplier or government have
additional or more stringent requirements.
Inspection and Testing
2
Approved for Public Release
Introduction (continued)
• Purchase order imposes inspection
systems via EB2678 and Standard
Clauses (60-5, 60-19, 60-58) for MIL-I45208, MIL-Q-9858, or ISO9000 series
– Accordingly, suppliers must establish and
maintain a compliant inspection system
– System must also address subtier suppliers
– Be aware of Supplemental Technical
Requirements (60-58 STRs) for ISO9000
Inspection and Testing
3
Approved for Public Release
Introduction (continued)
• Inspection and Testing that result in OQE
must be performed by a supplier’s
organization independent of production,
i.e., the Quality Control Department.
Inspection and Testing
4
Approved for Public Release
3 Basic Types of Inspection:
• Receiving Inspection verifies
acceptability of materials, services, and
associated documentation at receipt.
Inspection and Testing
5
Approved for Public Release
3 Basic Types of Inspection:
• In-Process Inspection performed at
manufacturing stages deemed necessary
to verify:
– internal compliance with requirements as
production progresses, statistical process
control charting, non-accessible assembly,
etc.
– as required by the purchase order, drawing,
or specifications to be an EB or Government
Hold/Witness Point (SC37-8 series).
Inspection and Testing
6
Approved for Public Release
3 Basic Types of Inspection:
• Final Inspection shall verify that the
product is dimensionally acceptable,
properly assembled, and the
documentation is satisfactory in
accordance with the purchase order.
Inspection and Testing
7
Approved for Public Release
Requirements
• Inspection and Testing must be accomplished
using clear, complete, and current procedures
and instructions
• Inspection and Testing shall be performed in
appropriate environmental conditions with
respect to temperature, humidity, noise,
vibration, etc.
Inspection and Testing
8
Approved for Public Release
Requirements (continued)
• Instruction needs to specify:
– Source of the inspection or test criteria
• drawing, specification, standard clause, etc.
– Gaging or tooling required to ensure proper
accuracy of measurements
– Provision for recording the actual results as
objective quality evidence for reference
Inspection and Testing
9
Approved for Public Release
Requirements (continued)
• When required by a standard clause (10,
60, 76 series), drawing, or specification,
procedures shall be approved by Electric
Boat on a Vendor Procedure Approval
Request (VPAR), prior to performance of
the testing.
Inspection and Testing
10
Approved for Public Release
Requirements (continued)
• Examples of Testing Procedures requiring
Electric Boat approval:
– NDT Procedures
– Noise Testing Procedures
– Shock Testing Procedures
– Vibration Procedures
Inspection and Testing
11
Approved for Public Release
Requirements (continued)
• Examples of Testing Procedures requiring
Electric Boat approval (continued):
– Forging test specimen location drawings
– Production Procedures (when specified by the
Purchase Order or Procurement
Specification)
– Qualification and First Article Procedures
(when specified by the Purchase Order or
Procurement Specification)
Inspection and Testing
12
Approved for Public Release
Electrical Testing
Dielectric Voltage Withstand Test
 Dielectric Voltage can be a Destructive test.
 Voltage Level and time should be considered.
• Example: Operating Voltage is 440VAC
• Test at 2 X 440 +1000VAC= 1880VAC
Inspection and Testing
13
Approved for Public Release
Electrical Testing
Insulation Resistance
 An Insulation Resistance test is normally done with DC and is
usually performed at a lower voltage level such as five (500VDC)
hundred volts. An IR test measures the quality of the insulation
system and provides a measure in ohms or megohms. It is
sometimes used before a HiPot Test as both a predictor of a failure
condition and to provide a quantitative value of the insulation
system.
 Often performed before, during and after Hydro on Electrical Hull
Penetrators.
Inspection and Testing
14
Approved for Public Release
Electrical Testing
Continuity
• Determines if there is an uninterrupted electrical
connection between two points.
•
•
•
•
Resistance or DC Resistance
Measured in ohms
The opposition to current flow
Report actual results EX: > 1 Ohm
Inspection and Testing
15
Approved for Public Release
Documentation
• Inspection and test results shall be documented,
preferably on a company form with letterhead.
• Inspection and test results must clearly indicate:
–
–
–
–
the type and number of inspections or tests performed
the results of the inspection or test
the signature/date of personnel performing the test
additional requirements of the applicable SC76-9 series
Inspection and Testing
16
Approved for Public Release
Documentation (continued)
• When required by the Purchase Order,
generally a Standard Clause, the
Inspection and Test Reports shall be
provided to Electric Boat.
• Inspection and Test Reports shall not
contain any qualifying statements, such as
“to the best of our knowledge”, “while in
our possession”, “approximately”, etc.
Inspection and Testing
17
Approved for Public Release
Documentation (continued)
• All instruments, gages, and tools used to perform
official inspections and tests must be calibrated in
accordance with a documented calibration
program.
• Actual instruments, gages, and tools used to
perform official inspections and tests should be
identified and listed in the inspection or test report:
– provides additional objective quality evidence
– traceability if gage out of calibration
Inspection and Testing
18
Approved for Public Release
Documentation (continued)
• Inspection Records and Test Reports shall
be traceable back to the product being
tested or inspected and the applicable
procedures or instruction being used.
• Corrections of errors on Inspection
Records or Test Reports shall be in
accordance with the requirements of
Electric Boat Specification 2678.
Inspection and Testing
19
Approved for Public Release
Suggestion
• Initiate a method and procedure defining
type and accuracy of gages to be used
for dimensional inspection of particular
attribute tolerance ranges
– Gage for +/-.020” tolerance different than
+/-.0005” tolerance as is a 50psig test
different than a 500psig test
– 10% rule
Inspection and Testing
20
Approved for Public Release
Suggestion
• To better ensure that the integrity and caliber
of the inspection system and the personnel
are being maintained:
– Implement an overcheck program that periodically
confirms inspector results
– Implement a refresher training and qualification
program for inspectors (similar to NDT, welding,
etc.)
Inspection and Testing
21