Kansas Interconnection
Implementation Workshop
The FERC Process:
What it means for Kansas and other states
Wichita, Kansas Oct. 1, 2003
Christopher Cook
Interstate Renewable Energy Council
Interconnection and Net Metering Specialist
E3 Energy Services, LLC
www.E3Energy.com
Procedural History at the Federal Energy
Regulatory Commission (FERC)
FERC ANOPR B Large and Small generators
Issued in October 2001
Negotiations until Jan. 2002
Parties filed consensus documents (including
differences) Jan 11, 2002
NOPR issued April 24,2002
FERC Generator Interconnection
Rulemaking - Procedure
Original ANOPR suggested FERC wanted
expedited procedures for small generation B
set bar at 20MW
Parties achieved little consensus on small
generator interconnection standards
Second ANOPR issued for small generators
August 2002
FERC Generator Interconnection
Rulemaking - Workgroups
Working groups started in September
Many meetings with utilities; small generator
coalition; NARUC
Input from best technical sources in the country
Meetings went on till parties were sick of each
other
Consensus document filed with FERC in Dec.
Small Generator ANOPR
Super Expedited (<2MW) very detailed
guidelines
2 Technical components
Protection on the generator
Impact on the Grid at the point of
interconnection
Also includes fees; timing; procedure; standard
form contract; application
Small Generator ANOPR (cont.)
Generator protection
Meets or exceeds all applicable IEEE, UL, and
NEC requirements
UL Listed Generator System = plug and play
FERC registry of certified equipment
Small Generator ANOPR (cont.)
Grid impact
<15% of peak load
Limited fault current contribution
Limits on imbalances
10 steps total
Small Generator ANOPR (cont.)
Secondary screens
Issue: should grid modifications be included or
should the small generator have to accept the
grid conditions as found
Cut-out
Small Gen proposal: $300 time and materials
Small Generator ANOPR B
Non- technical
Fees (nc)
Free for <20kW
Graduated up to 2 MW
Max $700
Anticipates average of three hours work and/or
minor equipment change
Small Generator ANOPR B
Non- technical
Timing
Most interconnections approved in 30 days
Disputes
Technical Master
FERC ANOPR B Technical Difficulties
Distribution networks
Found in large urban areas B where DG most
valuable
Sensitive protection devices
Utilities would suggest no interconnected
generators
Very small and those with no export should be fine
FERC Issued NOPR
Published in Federal Register Aug. 19, 2003
Comments due Oct. 3, 2003
Details are difficult to discern
Redundant and conflicting procedural guides
Fundamental misunderstanding of consensus
documents
Bad parts for both sides B some items could be
dangerous
FERC Interconnection Processes
Generator
Application
>20MW?
High
or low voltage
(69kV)?
Low
No
Yes
High
Large Gen
No
< 10MW?
Full
Application
Process:
Feasibility
Quick
Impact
version of
Facilities
studies
Studies
Interconnection
Agreement
Expedited
Application
Process
< 2MW
Yes
Super
Expedited
Application
Process
FERC NOPR Technical
Small Gen defined as those less than 20
MW (Orig. FERC position opposed by many)
Super Ex IP
2MW and under low voltage (radial) only
5% of peak load; spot network 5% or 50kW; 10%
fault current; can’t exceed 85% short circuit
ratings; 10MW total in stability limited areas;
3wire & 4wire configurations; 20kVA secondary
limit; 20% imbalance on center taps
FERC NOPR Technical
Expedited (<10MW)
Same as Super Ex except 15% of peak load,
90% of short circuit max
Seems to apply to failed Super Ex. as well
If passes screens but utility is nonetheless
concerned, can send to feasibility study. If
study finds no impact, utility pays for study.
Non-expedited small generator review
Feasibility Study (high level look --benefits
generator before spending $ on Impact Study)
Impact Study BT&D (this costly study waived
in most cases for small generators)
Facilities study (equipment)
These are expedited versions of the same
for large generators
FERC NOPR Procedures
Single queue
TP must work with Affected Systems
Dispute Resolution B no FERC technical
master
Costs - not defined but generator must pay
Insurance - same as Large Gens.
FERC NOPR Procedures (cont.)
Does not apply to incremental additions
Unlike PJM procedures
FERC ANOPR -Jurisdiction
Would apply to all FERC regulated generators
FERC defines as generator interconnecting to
dual use low voltage facility (has some
wholesale generation already on it)
Safe Harbor utilities would have to follow rule
to preserve safe harbor
FERC NOPR gaps/contradictions
No transmission checks on 2-10MW on low
voltage
No small low voltage procedures for area
networks
Incentive to find impact
Different criteria used in titles
Commentary:
Interconnection Policy
All interconnection rules to date focus on
integrating DG without change to the grid
There is at present NO discussion in the
regulatory arena about changing the grid to
be more accommodating to DG
DG unlikely to attain lofty goals without a
more deliberate debate on interconnection
That's all Folks...