Upgrade week FNAL 20111108 M. Hansen, CERN
Download
Report
Transcript Upgrade week FNAL 20111108 M. Hansen, CERN
System issues for the
Upgrade Project
Magnus Hansen
20111110
Current Standards in CMS
CMS systems comply with a number of agreed
standards for good reasons
Common infrastructure
Common maintenance organization
Common problems and solutions
For different reasons not all subsystems comply
with all possible standards
E.g. standard not stable in time
To my understanding there is no significant
advantage NOT to comply with the agreed
standards
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
Current Standards in CMS
Register access (Slow control)
VME64x PnP compatible VME interface
Numerous flavours, ~ 1 per fw designer
We could have done better here
HAL Register description file format and
associated software
Centrally developed and maintained
Not adopted by all systems but most
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
Current Standards in CMS
VME crates
WIENER VME crates
Standard 9U and 6U card cages
Standard VME64x backplane
Except ECAL, GCT
Custom J0 for power
Standard CAN bus controlled fan tray
Three flavours: 6U, 9U with/without transition module coverage
Large number of different spec power supplies
Under CERN supported maintenance contract
Few exceptions, e.g. RCT
VME controller
CAEN PCI-VME bridges
“Simple” PC upgrade path
Except for PCI bus running out of fashion
Under CERN supported maintenance contract
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
Standards in CMS
LVPS
CAEN EASY 3000
WIENER MARATON
Preshower, DT, RPC
ECAL, CSC, CASTOR
LHVPS
CAEN EASY 4000
Pixels, Strips
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
Standards in CMS
HVPS
CAEN
ECAL, DT, RPC, CSC ME1/1
Other
HCAL (custom), CSC (Commercial and custom)
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
Standards in CMS
CAEN and WIENER power supply equipment is Standard
from a software (DCS) point of view but basically all
hardware modules are custom, customized or unique for
the user
CAEN and WIENER equipment bought for CMS is
covered by maintenance contracts
Runs until December 2019
Logistics supported by CERN
WIENER equipment can be bought through a CERN
supported purchase contract until 2019
CAEN equipment can be bought through a CERN
supported purchase contract
Limitations apply
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
Upgrades
Maintain or Improve performance
For physics
Maintain or Improve reliability
For CMS availability
Maintain or improve maintainability
For total cost of ownership
Maintain compatibility with CMS interfaces or
agree on evolution
TTC, TTS, DAQ, DCS, etc.
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
What we want
Integration in the existing infrastructure
E.g. crate cooling with vertical air-flow
Limit the number of families of crates and power
system
System control
Common control and monitoring software
Common system management hardware
Purchasing and maintenance contracts
Preferably analogous to the CAEN and
WIENER frameworks currently in place.
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
What we want to avoid
Skimping on any part of upgraded system such that it is
marginal in terms of reliability or performance
Power supplies
On board / on detector
Can any firmware build cause overload and subsequent shutdown of the power
supply?
Can you get out of this situation?
Off detector
Re-use of power supplies may seem economically justified but does it meet
reliability goals? Is the performance marginal?
Cooling
We construct for 10 years of solid operation. Industry 3 years.
Mechanical elegance
Mezzanine cards with scattered connectors, i.e. mechanically overconstrained
Bulky cables with tiny and fragile connectors
ETC.
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
CMS Reviews
I claim the established CMS review process is
effective but the follow-up is sometimes difficult
Many current reliability issues were pointed
out during reviews but were contested and/or
ignored
To be fair: many recommendations were contested and/or ignored
and have not caused any problem. Yet.
Some of the issues lead to upgrades earlier
than expected
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
Large number of Electronics System
Reviews (ESRs) contributing to the
success of CMS
Example: November 2003 Electronics Week
Monday, 3 November 2003 10:30 ->12:45 Review of the Preshower LV Power System
Monday, 3 November 2003 13:30 ->17:50 ESR for the Muon DT Mini Crate System
Tuesday, 4 November 2003 09:30 ->18:00 Review of the CMS Low Voltage System (In
parallel with Trigger Review)
Tuesday, 4 November 2003 09:00 ->12:50 Calorimeter Triggers (40-5-A01)
Tuesday, 4 November 2003 14:00 ->17:45 Muon and Global Triggers (40-5-A01)
Wednesday, 5 November 2003 09:00 ->14:00 ESR of the CMS Tracker Electronics
Wednesday, 5 November 2003 14:00 ->18:45 ESR of the CMS Pixel Electronics
Thursday, 6 November 2003 09:00 ->14:00 Meeting of the Electronics System Steering
Committee
Thursday, 6 November 2003 14:00 ->18:30 ESR of the Muon CSC Electronics
Friday, 7 November 2003 08:30 ->09:30 CPT Plenary Session on the CMS Trigger
Friday, 7 November 2003 09:30 ->14:00 Review of CMS FEC and USC Cabling Plans
Friday, 7 November 2003 14:00 ->18:15 ESR of the HCAL Electronics
One full day and 11 half day ESRs in five days all chaired by Peter!
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
Standardization of new equipment
xTCA
Selected microTCA in addition to VME for stage 1
upgrade back end systems
Standardize:
Shelf perhaps including backplane
Calorimeter trigger may require customization of the un-used backplane
connections. Customization by vendor, thus still commercial
MicroTCA Carrier Hub
Meant to be multi-vendor compatible but beware…
Power modules
Multi-vendor compatibility
Bulk power supplies
In principal multi-vendor BUT: Vertical air flow 48V modular ipmi controllable
supplies are rare but exist.
Shelf management software
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
Example: Future HCAL Backend Crate
TTC/Fast Controls
Central DAQ/FMM
FE Data Links
DAQ
Timing
uHTR
uHTR
uHTR
uHTR
uHTR
uHTR
Upgrade week FNAL 20111108
Control
MCH
(commercial
)
uHTR
uHTR
uHTR
uHTR
uHTR
uHTR
Trigger Links
(DTC/
AMC13)
Configuration/ Slow
Controls (Ethernet)
M. Hansen, CERN. [email protected]
J. Mans
uTCA Workshop planned
Jan/Feb 2012
CMS rack integration
CMS cDCS integration
CMS common shelf specification
DAQ interface evolution in view of the upcoming
DAQ upgrade
Applies to uTCA systems only; legacy (soon
vintage ) Slink sender cards supported for
legacy systems
TTC distribution (maintenance) upgrade
Under discussion
ETC.
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]
End
Electronics week in January/February
Invitation will be distributed at least to hn-cmselectronics
Upgrade reviews and workshops
Common spares review
Etc.
Electronics twiki under construction under CMS
technical coordination
Collection of docs and links. Please contribute.
Upgrade week FNAL 20111108
M. Hansen, CERN. [email protected]