Project Update
• GN4-1 grant agreement signed on 28th October
• GN4-1 pre-financing received 75%
• Next step: amend FPA/SGA to add Latvia (and later (in GN4-2) Azerbaijan, Albania)
Networks ∙ Services ∙ People
www.geant.org
2
Project Activities RAG Status
Activity
Manpower
(M1-M5)
RAG Status
(Oct 2015)
NA1
74%
GREEN
NA2
78%
GREEN
NA3
78%
GREEN
NA4
92%
GREEN
SA1
88%
GREEN
SA2
107%
GREEN
SA3
79%
GREEN
SA4
84%
GREEN
SA5
77%
GREEN
SA6
86%
GREEN
SA7
64%
GREEN
SA8
64%
GREEN
JRA1
75%
GREEN
JRA2
77%
GREEN
JRA3
95%
AMBER
Networks ∙ Services ∙ People
www.geant.org
Comments
Green code has been restored as although the legal action continues, the scope of impact on the activity has been managed. A
replacement function for this part of CAT is due for the new year via a subcontract, the affected deliverable has been rebenchmarked.
A number of people will be leaving the project before the end of this year.
3
GN4-1 Deliverables till the end of October 2015
#
Deliverable
number
Deliverable Title
Activity
Lead participant
Delivery
date
Status
1
D10.1
GÉANT Monthly Service Report
10/SA6
GEANT Limited
M02
Done
2
D10.2
GÉANT Monthly Service Report
10/SA6
GEANT Limited
M03
Done
3
D2.1
Services Marketing and Promotions Strategy
2/NA2
GEANT Limited
M03
Done
4
D10.3
GÉANT Monthly Service Report
10/SA6
GEANT Limited
M04
Done
5
D9.1
Moonshot Service Specification
9/SA5
JISC
M04
Done
6
D10.4
GÉANT Monthly Service Report
10/SA6
GEANT Limited
M05
Done
7
D1.1
Quarterly Management Reports
1/NA1
GEANT Limited
M05
Done
8
D9.2
Market Analysis for Virtual Organisation Platform as a Service
9/SA5
AMRES
M05
To be submitted
9
D10.5
GÉANT Monthly Service Report
10/SA6
GEANT Limited
M06
Done
10 D9.3
Service Approach Specification to Small Site eduroam Adoption
Implementation of GN3plus Regional Connectivity Study
9/SA5
CARnet/SRCE
M06
31 Dec
11 D5.1
Recommendations (inc. Cost Savings) and Handover of Network 5/SA1
Changes to 10/SA6
GEANT Limited
M06
30 Nov
12 D5.2
Revision of GÉANT Network Evolution Plan
GEANT Limited
M06
30 Nov
Networks ∙ Services ∙ People
www.geant.org
5/SA1
4
GN4-1 Deliverables till the end of October 2015
• 8/51 Deliverables
• 16%
Networks ∙ Services ∙ People
www.geant.org
5
GN4-1 Milestones till the end of October 2015
#
Milestone Milestone Title
Activity
Delivery
Status
1
M1.1
Training Workplan
1/NA1
M1
Done
2
M1.2
PMF/PLM in Place
1/NA1
M3
Done
3
M1.3
Working/ICT Tools and Infrastructure
1/NA1
M3
Done
4
M14.1
Delivery of Software Component Repository and Initial Requirements-to-features matrix
14/JRA2
M3
Done
5
M14.2
Future Network Services Specification
14/JRA2
M4
Done
6
M1.4
GEANT Event
1/NA1
M5
Postponed
7
M2.1
Services Case Studies
2/NA2
M6
Done
8
M4.1
Focus Group Report
4/NA4
M6
Done
9
M5.1
Recommend Solution for Anticipated 100Gbps Router Port Shortage
5/SA1
M6
Done
10 M5.2
Implementation of Regional Connectivity Study Recommendations
5/SA1
M6
30 Nov
11 M6.1
GTS Version 3.0 Architecture (Update)
6/SA2
M6
30 Nov
12 M7.1
Wireless Crowd Source Performance Measurement and Verification
7/SA3
M6
19 Nov
13 M8.1
Production Supervision Process
8/SA4
M6
Done
14 M9.1
eduGAIN Roadmap Update
9/SA5
M6
19 Nov
15 M9.2
eduroam Roadmap Update
9/SA5
M6
30 Nov
16 M11.1
Online Services Q1, Q2 Progress Report
11/SA7
M6
Done
Networks ∙ Services ∙ People
www.geant.org
6
GN4-1 Milestones till the end of October 2015
• 10/30 Milestones
• 33%
Networks ∙ Services ∙ People
www.geant.org
7
Deliverables at the end of the project
• 24 out of 51 deliverables in M12
• More QASPER reviewers invited
• Could use extra Technical Authoring resources for a couple of months
• Clear message to Activity Leaders to try to finish as soon as possible
• Still unclear if everything will be on time
• More progress reports will be provided on a monthly basis
Networks ∙ Services ∙ People
www.geant.org
8
GN4-1
Budget Update
Networks ∙ Services ∙ People
www.geant.org
Manpower at the end of September ~ 81%
Networks ∙ Services ∙ People
www.geant.org
10
Manpower for M1-M5 GN4-1
actual
SA
NA
JRA
FTE Equiv
budget
budget
5mths to
30/09/15
5mths to
30/09/15
12mths to
30/04/16
MM
MM
MM
409
196
124
729
146
498
250
153
901
180
1,192
600
367
2,159
180
VAR.% - act vs.
bud (to date)
% of total
spent to
date
-18%
34%
-22%
33%
-19%
34%
-19%
34%
-34
-19%
• On average partners are claiming 81% of budget Manpower during first 5 months
Networks ∙ Services ∙ People
www.geant.org
11
Main GN4-1 project contributors (M1-M5)
Partner
Actual
Budget
%
GEANT Ltd
269
283
95%
PSNC
81
83
98%
NORDUnet
62
81
76%
DFN
36
45
79%
GRNET
26
39
68%
GEANT Association
29
37
78%
UoB
23
36
63%
CESNET
30
32
94%
SURFnet
18
30
59%
CARNet
25
30
85%
Networks ∙ Services ∙ People
www.geant.org
12
Actual vs Budget position at Cost
Category Level M1-M5 (to 30 September 2015)
5 Months Actual to 30 September 2015
Manpower
Travel
Network
Other /
SubContract
2.9
1.7
.8
.2
.2
.0
10.0
.0
.0
.1
.5
.0
13.3
2.4
.8
5.4
.4
10.0
.7
16.5
SA
NA
JRA
3.5
2.1
1.1
6.6
.4
.3
.1
.8
10.2
.0
.0
10.2
.1
.9
.0
1.0
14.1
3.3
1.2
18.6
SA
NA
JRA
.6
.4
.3
1.2
.2
.1
.1
.3
.2
.0
.0
.2
.0
.4
.0
.4
.9
.9
.4
2.1
% variance
-18%
-45%
-2%
-35%
-11%
VARIANCE
BUDGET
ACTUAL
€M
Actuals 11% favourable to budget after 5 months
SA
NA
JRA
Total
BUDGET
total
(12 mths)
€m
32.3
7.9
2.8
43.1
42% Project time elapsed >>> 38% of budget spent
Networks ∙ Services ∙ People
www.geant.org
13
Extension needed? Funding claimed so far
• Current underclaim: 0.96M
• Projected underclaim: 1.85M
• Options:
• Claim manpower at 125%
• Project extension by 1 month
• The Commission services will, in future, more closely examine each request for an extension to the
duration of the project to ensure that they are only given where there is a clear added value for the
project, or where external events (not reasonably foreseeable at the point of signing the grant) mean
that it is impossible to complete the work in the agreed timeframe.
Networks ∙ Services ∙ People
www.geant.org
14
Activities Highlights
Networks ∙ Services ∙ People
www.geant.org
Some activities highlights/lowlights
(from RAG reports & 1st Quarterly Management Report)
• SA1: Network Services
• SA1 Study of NRENs fibre and optical networks - 10 NRENs completed
• SDN IP and BOW and path computation proof of concepts progressing, pilots planned for Q1 2016.
• Regional study implementation all complete. Ireland, Nordic and Baltic connectivity reconfiguration and SEE
connectivity
• Solution agreed to solve GEANT router 100G port shortage problem – 4 port 100G cards will be used in
routers that require additional 100G ports to replace dual port cards, dual port cards will be reused to
replace single port cards, shortage of slot capacity will trigger the creation and deployment of a low speed
chassis at sites. 1& 10G ports will be migrated off MX 960 to unused MX480s
• Negotiation complete with Interxion at Frankfurt, Paris and Vienna and contracts signed, recuing power cost
by €250k pa
• Support deal signed with Infinera, capping support and delivering a saving of €540k in 2017 and €300k of
hardware
• Analysis complete to expand PoP housing capacity in London – site and fibre providers chosen, contracts
being negotiated, RFS date target end of January.
• MX routers finally upgraded to version of JuNOS that supports netflo v9 after 18 months of working with
Juniper to obtain JuNOS code that works - migration to separate AS and VPN for Internet traffic will begin
soon
Networks ∙ Services ∙ People
www.geant.org
16
Some activities highlights/lowlights (cont’d)
• SA2: Testbeds
• Held the first of two GTS Tech+Futures Workshop (20-22/10) with excellent participation, and good
discussions on how the users would GTS to evolve.
• Attended the GLIF workshop in Prague (28-30/9) demoing GTS, as well as EWSDN in Bilbao (30/9- 2/10)
with both a GTS demo and lightning talk.
• Deployed PODS at three new sites in Milan, London and Hamburg.
• SA3: Network Delivery and Support
• Stefan Metzger is the new Task Leader for SA3T1 - Security Service Development.
• eduSAFE platform has been changed to OpenVPN. Have tested single tunnel capacity in the range of
200Mb/s between CPH and STC. Portal has been upgraded with federated login making it easy for users to
test.
• WIFImon deplyeded at NORDUnet conference, additional experience found and described in deliverable.​
• CMon working with GTS to help them monitor links.
Networks ∙ Services ∙ People
www.geant.org
17
Some activities highlights/lowlights (cont’d)
• SA4 ​Production Application Services and Infratsructure
• FaaS transition - SA5 and SA4 finalizing steps for the service transition into operation.
• "School for developers" organized and held in Poznan, in cooperation with NA1T7, and got very positive
feedback from participants.
• SA5: Trust and Identity Service Development
• Green code has been restored as although the legal action continues, the scope of impact on the activity
has been managed. A replacement function for this part of CAT is due for the new year via a subcontract,
the affected deliverable has been rebenchmarked and is back on track.
• SA6: Production Support
•
•
•
•
•
GTS full FLS due to go in to production Nov 16.
6th STF to be hosted by RENATER in Nov
SA6 Task 4 disbanded and responsibilities transferred to T3 and SA1 T2.
GN4 Monthly Service Report submitted on time.
eduroam FLS in pilot and due to go into full production this month.
Networks ∙ Services ∙ People
www.geant.org
18
Some activities highlights/lowlights (cont’d)
• SA7: Supply Chain Support
• Around 30 providers interested in our IaaS tender
• Tender will take 3 months longer to complete because of external legislative aspects.
• SA7 is making online services available in several areas:
• Facilitating the use of OwnCloud online file storage (many NRENs now use this)
• Helping NRENs deploy the open source Rendez-Vous (JITSI) web conferencing platform, as spearheaded by
RENATER.
• 5 NRENs now active
• Making the Okeanos IaaS platform from GRNET wider available
• looking at use within the GN4 project.
• Facilitating knowledge sharing on OpenStack.
• SA8: Real-Time Appplications and Multimedia Management
• The WebRTC task drafted a straw-man proposal that will form the basis of the WebRTC Roadmap
deliverable.
• The GÉANT OER service development (SA8 Task 3) is right on track, we are expecting the pre-launch of the
user portal by the end of the year.
Networks ∙ Services ∙ People
www.geant.org
19
Some activities highlights/lowlights (cont’d)
• JRA1: Future Network Topologies
• JRA1 and GÉANT 4th Network Architects Workshop successfully passed 19-22 of October in Dubrovnik, Croatia.
Workshop attracted near 40 present and remote participants from more than 20 NREN’s and organisations. Plenty
of time dedicated for internal and cross task meetings, which gave valuable results.
• JRA2: Future Network Services
• Task 1 has completed M14.2 Future Network Services Specification. All JRA2 SDN use cases are now defined and
analysed
• Task 2 has completed M14.1 Software component repository and initial requirements to features matrix. A
software development plan is in place, implementation has started with SDN BoD and SDN IP use cases
• The activity is in now in existing hardware/software testing phase (T1-T3) and software development phase (T2)
(for requirements not met by existing controllers)
• Current JRA2 developments related to the consolidation of services communicated to the product management
team and SA3
• JRA3: Trust and Identity Reseacrh
• JRA3T1: Presentation of eduKEEP at I2 TechEx, positive feedback
• JRA3T2: Two disccussion sessions for OIDC federations (at IIW and I2 TechEx)
• JRA3T3: ​GNTB ideas and work done so far presented at the ‘ZKI Verzeichnisdienste Herbsttreffen’ ​(German IdPs)
Networks ∙ Services ∙ People
www.geant.org
20
Some activities highlights/lowlights (cont’d)
• NA1: Project Management and Coordination
•
•
•
•
1st Quarterly Management Report on time.
GN4-1 grant agreement was signed, next step FPA/SGA amendment to add Latvia
GN4 Symposium early March in Vienna.
Managing People and Performance in Remote Teams (MPiVIT ) Training
• NA2: Communications and Promotion
• CONNECT gone to print, due out next week; next issue planned for Jan/Feb timeframe.
• Preparing for ICT (21-22 Oct); invited users MD-PAEDIGREE and CARDIOPROOF - these 2 projects are about to
create the first Big Data and Model-Driven decision support system for paediatrics, connecting 7 hospitals across
Europe.
• Global PR Network - a visual blog platform to demonstrate the impact of R&E networks around the world (led by
AARNet)
• Case for NREN portal - regional projects and GÉANT
• Services and JRA marketing/comms planning - esp. Vidyo service, Open Paris, Federation as a service, GTS, CBP.
• TF-CPR meeting in Cambridge, 28-30 October
• Building a responsive website for GEANT which incorporates the project information and activities as part of this.
• Schedule of web work including integration of web functionality, establishing wiki look and feel/branding for TF
and other "collaborative working", review microsites.
Networks ∙ Services ∙ People
www.geant.org
21
Some activities highlights/lowlights (cont’d)
• NA3: Status and Trends
• NA3 T1 2015 data is collected and section authors from community recruited (1 outstanding). Relevant data
distributed to the section authors
• NA3 T2 & T3 regular meetings leading to deliverables
• NA3 T4 full programme of TF and SIG meetings running including cross groups meetings and workshops.
• NA4: International Business Development
• The interconnection between GÉANT and ESA’s Copernicus Ground Segment network has been agreed (via DFN)
and contracts are at signature
• A birds-of-a-feather session on Science Engagement has been co-organised at SC15 along with Internet2 and ESnet
• A number of NREN visits have taken place including a trip to ESnet in Berkeley –outcomes focussed on closer
working relationships for large international users
• A contract has been agreed with CERN to provide a second 100Gbps Lambda service between Geneva and
Budapest
• A new interconnection with the Japanese NREN, SINET is being established via 20Gbps of SINET-funded capacity
from Tokyo-London. GÉANT is assisting with hosting a SINET router in London
• GÉANT was represented at the EGI Forum in Bari, Italy –one area of interest is a discussion of plans for the Open
Science Cloud (outcome TBD)
Networks ∙ Services ∙ People
www.geant.org
22