What has been achieved since last meeting?

Download Report

Transcript What has been achieved since last meeting?

Gemini Re-platforming Project
User Readiness Testing Overview
June 2012
Introduction
The purpose of this presentation is to provide recommendations to
Gemini System External Users on areas to test when participating
in GRP User Readiness Testing including technical guidance on
how to amend the command file on User’s API Clients as
discussed at the May UKLC.
External User Testing & Cutover Plan
KEY
GRP/IAP Project Activities
Recommended External User Testing
Optional External User Testing
OAT2
PT
Prep.
OAT2
Perf.
Test
UAT
User Acceptance Testing
Prep.
SIT
Prep.
ST
Prep.
App.
Porting
UT Prep.
System Testing
System Integration
Testing
Implementation Planning
Dress Rehearsals
C Early Life Support
O
12 wks
Plan and implement necessary changes required
for readiness testing. Plan and prepare business
users for readiness testing.
Application Porting &
Unit Test
Recommended Readiness
Testing Preparation
Recommended
Readiness
Testing
Recommended readiness testing required for
validating External User connectivity to upgraded
Gemini infrastructure.
Optional Functional
Testing Preparation
Optional
Functional
Testing
Optional functional testing to provide additional
assurances of no functional change within Gemini
(Registration of participation required).
Evn. Build
Environment Build
Prep.
Cutover
Preparation
Build
Infrastructure Build
Preparation
& OAT1
C
O
Cutover to upgraded Gemini.
OCT
NOV
DEC
JAN
2012
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
Winter
JAN
FEB MAR APR MAY JUN
2013
Period
DEC
JUL
AUG SEP
Confidence
Start-up
External User Test Requirements
 GRP is replacing technology not re-writing the application; the Gemini
service will be unchanged, system functionality will remain ‘as is’ and
the look and feel of screens will remain the same.
 The GRP Project Team have conducted extensive testing of the new
Gemini design through Build, System Testing and comprehensive
User Acceptance Testing is planned for a period of 3 months starting
late August 2012.
 Gemini functionality is known to be unaffected. As consequence of
the infrastructure upgrade and relocation to Xoserve’s data centres, it
is recommended that all external users participate in the readiness
testing stage of the project.
Recommended Readiness Tests

External Users will be required to make minor amendments to a
command file on their API Clients to enable connection to the replatformed system (refer to Appendix 1) and further changes will be
required to establish connectivity to the new Gemini environment
(refer to Appendix 2)

Xoserve recommends all External Users to perform the following
tests during Readiness Testing (test cases shall be provided):
1.
2.
3.
4.
5.
On-line screen access and printout
API connectivity and run
File transfer
IX and XP1 connectivity
Connection to legacy Gemini and re-platformed Gemini
Optional Functional Tests
• Gemini functionality is known to be unaffected, therefore there is no
requirement for External Users to conduct Gemini functionality
testing.
• GRP will provide support to registered external users wishing to
conduct optional functional tests to gain additional assurance and
confidence.
• Optional Functional Testing is planned from 21st January 2013 – 1st
March 2013.
External User Testing Registration
• Xoserve welcomes External Users working with the GRP Project
Team to define a range of tests to be performed during Readiness
Testing.
• Users are invited to register their participation in Readiness Testing
by contacting .box.xoserve.GRPcommunications.com by 1st
September 2012.
• Users requiring additional assurances and wish to participate in
Optional Functional Testing are invited to discuss and register their
participation by contacting .box.xoserve.GRPcommunications.com by
1st August 2012.
Next Steps
GRP will provide an update at the UK Link Committee every month until
Post Implementation Support is complete. The current schedule of GRP
topics for discussion is as follows:
 July 2012
– Implementation Cut-over (initial discussions)
 August 2012 – Implementation Cut-over (commencement of
approval process)
If you have queries, please contact Andy Earnshaw on 0121 623 2820 or
Andrew Boyton on 0121 623 2363.
Appendix 1
Amendments on API Clients
In preparation for User Readiness Testing and Implementation,
amendments to the command file on API Clients need to be made
•
All existing URL references shall be replaced with geminints.com for
production access (see examples below):
•
Java Client .bat file or windows shortcut example:
java exit.api.client.Invoker -user API100 -password ******** -url URLREF schemaUrl URLREF
•
VB API (header) Client example:
Set objXMLHTTP = New msxml.XMLHTTPRequest
strAPIUrl = “URL REF port>/<API_URL>“
Appendix 2
Readiness Testing Changes
During the Readiness Testing Preparation stage of the project the following
changes will need to be made. Further details will be provided in the Gemini
Readiness Connectivity Guide.
Network
• New firewall rules to allow secure access to Gemini Production,
Disaster Recovery and Shipper Trials environments.
• Network and IP address routing to establish network links between
the external site and the Gemini Service.
• DNS settings to resolve URLs and IP address.
User P/C’s
• Creation of shortcuts and icons
• Citrix client installation on all User P/C’s for remote on-line access
• Deployment of developed APIs to all User P/C’s