Transcript G. Shirkov
DEVELOPMENT OF THE JINR
ENGINEERING INFRASTRUCTURE
AND
INFORMATION TECHNOLOGIES
DURING 2010-2016
G.Shirkov, JINR Chief Engineer
106th JINR Scientific Council, 25 September, 2009
G.Shirkov, JINR Scientific Council, 24.09.2009
ENGINEERING INFRASTRUCTURE
The JINR engineering infrastructure is a multi
component structure of the interacting elements.
The following subsystems have the greatest
effect on integrative properties of the entire system:
operability assurance of the JINR basic facilities;
supply of energy resources;
communication service;
safety protection of vitally important and potentially
dangerous elements of the JINR infrastructure
G.Shirkov, JINR Scientific Council, 24.09.2009
BASIC
FACILITIES
DRIBs
Development of the JINR engineering
infrastructure is the necessary condition
for the operation of basic facilities and
the basement for new facility creation
according to the 7 years programme.
The programme of basic facilities
development and creation is the subject
of the 2010-2016 years scientific
programmes of JINR Laboratories.
IBR-2M
NICA-MPD
IREN
G.Shirkov, JINR Scientific Council, 24.09.2009
ENGINEERING
INFRASTRUCTURE
SAFETY POLICY
Electric power
Radiation and
nuclear safety
Heat supply
Physical protection
Water supply
Industrial safety
Liquid nitrogen
production
Labour protection
Cooling systems
Communication service
Fire safety
G.Shirkov, JINR Scientific Council, 24.09.2009
ELECTRIC POWER
Objectives:
At present
• to increase the total power;
• to improve reliability;
• to provide independent power
supply of the basic facilities.
Plans
Goals
+ 15 MW
+ 1 transformer
LHEP (NICA)
Main step-down
P=25 MW
+ 19 MW
station 2
2 transformers + 2 transformers
DRIBs, IBR-2,
Phasotron
Main step-down
P=19 MW
station 1
2 transformers
Other
+ 4 MW from
To release the load
Moscow Channel of the main stepdown station 2
Approx. cost (2010-2016): ~ 4.3 M$
including budget: ~ 0.1 M$
G.Shirkov, JINR Scientific Council, 24.09.2009
HEAT AND WATER SUPPLY
Plan: Replacement of the outdated equipment
Goal: Reliability, modern equipment, economy
Activities to be continued:
Boiler-houses and heat network:
• Automation of boiler-houses.
• Replacement of the steamboiler in the east boiler-house.
• Reconstruction and
replacement of the heat
network.
• Heat accounting.
Water supply:
• Enlargement and reconstruction
of the pumping-filtering station.
• Automation of the drinking water
preparation.
• Reconstruction and replacement
of the water pipes.
• Water accounting.
Approx. cost (2010-2016): ~14.1 M$
including budget: ~ 2.5 M$
G.Shirkov, JINR Scientific Council, 24.09.2009
TELEPHONY
At Present:
• Analog station (1975-1985)
• 5500 users (~3800 at JINR)
• Old network
• No additional services
(IP-telephony, etc.)
• Space requirement is ~950 m2
In the Future:
• Digital electronic station
• Scalability
• Optical connection
• Low cost of long distance calls
• Modern services
• Floor space and electricity saving
JINR Technical Council
(14-15.08.2009)
recommended to replace the
analog station by digital
one, to increase the level of
services, keep the
communication reliability in
emergency situation, reduce
the expenses for the station
operation.
Approx. cost: ~ 0.5 M$
G.Shirkov, JINR Scientific Council, 24.09.2009
RADIATION AND NUCLEAR
SAFETY
Objectives:
• Purchasing of devices and the equipment
for the radiation control.
• Purchasing of a mobile radiological laboratory.
• (*) Reconstruction and development of new
systems of the radiation control
(e.g. IBR-2M, NICA, IREN).
• (*) Disposal of the used radioactive sources.
• Handling with the radioactive wastes.
• Metrological maintenance of the radiation control.
• Accreditation of the radiation control laboratory.
(*) - financial means of JINR Laboratories
Approx. cost (2010-2016): ~ 0.5 M$
G.Shirkov, JINR Scientific Council, 24.09.2009
LABOUR PROTECTION AND INDUSTRIAL SAFETY
Main Goals:
•Providing safe and healthy working conditions for personnel.
•Ensuring prescribed benefits and compensation for appropriate
category of workers .
•Realization of preventive actions to avoid traumatism, industrialcaused diseases, and also emergencies and failures.
Activities to be continued:
• Certification of workplaces in regard to working conditions to validate, in particular,
available benefits and compensation for work in harmful and/or dangerous working
conditions.
• Scheduled replacement of morally and physically outdated equipment and technical
devices.
• Re-equipment of the JINR Industrial and Sanitary Lab with modern instrumentation
to take more precisely measurements and online processing of parameters and
levels of the harmful and dangerous production factors.
• Technical upgrade of workplaces of the specialists on labor protection in the JINR
departments.
• Advanced training in the fields of labor and industrial safety for the JINR experts
and department heads. The JINR University Center can be involved in this activity.
G.Shirkov, JINR Scientific Council, 24.09.2009
FIRE SAFETY
FIRE STATION
control panel
GOALS:
• Re-equipment of the fire
station with fire engineering.
• Modern control panel (GSM,
JINR
large covering area, etc.).
• Gradual replacement of
15000 enunciators
the RID-1 enunciators
• Persistent activities to
maintain the JINR infrastructure
including ~3500 RID-1
in accordance with the fire
which have to be replaced
safety requirements.
7 automatic gas
fire-fighting systems
Approx. cost
(2010-2016): ~ 2 M$
G.Shirkov, JINR Scientific Council, 24.09.2009
SUMMARY
Preliminary estimate of the financing for the
programme of JINR engineering infrastructure
development in 2010-2016
Budget, M$ Off-budget, M$ TOTAL, M$
Electric power
0.1
4.3
4.4
Heat and water supply
2.5
11.6
14.1
Telephony
0.5
-
0.5
Radiation and nuclear safety
0.5
-
0.5
Industrial safety and labour
protection
2.0
-
2.0
Fire safety
2.0
-
2.0
7.6
15.9
23.5
TOTAL, M$
G.Shirkov, JINR Scientific Council, 24.09.2009
INFORMATION TECHNOLOGIES
The working group at the JINR Technical
Council was formed to analyze the current
status, usage efficiency and plans of
development of Information and Computing
infrastructure and communication services:
• telecommunication data links
• local area network
• computing power and data storage
• telephony
The aim of this working group is to prepare
recommendation directed to the effective
usage of these systems as a part of general
Institute engineering and information
infrastructure development strategy.
The Laboratory of
Information Technologies
Main Tasks:
• Provision of JINR and its Member States with
high-speed telecommunication data links
• Maintenance of a high-speed, reliable and
protected local area network (LAN) of JINR
• Further development of the Central Information
and Computing Complex (CICC)
• Maintenance of the JINR Grid-segment
• Development and support of information
systems with web-interface: thematic portals,
paperless document circulation, workshop and
conference sites, etc.
• Development of general Institute strategy and
further implementation of the licensed software
Recent significant results
JINR - Moscow communication channel
The channel has been launched in 2009 with a capacity of 20 Gbps. The mentioned technologies allow
one to create up to 72 channels of 10 Gbps each, and to raise the total throughput up to 720 Gbps.
The project is realized in cooperation by JINR, RSCC, NORTEL, JET Infosystems, RosNIIROS, the
Computer Networks Interaction Center “MCK-IX”
Central Information and Computing Complex (CICC) upgrade
During the last year the CICC performance was increased up to 2300 kSI2K (60%) and the disk
storage capacity up to 400
TB (4 times)
G.Shirkov, JINR Scientific Council, 24.09.2009
COMPUTER NETWORK
Short description of
the JINR network
• 6505 computers and nodes
• 3588 users
• 7531 IP
• 1223 Remote VPN users
• 1Gbps LAN (min. 100 Mbps)
• Controllead-access at
network entrance
• General services: AFS, batch,
Grid, JINR remote access, etc.)
Local area network
• Step-by-step modernization of the
JINR Backbone – transfer to 10 Gbps
(could be started this year)
• Development and modernization of
the control system of the network
• Development of IP telephony and
other services based on JINR LAN
Traffic
Full incoming traffic during
9 months 2009 is > 300 TB
In 2010 it is expected > 1 TB
JINR – Moscow communication channel
Plans: Step-by-step increasing the total throughput
based on DWDM technology
20 Gbps (2009) → 40 Gbps (2011) → 60 Gbps (2013) →….
It will be useful to investigate a possibility of using the
channel for companies - residents of the Special Economic
Zone.
International channels
The main JINR service-provider for access to the
international networks is RBNеt. The parent
organization, the ROSNIIROS, is operating the
international channel for science and education.
They started the process of transition of the trunk
lines of these networks to the DWDM technology.
G.Shirkov, JINR Scientific Council, 24.09.2009
JINR GRID SEGMENT
RDIG (Russian Data Intensive Grid)
CPU
KSI2K
Disk, TB
FIAN
50
97
41
IHEP
304
481
132
ITEP
66
748
192
JINR
960
2415
429
MEPHI
188
454
57
SPbSU
32
143
24
PNPI
276
470
232
PSN
36
-
-
SINP
32
479
184
RRC-KI
776
2003
720
Central Information and Computing Complex (CICC)
2010-2011
2012-2013
2014-2015
2016
CPU (kSI2k)
2500
4000
7000
10000
Disk systems (TB)
1200
2000
4000
8000
Mass storage (TB)
500
2000
5000
10000
• ~85% of CICC CPU time and ~80% of CICC disk space are used by GRID (mainly LHC)
• The allocated resources for their use in JINR only should be increased constantly with development
of CICC for successful realization of JINR new home projects and JINR participation in future large
scale projects
• It is also necessary to organize in LIT series of lectures and a practical training on bases and methods
in GRID system
G.Shirkov, JINR Scientific Council, 24.09.2009
Summary
k$
2010
2011
2012
2013
2014
2015
2016
50
50
60
60
80
80
100
15
15
25
25
55
55
85
25
25
25
25
25
25
25
100
100
100
100
180
180
200
1. External communication links:
1.1 maintenance
(1)
1.2 development
1.3 one-time expenses
(2)
100
2. LAN:
2.1 maintenance
2.2 development
(3)
2.3 one-time expenses
(4)
100
3. CICC and Grid-infrastructure:
3.1 maintenance
60
40
50
60
80
80
100
3.2 development
200
120
340
430
570
590
690
3.3 one-time expenses
(5)
4. Licensed software:
5. Service acquisition and other
expenses:
Totals:
300
80
80
80
80
100
100
100
16.8
20
20
40
43.2
53.2
64.2
646.8
750
800
820
1133.2
1163.2
1364.2
(1) payments according agreement and the total cost is distributed among the JINR subdivisions
(2) laying a single mode optical cable from LIT to SCC “Dubna”
(3) large investment funds are needed along the first years during the switch to 10 GE
(4) laying high throughput optical cable between LIT and the settlement in Ratmino
(5) acquisition of long term data mass storage using tape robot
G.Shirkov, JINR Scientific Council, 24.09.2009
PROGRAMME
OF DEVELOPMENT OF THE
JINR ENGINEERING
INFRASTRUCTURE
2010-2016
The development of the engineering
infrastructure is the basis, which has to
provide effective realization of the
research programme to achieve
significant scientific results.