What is a multi-vendor GSM-R network?
Download
Report
Transcript What is a multi-vendor GSM-R network?
The road of success for implementing
a multi-vendor GSM-R ERTMS network
Turkey, a multi-vendor region linking Asia with Europe
Extensive multi-annual rollout of GSM-R lines
* Picture source: Wikipedia
1
What is a multi-vendor GSM-R
network?
Core Network
(NSS)
SCP(NS)
• NSS vendor 1
MSC(NS)
A interface
HLR(NS)
More competition
Variety to rail customers
Assurance for system
integrators
Access
Network (BSS)
M2000(HW)
BSC(HW)
• BSS vendor 2
Flexibility & innovations
in solutions
BTS(HW)
Teminals
DBS(HW)
• OPH, GPH,
Dispatchers…
(additional
vendors)
Um Interface
OPH
GPH
GPH
OPH
GPH
GPH
2
Protecting investment
…
Latest multi-vendor GSM-R Projects in
Turkey
Eskisehir-Kutahya-
Alsancak-Cumaovası
Balikesir
ETCS L2
Alstom
GSM-R core (R99):
NSN
Macro & Distributed BTS:
Full SDH Network:
Outdoor trackphones and PBX
Mobile and fixed GSM-R terminals
464 km, 42 tunnels
ETCS L2:
Thales
GSM-R core (R99):
GSM-R core (R99):
NSN
Macro and Distributed BTS: Huawei
Macro & Distributed BTS:
Full SDH Network:
366 km, 23 tunnels
GSM-R design: ETCS L2 ready
Huawei
Huawei
Huawei
Kayas-Kayseri
Full SDH Network:
Huawei
Mobile and fixed GSM-R terminals
51 km, 1 tunnel
A true multi-vendor GSM-R/ERTMS architecture for Turkey
3
NSN
Huawei
The path to multivendor GSM-R
networks
Clear public standards
Appointed Notified Bodies
Conformity Assessments
Intermediate Statement of
Verification “ISV”
specific)
DBS
tunnel
4
Harmonised Test Specification
(EU/global)
BTS
Test Specification (NoBo
Availability of Test laboratories
DBS
mountain
BTS+DBS
Shunting yard
The history of a harmonised GSM-R
Test Specification
* From B.Wendler, DB-Systel presentation at ERA CCRCC 25th October 2011
5
DB Test Specification published in
2011
Number of test cases 360
NoBo validated for completeness
Including EIRENE traceability matrix:
* From B.Wendler, DB-Systel presentation at ERA CCRCC 25th October 2011
6
ERA drives Interoperability
ERA published
final DB test specification
Draft Network Assessment specification for
review by stakeholders
Set process to arrive at a “Harmonised
GSM-R Test Specification”
7
The BSS integration into GSM-R NSS of
Turkey
Test Specification: source ERA server, DB-Systel Test
Legacy
R99 NSS
Specification
Applicable Test Cases according to Test Specification: 136
BSS integration test period: 4 months
Test execution and correctness witnessed by Alstom
8
BSS
Multi-vendor GSM-R integration results
Huawei BSS system was successfully integrated to TCDD’s
GSM-R Core Network.
The final test report was issued 30th April 2013 and ratified in
May 2013
Press Release : “The completion of the multivendor GSM-R
integration is an important project milestone for the Eskisehir-AlayuntKutahya-Balikesir (EKB) European Rail Traffic Management System
(ERTMS) Line. … Stringent GSM-R specifications and equipment
guidelines enable railways globally to setup multivendor systems such
as the one now fully integrated for the EKB High Speed line with a
total length of 464 km.“
With the integration completed TCDD takes benefits of an open, feature-rich and
competitive GSM-R multivendor market.
9
Turkey, an integrated IT rail network
Ankara – Eskisehir
Pehlivanköy Pythion
IP Cameras
SDH
Video Analysis
OMC
DWDM
Equipment implementation
Switch
Maintenance
Geo-redundant Storage
Training
OMC
Equipment implementation
Maintenance
Training
10
Ankara Sincan North
Line
SDH
OMC
Equipment implementation
Maintenance
Training
Article 5th
December 2013
NEWS flash LTE for Rail
Zhengzhou Metro
Now under
passenger operation
(26th December 2013)
11
Conclusion
Strong demand and utilization of
GSM-R outside of Europe
UIC vital role to promote GSM-R
and its evolution
Promotion campaigns in Central
Asia, South America and Africa
would help the continuation of this
success
12
HUAWEI ENTERPRISE ICT SOLUTIONS
A BETTER WAY
Copyright©2014 Huawei Technologies Co., Ltd. All Rights Reserved.
The information in this document may contain predictive statements including, without limitation, statements regarding the future financial and operating results, future product
portfolio, new technology, etc. There are a number of factors that could cause actual results and developments to differ materially from those expressed or implied in the predictive
statements. Therefore, such information is provided for reference purpose only and constitutes neither an offer nor an acceptance. Huawei may change the information at any time
without notice.