Using a Collaborative Approach to Interconnection

Download Report

Transcript Using a Collaborative Approach to Interconnection

Gas-Electric System Interface Study
OPSI Annual Meeting
October 8, 2013
Raleigh, North Carolina
Acknowledgement and Disclaimer
The EIPC appreciates and acknowledges the support of DOE for the Eastern
Interconnections Studies Project
Acknowledgement:
•
This material is based upon work supported by the Department of Energy, National Energy Technology
Laboratory, under Award Number DE-OE0000343.
Disclaimers:
•
This report was prepared as an account of work sponsored by an agency of the United States Government.
Neither the United States Government nor any agency thereof, nor any of their employees, makes any
warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness,
or usefulness of any information, apparatus, product, or process disclosed, or represents that its use
would not infringe privately owned rights. Reference herein to any specific commercial product, process,
or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply
its endorsement, recommendation, or favoring by the United States Government or any agency thereof.
The views and opinions of authors expressed herein do not necessarily state or reflect those of the United
States Government or any agency thereof.
2
Gas-Electric System Interface Study
• Participating Planning Authorities (PPAs) are: ISONE,
NYISO, PJM, IESO (Ontario, Canada), MISO (including
the Entergy system), and TVA
• Four Targets (areas to be analyzed)
• Most analytical work to be completed by a
consultant with gas industry expertise
• Stakeholder process:
– Regional stakeholder groups from each PPA
– Interconnection-wide Stakeholder Steering Committee
(SSC) continues from earlier work
– Gas Sector added to SSC with pipeline, supplier, and LDC
representatives
3
Target 1
• Develop a baseline assessment that includes
descriptions of the natural gas-electric system
interface(s) and how they impact each other
– Utilize public information and other appropriate sources
of data
– Develop a baseline of the natural gas and electric systems
interface(s) within each PPA Area and the entire Study
Region
– Assess the specific drivers of the planning process for
each of the major pipelines/LDCs in the Study Region
4
Target 2
• Evaluate the capability of the natural gas system(s)
to supply the individual and aggregate fuel
requirements from the electric power sector
– By each PPA Area and for the overall Study Region
– 5 and 10 year study horizon
– Reference Gas Demand Case and a High Gas Demand
Case
– Subject to funding availability, the same for a Low Gas
Demand Case or a different scenario
– Subject to funding availability, sensitivities defined by
stakeholders
5
Target 3
• Identify contingencies on the natural gas system
that could adversely affect electric system reliability
and vice versa
– By each PPA Area and for the overall Study Region
– 5 and 10 year study horizon
– Subject to funding availability, the same for a High Gas
Demand Case
– Subject to funding availability, the same for a Low Gas
Demand Case or a different scenario
6
Target 4
• Review operational and planning issues and any
changes in planning analysis and operations that
may be impacted by the availability or nonavailability of dual fuel capability at generating units
– Review the benefits and costs of requiring dual fuel
capacity versus the benefits and costs of gas sector
infrastructure expansion
– Review of the siting and/or permitting issues that might
affect the feasibility of one solution over the other (e.g.
dual fuel versus gas system expansion), or possibly drive
an alternative solution
7
Questions and Discussion
8