Integer Programming
Download
Report
Transcript Integer Programming
Integer Programming
• Integer programming is a solution method for many
discrete optimization problems
• Programming = Planning in this context
• Origins go back to military logistics in WWII (1940s).
• In a survey of Fortune 500 firms, 85% of those
responding said that they had used linear or integer
programming.
• Why is it so popular?
– Many different real-life situations can be modeled as integer
programs (IPs).
– There are efficient algorithms to solve IPs.
Standard form of integer program (IP)
maximize c1x1+c2x2+…+cnxn
(objective function)
subject to
a11x1+a12x2+…+a1nxn b1
(functional constraints)
a21x1+a22x2+…+a2nxn b2
….
am1x1+am2x2+…+amnxn bm
x1, x2 , …, xn Z+
(set constraints)
Note: Can also have equality or ≥ constraint
in non-standard form.
Example of Integer Program
(Production Planning-Furniture Manufacturer)
• Technological data:
Production of 1 table requires 5 ft pine, 2 ft oak, 3 hrs labor
1 chair requires 1 ft pine, 3 ft oak, 2 hrs labor
1 desk requires 9 ft pine, 4 ft oak, 5 hrs labor
• Capacities for 1 week: 1500 ft pine, 1000 ft oak,
20 employees (each works 40 hrs).
• Market data:
profit demand
table
$12/unit
40
chair
$5/unit
130
desk
$15/unit
30
• Goal: Find a production schedule for 1 week
that will maximize the profit.
Production Planning-Furniture Manufacturer:
modeling the problem as integer program
The goal can be achieved
by making appropriate decisions.
First define decision variables:
Let xt be the number of tables to be produced;
xc be the number of chairs to be produced;
xd be the number of desks to be produced.
Production Planning-Furniture Manufacturer:
modeling the problem as integer program
Objective is to maximize profit:
max 12xt + 5xc + 15xd
Functional Constraints
capacity constraints:
pine: 5xt + 1xc + 9xd 1500
oak: 2xt + 3xc + 4xd 1000
labor: 3xt + 2xc + 5xd 800
market demand constraints:
tables:
xt ≥ 40
chairs:
xc ≥ 130
desks:
xd ≥ 30
Set Constraints
xt , xc , xd Z+
Solutions to integer programs
• A solution is an assignment of values to variables.
• A feasible solution is an assignment of values to
variables such that all the constraints are satisfied.
• The objective function value of a solution is obtained
by evaluating the objective function at the given point.
• An optimal solution (assuming maximization) is one
whose objective function value is greater than or equal
to that of all other feasible solutions.
• There are efficient algorithms for finding the optimal
solutions of an integer program.
Next: IP modeling techniques
Modeling techniques:
Using binary variables
Restrictions on number of options
Contingent decisions
Variables with k possible values
Applications:
Facility Location Problem
Knapsack Problem
Example of IP: Facility Location
• A company is thinking about building new facilities in
LA and SF.
• Relevant data:
capital needed
expected profit
1. factory in LA
$6M
$9M
2. factory in SF
$3M
$5M
3. warehouse in LA
$5M
$6M
4. warehouse in SF
$2M
$4M
Total capital available for investment: $10M
• Question: Which facilities should be built
to maximize the total profit?
Example of IP: Facility Location
• Define decision variables (i = 1, 2, 3, 4):
1 if facility i is built
xi
0 if not
• Then the total expected benefit: 9x1+5x2+6x3+4x4
the total capital needed: 6x1+3x2+5x3+2x4
Summarizing, the IP model is:
max 9x1+5x2+6x3+4x4
s.t. 6x1+3x2+5x3+2x4 10
x1, x2, x3, x4 binary ( i.e., xi {0,1} )
The Facility Location Problem:
adding new requirements
• Extra requirement:
build at most one of the two warehouses.
The corresponding constraint is:
x3 +x4 1
• Extra requirement:
build at least one of the two factories.
The corresponding constraint is:
x1 +x2 ≥ 1
Modeling Technique:
Restrictions on the number of options
• Suppose in a certain problem, n different
options are considered. For i=1,…,n
1 if option i is chosen
xi
0 if not
• Restrictions: At least p and at most q of
the options can be chosen.
• The corresponding constraints are:
n
x
i 1
i
p
n
x
i 1
i
q
Modeling Technique: Contingent Decisions
Back to the facility location problem.
• Requirement: Can’t build a warehouse
unless there is a factory in the city.
The corresponding constraints are:
x3 x1 (LA)
x4 x2 (SF)
• Requirement: Can’t select option 3 unless
at least one of options 1 and 2 is selected.
The constraint:
x3 x1 + x 2
• Requirement: Can’t select option 4 unless
at least two of options 1, 2 and 3 are selected.
The constraint:
2x4 x1 + x2 + x3
More on Integer Programming and other
discrete optimization problems and
techniques:
• Math 4620
Linear and Nonlinear Programming
• Math 4630
Discrete Modeling and Optimization