Strategy TfL’s strategy to grow cycling

Download Report

Transcript Strategy TfL’s strategy to grow cycling

Heading
BASE London June 2013
TfL Sustainability Approach and
Resource management
Helen Woolston, TfL Sustainability Coordinator
Transport
Heading Strategy and Sustainability Goals
Support economic development and
population growth
Enhance the quality of life for all
Londoners
Improve the safety and security of all
Londoners
Improve transport opportunities for all
Londoners
‘’every day we will
deliver safe,
reliable, clean
sustainable and
accessible
transport’’
Reduce transport’s contribution to climate
change, and improve its resilience
Goals incorporate sustainable development principles
Heading
3
Heading
Steps 1-3: Impact, magnitude & likelihood
Will the
project, plan or
What is
What is the
Evidence and
operation have
the
What action can be
magnitude
additional notes
Guiding Question
a positive or
likelihood Ranking
taken to improve the
of the
to support the
negative
of the
impact?
impact?
assessment
impact on the
impact?
indicator?
Construction
material is unable
Will freight be
to be delivered and
transported by rail or any
taken off site by
Transporting by rail is
Negative
Moderate
High
other sustainable
train which will
being explored.
modes?
cause disruption
during the
construction phase.
How will the
impacts be
monitored and
managed?
Number of freight
movements will be
recorded and by
which mode.
4
Heading
Steps 3-4: Record Outcome of Discussions
Will the
project, plan or
What is
What is the
Evidence and
operation have
the
What action can be
magnitude
additional notes
Guiding Question
a positive or
likelihood Ranking
taken to improve the
of the
to support the
negative
of the
impact?
impact?
assessment
impact on the
impact?
indicator?
Construction
material is unable
Will freight be
to be delivered and
transported by rail or any
taken off site by
Transporting by rail is
Negative
Moderate
High
other sustainable
train which will
being explored.
modes?
cause disruption
during the
construction phase.
How will the
impacts be
monitored and
managed?
Number of freight
movements will be
recorded and by
which mode.
Delivering outcomes:
•Through Benefits Realisation Plans
•Through Critical Design Features
•Through Procurements
5
Heading
Sustainability Assessment
Economic Progress
Climate Change
Safety and Security
Quality of Life
Transport for All
Tackling congestion and improving
traffic flow
Improving productivity and
Enhancing diversity
competitiveness
100
90
80
70
Supporting regeneration and spatial
development
60
50
Tackling CO2 emissions
40
30
20
Improving access to the transport
system
Enhancing physical wellbeing
10
0
Adapting to a changing climate
Improving resource efficiency
Improving built structures and
Improving security and resilience
streetscapes
Improving transport safety
6
Heading
Resource
Use and Waste Management
•
•
•
•
•
Consolidation centres
Materials Storage
Consider moving materials and waste by sustainable transport
Sustainable design eg recycled content, local materials, minimised design
Water saving measures
7
Heading Centres
Consolidation
•
A distribution facility through which material deliveries can be channelled to
construction sites.
•
Materials can be carefully handled and stored where there are no
opportunities to do so on sites.
•
By using a central location, contractors would be able to bring and store
materials for re-use at a later stage and pick up other material/plant during
the same journey, improving the overall resource efficiency of a construction
project.
8
Heading
Materials
Storage
Contractors should consider suitable locations where to store materials and/or
equipment
Locate away from sensitive receptors (eg residents) to avoid disruption while
accessing the stores during sensitive hours
A dedicated storage area would eliminate or reduce the need to bring materials by
road each shift
9
Heading Transport of Materials and Waste
Sustainable
•
•
Distribution Service Plans
Transport by rail, barge, river
– Eg Crossrail excavated material to Wallasea Island, new RSPB reserve
10
Heading
Water
Saving Measures
•
Identified by contractor for a new project:
– Use of Siltbuster to process concrete washout to a suitable standard for
re-using wastewater for cleaning purposes or dust suppression on site
– Agreement with concrete suppliers to washout at their facilities
– Rain water harvesting to allow for re-use of water for dust suppression
and/or cleaning of welfare units, by allowing space for catchment area
when designing welfare facilities
– Use of concrete cloths as an alternative to traditional concreting in-situ
for stabilising of ground. Alternative material brings a low environmental
impact in terms of less water required, no wastage, no nuisance
generated by having to break it down when no longer needed.
11