Transcript Electrical
Assembly and Installation Industry Information Day
Electrical, Cabling, I&C Works Contract
by Sergio Orlandi & Federico Fortunato
21 May 2015
Disclaimer: The views and opinions expressed herein do not necessarily reflect those of the ITER Organization
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 1
Contract Map
ITER Organization
Construction Manager-as-Agent
Machine
Assembly
Works
Mechanical &
Piping
Works
Electrical,
I&C Works
Specialized
Works
Super
Conducting
Joints
Domestic
Agency
Works
Contractors
Special
Techniques
MCP
ASY
Tokamak
EIC
CMA
Lifting & Handling LFT
Scaffolding
SCF
Access, Plant Hire APH
Civils & Finishing CIV
SPx
Balance of Plant
Works Contracts
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
Support Contracts
IDM UID: XXXXXX
Page 2
Electrical, Cabling, I&C Works Contract
ITER Organization
Construction Manager-as-Agent
Machine
Assembly
Works
Mechanical &
Piping
Works
Electrical,
I&C Works
Specialized
Works
Super
Conducting
Joints
Domestic
Agency
Works
Contractors
Special
Techniques
MCP
ASY
Tokamak
EIC
CMA
Lifting & Handling LFT
Scaffolding
SCF
Access, Plant Hire APH
Civils & Finishing CIV
SPx
Balance of Plant
Works Contracts
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
Support Contracts
IDM UID: XXXXXX
Page 3
Table of Contents
1.
2.
3.
4.
5.
6.
Scope
Role and Responsibilities
Interfaces with other companies
Works Schedule
IO Expectations
Procurement schedule
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 4
1. SCOPE
Location of main Electrical Distribution components
Switching Networks and
Fast Discharge Units
400 kV switchyard
66 kV switchyard
Coil Power Converters
Reactive Power
Assembly and Installation Information
Day – 21 May 2015
Compensators
st
© 2015, ITER Organization
IDM UID: XXXXXX
Page 5
1. SCOPE
• Summary of components to be installed:
–
–
–
–
–
–
–
DC busbar and switching network (RUDA Supply)
Tokamak in-vessel coil busbars and switches (KODA Supply)
Access Control and Security Equipment (IO Supply)
Distribution and Control Boards (DA’s Supply)
Power and Control Cables (IO or Construction Contractor)
Cable Tray and Conduit (Construction Contractor)
Process Instrumentation and Connections (DA’s Supply)
Quantity and technical characteristics of all the
equipment to be installed will be described in the
technical specification for tendering process.
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 6
1. SCOPE
• Summary of components to be procured:
–
–
–
–
–
Supply of Power Cables (as an Option)
Supply of Signal Cables (as an Option)
Cable Trays
Electrical Conduit
Consumables
Quantity and technical characteristics of all the
equipment to be procured will be described in the
technical specification for tendering process.
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 7
DC busbar and switching network
Water cooled busbars:
• Capable to carry
up to 70 kA dc;
• Max. cross-section:
425*690 mm.
1.5 m
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 8
DC Busbar General Layout
Building 32
Bridge 1
Building 33
Building 11, L3
Bridge 2
Building 74, vertical busbars
Building 74, L3
Building 74, B2
Building 11, B2
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 9
Tokamak machine, busbars and switches layout
DC Busbars
CS/PF SN and
FDU switch
TF FDU switch
(9 units, SIC)
Total length of busbars: 10 km
120 switches up to 70 kA rating
Max. cross-section: 425*690 mm
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 10
Tokamak building: layout integration and installation
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 11
DC busbar and switching network
Switches capable to carry and break
or make, up to 70 kA dc.
Explosively actuated
circuit breaker
Discharge Resistor
Counter-pulse circuit
Bypass Switch and
Vacuum Circuit Breaker
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 12
Power cables for discharge resistors.
• FDU Power cables (400mm2, F 63mm) will connect the FDU circuit breakers
located in the Tokamak building (#11) and Diagnostic building (#74) with the
discharge resistors (FDR) located in the FD&SN Resistors building (#75).
Special, very large, coaxial cables, specifically
manufactured for the project :
In case of damage of cable during cable pulling there
will be a considerable delay in the activity
(cables not available on the market)
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 13
FD and Switching Network Resistor Building
Discharge Resistor each
Module weight 4.5 Ton
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 14
In-Vessel Coil (IVC) Power Supply (PS) Busbar
The main Installation Issue is the management of the interface with the
other contractors. These Busbar will be installed in a very crowded area.
Total Length of the The IVC Busbar is 1200 meter
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 15
In-Vessel Coil (IVC) Power Supply (PS) Busbar
Tokamak Building Level L2
An example of very crowded area.
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 16
Access Control and Security Equipment
•
CCTV Cameras
–
•
•
•
•
•
•
Site wide system with ~200 controlled
(Internal and External including Infra-red)
doors and associated devices
Access Control devices
Telephones (Mobile & Fixed)
Emergency Devices
Sounders / Semaphores
Public Address speakers
Motion detectors
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 17
Distribution and Control Board
Special Skill for
re-engineering and
re-works
inside distribution
and control board
to manage possible
field change
Quantity of Distribution and Control Board is ~ 4 000
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 18
Example of Distribution and Control Board Layout
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 19
Power Cables LV and MV
•
•
•
Quantity and technical characteristics of all the Power Cables to be procured (as
an Option) will be described in the technical specification for tendering process.
All the cable to be installed are Industry Standard cable
The most used type of cables are:
– Single Conductor Overall Shield or Unshielded,
Typical Sections from 120mm2 up to 400mm2
– Multiwire Overall Shield or Multiwire Unshielded,
Typical Sections from 1.5mm2 up to 120mm2
• Will be IO-CT responsibility provide to contractors:
– Production of Cable procurement Specification
– Cable BOM
– Cable Routing Cards (for cable pulling activities)
– Cable Termination Cards
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 20
Control and Instrumentation Cables
•
•
•
•
Ethernet, FiledBUS, Thermocouple, Coaxial and Fibre Optic cables
All the cable to be installed are Industry Standard cable
Quantity and technical characteristics of all the Control Cables to be procured (as an
Option) will be described in the technical specification for tendering process.
All the cable to be installed are Industry Standard cable The most used type of cables
are:
–
–
–
–
Individually Shielded Twisted Pairs / Overall Shield
Thermocouple Compensating Cable
Ethernet Cable / Fieldbus cable
Fiber Optic Single Mode / Multimode
• Will be IO-CT responsibility provide to contractors:
– Production of Cable procurement Specification
– Cable BOM
– Cable Routing Cards (for cable pulling activities)
– Cable Termination CardsAssembly and Installation Information Day – 21 May 2015
st
© 2015, ITER Organization
IDM UID: XXXXXX
Page 21
Quantity of Power and Control Cables to be Installed
ITER Cables
Number of cables
Power Cables
22000
Instrumentation and control Cables
83000
Fiber Optic Cable
15000
Average length of cable
100 m
Estimated cable length
12 000 km
Estimated cable tray length
40 km
Procurement of cables as Option with quantities to be fixed
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 22
Cable routing inside the Tokamak building
120 m
The Integrated Installation Sequences will be defined by IO/CMA
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 23
Cable routing outside the Tokamak building
800 m
300 m
The Integrated Installation Sequences will be defined by IO/CMA
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 24
Functionality for PIC Cables
•
•
•
•
After the cable pulling, all the Cable Tray with PIC (Protection Important
Components) cables shall be added with FIRE-Wrapping
Add fire-wrapping to all cable trays, in critical rooms
The overall quantity of cable trays with fire-wrapping is around 10 km
The fire-wrapping material will be specified in the technical specification for
tendering process.
Detailed Definition of PIC Equipment will be specified in the technical
specification for tendering process
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 25
Connection of Process Instrument
•
•
•
•
Instrument Panel/Rack
Flow Instruments/Switch
Pressure Instruments/Switch
Temperature Instrument/Switch
•
•
•
•
Level Instruments/Switch
Others Instruments
ON/OFF Valves
Control Valve
~72000 Digital and ~32000 Analog Signal
• Will be IO-CT responsibility provide to contractors:
– Instrument BOM
– Installation Specification
– Typical Installation Drawing
For each kind of Instrument to be installed
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 26
2. Role and Responsibilities
• The Contractor shall be responsible for the
following activities:
–
–
–
–
–
Provide temporary systems (Utilities and Facilities)
Install new Systems & Components
Install I&C Components
Pull cables
Perform cable connection including head preparation and
tagging
– Procure necessary consumables
– Perform own QC, final installation tests and verification
– Issue as-built documentation
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 27
Contract Functional Interfaces
Support
Management
Co-activity
ITER Organization
Construction Manager-as-Agent
Domestic
Agency
Works
Contractors
Machine
Assembly
Works
Mechanical &
Piping
Works
Electrical,
I&C Works
Specialized
Works
Super
Conducting
Joints
Lifting & Handling
Scaffolding
Access, Plant Hire
Cryogenics
Civils & Finishing
Special
Techniques
Tokamak
Balance of Plant
Works Contracts
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
Support Contracts
IDM UID: XXXXXX
Page 28
3. Interfaces with other companies
• All works managed by IO and CMA
• Main Domestic Agency Installation Contracts:
– PPEN HV, SSEN HV substations and Main AC Distribution Building (EUDA)
• May 2016 – March 2020
– Building Emergency Power Supply Buildings (EUDA)
• May 2016 – October 2019
– Magnet Power Converter (CNDA and KODA)
• December 2016 – September 2020
– Reactive Power Compensators Area (CNDA)
• April 2017 – October 2019
• Mechanical & Piping Contract
– For scope see related presentation and next slide.
• Supplied Services, Facilities and Utilities
– See presentation on site organization
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 29
Process Instrument connection
Scope of electrical works for instrument will be to the nipple on the root
valves located on the process line installed by the mechanical
contractor.
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 30
5. Contractor Furnished Equipment and Material
• Option for procurement of cables
–
The contract will include an option to supply part of the cabling to be installed as part
of a centralized procurement strategy.
– This will include:
400/230 V Power Socket panel
Lights
• Low voltage power
Lighting Panels
• Instrumentation and control cables
Terminals and Connections
• Network cables (including fiber optic)
Cable/Wiring Core Ferruling
Labels
• Terminations for above
Flexible Conduit
Cable Glands
Anti-corrosive paste for
busbars/converters connection interface
Cable Tray/Conduit/Trunking (limited)
Earthing and Bonding
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 31
IO Requirements
• Safety Requirements
– ITER is submitted to Nuclear Licensing process.
– For Protection Important Components, the French Nuclear
Regulation must be observed.
• Contractors and Subcontractors must comply with :
– Order 7th February 2012 for protection important
components (PIC) and protection important activities (PIA).
– Compliance must be demonstrated in the chain of
subcontractors.
– All activities are subject to supervision by the Nuclear
Operator.
• Quality Assurance (QA)
– Contractors shall have an ITER approved QA Program or
ISO 9001 accredited quality system.
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
Towards Zero
Accidents
IDM UID: XXXXXX
Page 32
Time Distribution of Works by Contract
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 33
Assembly and Installation Industry Information Day
Thank you for your attention
Please send all questions to:
[email protected]
Replies to all questions received within 2 weeks shall be published on
the ITER web site and notified to all attendees
Assembly and Installation Information Day – 21st May 2015
© 2015, ITER Organization
IDM UID: XXXXXX
Page 34