CMS physicists meeting, Dec 08

Download Report

Transcript CMS physicists meeting, Dec 08

News from the LHC
Jörg Wenninger
Beams Department
Operations group
CMS Meeting
LHC beam
commissioning
S34 incident
and consequences
December 2008
1
Part I
Beam !
2
Beam Commissioning Phases 1 to 3
Pre-10.09.2008 beam tests : code name ‘synchronization tests’
Commission
the injection elements of the LHC.
Commission
controls and instrumentation of the LHC ring.
Check
Make
magnetic field (predictions), alignment and apertures.
sure we do not screw up too much on the 10th …
 The
tests were interleaved with commissioning of the remaining magnets
& circuits.
 Note
the first time we could run all magnets together :
The evening of September 9th !!
3
Synch. test no. 1
8-11 August 08
Beam 2 stopped
on collimator
4
Synch. Test no. 2
Beam 1 stopped
on collimator
22-25 August 08
Beam 2 stopped
on collimator
5
5-8 Sept. 08
9 Sept. 08
Synch. Test no. 3
Beam 1 stopped
on collimator
Beam 2 to
dump line
6
Polarity Errors
In single pass (trajectory) mode, focusing errors can be located by:

launching controlled trajectory oscillations

comparing the measurement with the predictions
>> Identified a number of sign errors – some rather severe (see below) !
Example of a polarity inversion of a main quadrupole (IR7). This error would have spoiled the 10th
September show – very difficult to get past such an error.
Histogram : measured trajectory change
Points : model
Polarity error
Beam 2
7
Aperture
A great relief : the aperture was very good – no buckled bellows & Co.
Example for sector 78 : the aperture is probed by increasing trajectory oscillation amplitudes until
losses appear. On the figures one sees the excursions of sample trajectories until losses appear.
8
And we quenched with beam…
In the very early morning of August 9th during the first test, we provoked the first
beam induced quench:

Bunch intensity ~4109 p, which is within
the expected range.
BLM signal
(beam2 side)
BLM signal
(beam1 side)
M. Sapinski
>> reduced the commissioning intensity
to ~2-3109 p.
In preparation of the 10th, a test revealed
that even with ~2109 p one can quench
– but very unlikely in normal operation due
to the large impact angle.
Preliminary results !
9
A look at the first quench : magnet perspective
4
1
3
1. Voltage = 0, no resistance, magnet is
superconducting.
2. Beam impact, Voltage != 0 : resistive area in
the magnet !
3. Voltage back to 0 – magnet has recovered
spontaneously – very little energy deposition !
4. Voltage != 0 : protection systems enter the
game and force-quench the magnet etc…
2
Voltage (V)
across magnet
400 ms
10
A crazy, but so successful D-Day !!!
11
September 10th
Despite the presence of an unbelievable crowd of people :
10:30
: Beam 1 around the ring (in ~ 1 hour). Beam makes ~ 3 turns.
15:00
: Beam 2 around the ring, beam makes 3-4 turns.
22:00
: Beam 2 circulates for hundreds of turns…
12
Beam 2 around the ring
1. Beam to TDI
5. Beam to IR3
2. Beam to IR7
3. Beam to IR6
4. Beam to CMS
13
Beam2 around the ring
1. Beam to TDI
5. Beam to IR3
2. Beam to IR7
6. Beam to ALICE
3. Beam to IR6
4. Beam to CMS
14
Beam2 around the ring
1. Beam to TDI
5. Beam to IR3
2. Beam to IR7
6. Beam to ALICE
3. Beam to IR6
7. Beam to ATLAS
4. Beam to CMS
8. Beam to LHCb – First Turn !
15
First Beam Around
Sept 10th 10:30 : two beam spots on a screen near ALICE indicate that the
beam has made 1 turn.
16
Beam 2 circulating – no RF
Evening of September 10th , after the crowds left :
Beam 2 makes hundreds of turns after some empirical correction (no RF)
 Turn by turn beam peak intensity
signal at the RF position monitor.
 The decay is due to the de-bunching
of the beam (bunch becomes longer
and longer – no RF).
17
Beam 2 captured by RF system
Evening/Night of September 11th
RF
RFON
RF
OFF
ON
& tuned
–
wrong
phase
Beam
wrong
2 frequency
‘captured’
18
Beam 2 on stable closed orbit
Sept 12th : Beam 2 captured, lifetime > 1 and closed orbit corrected.
Looking very good…
RF frequency is not (yet) correct:
average hor. orbit is negative…
19
Electrical transformer problem…
Late evening of Friday Sept. 12th an old LEP HV transformer in point 8 failed,
leading to a stop of the cryogenics – LHC ‘off’.

TS/EL had no spare (!), but a spare CMS transformer was recuperated and
installed during the weekend.

Due to various other problems, the cryogenic system was only completely back
for the Friday 19th.

In the meantime, access and commissioning of remaining circuits wherever
cryogenics conditions were OK.

Late in the morning of Sept. 19th the last dipole circuit of sector 3-4 is
commissioned to 5.5 TeV…
20
Status on the morning of Sept. 19th
Beam 2 well advanced:

Beam captured in RF system, good orbit and lifetimes of hours.

Optics in ‘reasonable’ shape, preparing for refinements.
Beam 1 in same state as 10th:

First turn established, beam in for 3-4 turns.
Objectives for the weekend

Bring beam 1 to same level as beam 2.

Improve measurement and correction on beam 2.

Try to circulate both beams together …
But….
21
Part II
S34 Incident
or
…what you can do with 200 MJ
22
And then came September 19th 11:18…
During the last commissioning step of main dipole circuit in sector 34, to 9.3kA :

At 8.7kA, development of resistive zone in the dipole bus bar between Q24.R3 and
the neighboring dipole.

Most likely an electrical arc developed which punctured the helium enclosure.
 Large amounts of Helium were released into the insulating vacuum.

Rapid pressure rise inside the LHC magnets
– Large pressure wave travelled along the accelerator both ways.
– Self actuating relief valves opened but could not handle all.
– Large forces exerted on the vacuum barriers located every 2 cells.
– These forces displaced several quadrupoles by up to ~50 cm.
– Connections to the cryogenic line damaged in some places.
– Beam ‘vacuum’ to atmospheric pressure
23
Dipole
7 TeV
• 8.33 T
• 11850 A
• 7M J
24
Inter-connection
Vac. chamber
Dipole busbar
25
Damage zone
Insulating vacuum barrier every 2 cells in the arc




Some moved
Considerable collateral damage over few hundred metres
Contamination by soot and debris (magnetic !) of vacuum chambers – extends beyond
mechanical damage zone.
Damage to super-insulation blankets
Large release of helium into the tunnel (6 of 15 tons)
26
Displacements
27
Collateral damage
S. Myers AB depart. meeting
28
Intermezzo : Quench Protection

A ‚quench‘ is the phase transition from the super-conducting to a normal
conducting state.

Quenches are initiated by an energy in the order of few mJ
–
–
–
–

movement of the superconductor (friction and heat dissipation),
beam losses,
cooling failures,
any other heat sources...
When part of a magnet quenches, the conductor becomes resistive, which can
lead to excessive local energy deposition due to the appearance of Ohmic
losses. To protect the magnet:
– the quench must be detected.
– the energy in the magnet /electrical circuit must be extracted.
– the magnet current has to be switched off within << 1 second.
29
Quench Detection and Energy Discharge
Power
converter
Dump
resistor
1.
2.
3.
4.
5.
Dump
resistor
The quench is detected based on voltage measurements over the coils (U_mag_A, U_mag_B).
The energy is distributed over the entire magnet by force-quenching with quench heaters.
The power converter is switched off.
The current within the quenched magnet decays in < 200 ms, circuit current now flows through
the ‚bypass‘ diode that can stand the current for 100-200 s.
The circuit current/energy is discharged into the dump resistors.
30
Dump Resistors
Those large air-cooled resistors can absorb the 1 GJ stored in a dipole magnet
circuit (they heat up to few hundred degrees Celsius).
31
Busbar Protection

The individual interconnects are not protected.
 The entire busbar (i.e. all magnet interconnections of a given electrical circuit)
is protected by a global protection system. In case of a busbar quench:
– the power converter is switched off,
– the dump resistor switch is opened to discharge the energy.
– the busbar is designed to cope with the discharge time of ~ 200 s.

A look at the quench protection system data for the incident revealed that:
1)
a busbar quench was developing,
2)
suddenly the voltage over the busbar increased dramatically, leading to a fault of
the power converter (over-voltage),
3)
followed by the dramatic energy release (~ 200 MJ) in the cold mass.
>> Most likely cause : an electric arc due to rupture of the interconnection.
Unfortunately this is difficult to prove, since the whole dipole
interconnect was ‚vaporised‘ during the event !
32
Busbar interconnection
Interconnection resistance ~ 0.35 nW
33
Welded interconnection
34
Main Dipole / Quadrupole Interconnection
Note that the connection
is NOT clamped !
Splice insulation Length
He II @ 1.9K, 1Bar
current
current
Bus Bar’s Insulation
Heat exchange with He II
Favored hypothesis for the S34 incident cause :
• Temperature increase due to an excessive resistance (estimate ~ 200 nW).
• Superconductor quenches and becomes resistive at high current
(temperature increase due to the resistance).
• Up to a certain current, the Copper can take it (cooled by the He II).
• Beyond a certain current, ‘run-away’ of the temperature, splice opens,
electrical arc …
35
Early Warning Signs

Following the incident, a closer look at the logged cryogenic data
(temperatures and valve states) clearly indicated a heat source in the cell
that was at the origin of the S34 incident:

The data revealed the presence of a ~ 200 nW resistance in that cell (before the
incident): most likely the interconnect quality.
>> Logged data recorded during commissioning of the 7 other sectors was
checked to locate other potential problems : a hint was found in a cell of S12.

Controlled calorimetric measurements (at different magnet currents) were
started in the sectors that are still available to:

Localize cells with current dependent heat sources.
 Confirm the source and localize precisely with electrical measurements.
36
Relative temperature, increase from 1.9 K
Calorimetric analysis of sectors before Sept 19
DT (mk)
7 kA test on Sector 3-4, Sept 15th
7 kA test on Sector 2-3, April 14th
+40 mK
Temperatures
stabilize
Temp of Q23 keeps rising!
1h
Current in kA
For comparison, another sector, identical scales
9.3 kA test on Sector 1-2, Sept 1st
Suspicious cell
in S12
Adriaan Rijllart
-5
-10
07R1
11R1
15R1
19R1
23R1
27R1
31R1
29L2
25L2
21L2
17L2
13L2
09L2
07R6
11R6
15R6
19R6
23R6
27R6
31R6
29L7
25L7
21L7
17L7
13L7
09L7
07R7
11R7
15R7
19R7
23R7
27R7
31R7
29L8
25L8
21L8
17L8
13L8
09L8
Specific resistive heating [mW/m]
Calorimetry tests : after September 19th
40
3000 A
S1-2
5000 A
S6-7
7000 A
L. Tavian
35
100 nW
30
75 nW
25
50 nW
20
15
25 nW
10
5
0
S7-8
38
0
07R1
11R1
15R1
19R1
23R1
27R1
31R1
29L2
25L2
21L2
17L2
13L2
09L2
07R6
11R6
15R6
19R6
23R6
27R6
31R6
29L7
25L7
21L7
17L7
13L7
09L7
07R7
11R7
15R7
19R7
23R7
27R7
31R7
29L8
25L8
21L8
17L8
13L8
09L8
Specific resistive heating [mW/m]
Calorimetry tests : candidates
40
15R1
Not confirmed by electric
measurements, poor(er)
data quality
20 19R1
31R1
S1-2
31R6
S6-7
L. Tavian
35
100 nW
30
75 nW
25
50 nW
25 nW
15
10
5
S7-8
39
Electrical Measurements

S12 ‘100 nW’ calorimetric anomaly:

All interconnects of the suspected cell were checked with high precision (nW)
resistance measurement devices. Result:



All interconnects OK, all resistances consistent with 0.35 nW.
A systematic campaign of internal magnet resistance measurements was
launched. Result:

A dipole with a 100 nW resistance was found in the suspected cell.

Test bench data indicates that this resistance was already present when the
magnet was tested to 9 T/7.6 TeV.
S67 ‘50 nW’ calorimetric anomaly:

The same magnet measurements localized a dipole with a 50 nW internal
resistance.
» The resistance of those magnets arises from the internal interconnections!
» The dipole in S12 will be exchanged, for the dipole in S67 the decision is
pending…
40
Electrical measurements : the data
The Quench Threshold is 100mV during 10ms
U_1
U_2
Sampling Rate 5ms
Resolution
0.125mV
13sec, 2450 points
~4mV
Average = -0.88±0.02mV
41
Magnet resistance measurements
Magnets are powered to different current levels.
 At each step the voltage is measured to determine a possible residual
resistance of splices INSIDE each magnet.
!! Does not measure the splice resistance of the tunnel interconnects !!

60min @ 7kA
10min @ 6kA,5kA,4kA,…,0kA
Voltage-over-magnet data collection from
the Quench Protection System for accurate
resistance determination.
42
Results from measurements of all dipoles in sectors 67 & 78
Voltage (V)
Sector 67
Sector
67
Sector 78
Dipole B32.R1 with 47 nΩ
splice resistance
 Current (A)
 Current (A)
43
Measurement campaign status
S1-2
Dipole circuit
S2-3
S3-4
S4-5
T
R
M
Quadrupole circuit
T
T
R
M
IPQ (6 kA)
T
T
R
M
T: Transport
R: Repair
S5-6
S6-7
S7-8
S8-1
M: Maintenance
Done

A calorimetric and electrical measurement campaign was run into December
to cover the largest possible number of sectors a maximum before the start of
the shutdown.

A little over ½ the LHC has been checked.
44
Repair
–
–
–
–
55 magnets will be taken out by Xmas (39 dipoles, 14 SSS [quadrupole assemblies]).
Magnets will be either replaced by spares or repaired (super-insulation).
All magnets will be re-tested in SM18 before installation in sector 34.
The vacuum chambers may have to treated outside the ‘zone’ : buckled bellows and dust in
beam vacuum chamber…
– Estimate (preliminary) : March 09.
45
Consolidation : limiting pressure with
flanges as relief valves
Courtesy V.Parma
Vacuum
instrumentation
DN100
Cryogenic
inststrumentation
DN63
BPM DN100
Each SSS/quadrupole assembly:
4 DN100 ports (2 for vac.devices, 2 for BPM cable feedthrough)
1DN63 port (for cryo instrumentation)
Beam position
monitors DN100
46
Limiting Pressure
Present: 2 DN90
QV
QV
Q
SV
D
D
D
Q
QV
D
D
D
PT
Q
SV
D
D
D
Q
QV
D
D
QV
Q
D
Consolidation option B (A), for cold sectors: x9.3
QV
SV
QV
Q
SV
SV
D
D
D
Q
QV
D
D
D
PTSV
Q
SV
SV
D
D
D
Q
QV
D
D
D
SV
SV
SV
D
D
D
QV
SV
Q
Consolidation option C, for warm sectors: x40
QV
SV SV
QV
Q
D
SV
SV
D
D
SV SV SV
SV
Q
D
D
SV
D
QV
SV SV
PT
Q
D
SV SV
D
D
SV
SV
Q
QV
QV
SV
Q
47
Consolidation work
The following modifications and consolidations will be implemented:
A. Upgrade of the quench protection system for precision measurements and
protection of all interconnects : early detection of similar problems +
protection against symmetry quenches (already in the pipeline before S34)
B. Modifications of commission procedure to include cryogenic/calorimetric
information and systematic electrical measurements.
C. Improved anchoring of SSS located at vacuum barriers.
D. BPM flanges modified as ‘pressure relief valves’.
E. Addition of pressure release valves on EVERY dipole cryostat for the warm
sector.
>> E cannot be implemented for 2009 for the sectors that will be
kept cold this shutdown.
48
Summary I
Start-up with beam:
• Despite totally ,crazy’ conditions the beam start-up was excellent.
• The speed of progress with beam2 exceeded even our optimistic hopes.
• A lot was learned, but not enough to be sure that the rest of the early
commissioning will proceed as well as the first 3 days…
• Things were looking were good !
• In the operations group we are analysing what could have been done
better and we are working hard to make the next start-up even more
efficient !
49
Summary II
Sector 34 incident:
• Revealed a weakness in the magnet protection system which did not cover
dramatic bus-bar/interconnect incidents.
• Repair or replacement of ~ 55 magnets will take most of the shutdown.
• Ongoing work to analyse consequences/fix the vacuum chamber ‘pollution’
in the sector.
Search for local resistances:
• Powerful calorimetric and electric measurements were validated to localize
suspicious electrical resistances.
• A little over half the ring could be checked. No other bad interconnect was
localized, but two dipoles with internal resistances were identified:
• Sector 12 / 15R1: resistance of ~ 90 nW
>> dipole will be replaced.
• Sector 67 / 31R6: resistance of ~ 50 nW.
50
Summary III
Repair & consolidation:
• Improvements in the quench protection system, ready summer 2009,
and a careful monitoring of the temperatures should provide early
warning/protection against similar events.
• Improved anchoring of SSS at vacuum barriers.
• The pressure relief system will be improved : full implementation on
warm, partial on cold sectors.
! The pressure relief systems will limit mechanical damage, but cannot
help against vacuum chamber pollution (if the beam vacuum is affected).
>> also an issue for beam induced damage !!
51
The plan for 2009
Running scenarios will be worked
out in February in Chamonix:
• Energy(ies)
• Intensity
LHC cold
Last magnet goes
into sector 34
2009
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Removal of damaged magnets
Cleaning and repair
Cold testing
Reinstallation
Interconnection
Pressure testing
Cool down
52
53
The CERN Accelerator Complex
5
LHC
4
Beam 1
Beam 2
7
3
TI8
SPS
2 TI2
protons
LINACS
6
Booster
8
1
CPS
Ions
LEIR
Linac
PSB
CPS
SPS
LHC
Top energy/GeV
Circumference/m
0.12
30
1.4
157
26
628 = 4 PSB
450
6’911 = 11 x PS
7000
26’657 = 27/7 x SPS
Note the energy gain/machine of 10 to 20 – and not more !
The gain is typical for the useful range of magnets !!!
54
Injection Regions
First difficulty : get past the tight and crowed injection regions near ALICE (Beam 1) and
LHCb (Beam 2)

Injected beam is brought parallel to LHC beam by magnetic septa (MSI).

Injected beam is kicked vertically down onto the LHC plane by fast kicker magnets
(MKI).

Protection block (TDI, 4 m long) to protect downstream elements from mis-injections.
Right of IP8 (H plane)
TI 8
D2 Q4
TDI
(MKI +90˚)
Q5
5xMKI
5xMSI
55
Beam Dump
Both dumps were nearly fully commissioned for 450 GeV.
BTVDD
56
Another…
57
LHC Arc ‘Cell’
•
•
•
23 regular cells in each arc
106.9m long, made from two 53.45m long half-cells
Half cell
– 3 15m cryodipole magnets, each with spool-piece correctors
– 1 Short Straight Section (~6m long)
• Quadrupole and lattice corrector magnets
58