Recent cross-wiring issue and implication for circuits protection
Download
Report
Transcript Recent cross-wiring issue and implication for circuits protection
Upgrades and Activities of 13kA EE
systems during LS1
Bozhidar Panev TE-MPE-EE 23.11.2012
Installation of Snubber capacitors in RQD/F EE systems
• The benefit: To suppress the voltage transient perturbations in the
circuits during switch commutation and to make the opening process
lighter by reducing the electrical arc existence
• All 16 EE systems of RQD/F circuits will be equipped. Four snubber
capacitors per system + associated auxiliary boards in total 64
snubbers and 64 boards
• All parts and components have been manufactured, commissioned,
packed and prepared to be transported to each UA area. Transport will
be required
2
Installation of Snubber capacitors in RQD/F EE systems
• Difficulties during the installation:
Snubber Capacitors - RQF
Limited space inside the switch
acoustic shield housing
The installation of snubbers on
the upper stage requires to lift
and handle heavy stuff at 2m
height over the ground.
Snubber Capacitors - RQD
2.0m
• The last issue has been discussed with S. Pelletier from transport
service in the presence of a safety person. The accepted solution is to
use a lifting mechanism, fixed at the ceiling inside of the switch housing.
• The IHEP team (4 experienced persons) is scheduled to perform the
work. All of them have previously participated in the EE systems
maintenance and the RB snubbers installation
• The work is planed to start in May 2013. The time estimation is 3 days
per one UA area 24 days in total
3
New arc chambers for RQD/F EE switches
• It will be combined with snubber capacitors installation. Two sectors
(S12 and S23) are already equipped. Still 12 EE systems 96 arc
chambers have to be replaced.
• The currently installed arc chambers up to 200V arc feeding voltage
(design specification and hard limit)
• The new arc chambers:
Identical design as in the dipole EE
systems
Good performance up to 1050V (arc
feeding voltage) is guaranteed
All chambers have been delivered to
CERN earlier this year
• The activity does not require the transport service
4
Mechanical modification in all RB dump resistors (DQRB)
• To prevent the potential damage of
the DQRBs in case of double
amount of energy deposited in the
dump resistors
thermal
expansion
crack and short
• Difficulties mainly due to lack of
space at the end of some DQRBs
e.g. in P1, P3 and P5 the “Roman
pots” or beam pipe supports are
placed between dump resistors
Modification
• The transport service will be involved to
move temporarily some dump resistors
in order to gain enough space
•
•
•
•
53 dump resistors (16 RB EE systems + spares) will be modified.
The estimated time 3 DQRBs per day ~ 20 days totally
The activity is scheduled to start in July 2013.
The IHEP team + AGH team (3 persons) will perform the work.
5
RB Dump resistors – thermostat replacement
• The installation of new thermostat is not fully completed
Two dump resistors: one in RR73 and one in RR77 still need to
be equipped
• Difficulty:
Resistors are blocked by concrete shield and there is little
access for manipulation
• During next TS both two
places will be visited and
carefully observed
• The activity is planed to
start in Aug 2013. Expected
duration: One week
• IHEP team + AGH team will
be involved
6
Power switching relay (230V/8V) of holding coil
(RL4,6,8,10 in BCMs)
• A recent inspection has found the significant erosion of contacts due
to electrical arc. The risk to burn the holding coil increases.
• In the beginning of closing process I = 22A(230V) then switched to
0.5A(8V)
• As a part of preventive maintenance it has been decided to replace
these relays in all EE systems (RB and RQD/F)
• 8 relays per EE system 32 systems 256 relays in total
• The new selected relay (still under
consideration):
Better contact material - AgSnO2
instead of AgCdO
Maximum peak current - (4 times
higher)
• TE-MPE-EE staff will perform the
activity.
7
Dump resistors re-configuration
• The expected new conditions in
LHC after LS1 require a new
configuration of the dump
resistors in RB and RQD/F EE
systems
• RB_EE system requires only
cable reconnection to get all
three resistors in parallel
Now
After LS1
I
I
R
Requiv. » 138mW
t » 55s
R
R
R
R
R
Requiv. » 70mW
t » 102 s
• RQD/F_EE system dump resistor internal modification
- Curren situation: R = 7.7 + 4*5.0 + 1.2 = 28.9 mΩ (51 MQ / circuit)
R = 6.6 + 4*5.0 + 1.2 = 27.8 mΩ (47 MQ / circuit)
- After LS1: R = 7.7 + 2*5.0 + 1.2 = 18.9 mΩ (51 MQ / circuit)
R = 6.6 + 2*5.0 + 1.2 = 17.8 mΩ (47 MQ / circuit)
t » 9.8s
t » 9.4s
t » 15.1s
t » 14.77s
• The activity is planed to start in Sep. and will take 2 weeks
• The work will be executed by IHEP team + AGH team + TE-MPE-EE
8
RB Dump resistor – 4 water cooling stations relocation
in P1 and P5
• The reason: Installation of new collimators in the place which, currently
occupied by water cooling station
• Cooling stations together with adjacent electrical cupboards will be
moved on top of one of the RB-dump resistors. Such a installation has
already been done in P3
• EN-CV and EN-EL will be involved
• The activity is scheduled to start in Aug. and it will take 2 weeks.
• The participants AGH team (3 persons) + TE-MPE-EE
9
Water cooled cable exchange of some 13kA EE systems
• Cracks in the rubber of the water cooled cables have been observed
close to the connection point with “busway”
• All cables susceptible of containing such a cracks will be replaced:
P4 right RB, RQD/F
P6 left & right RB, RQD/F
P8 left and right RB, RQD/F
• The work will be performed by EN-EL.
• The presence of a EE specialist is
needed during establishing the
connection with the switch “busway”
• The voltage drop measured across the
connection point must determine the
resistance of ≈ 0.6 μΩ
Modification in SUM_Fault electronic board
•
•
•
•
A few suspected diodes will be replaced
The signal “ST_OPENFAIL” will be removed by hardware modification
32 PCBs will be modified 1 per EE system
TE-MPE-EE staff will perform the work.
10
General maintenance of all 13kA EE systems
• Micro-switches(S1/2/3/4) functional check
• Air gaps of the breakers (∆1 and ∆2) measurement and adjustment
• Mechanical pressure verification of the main contacts adjustment if
required
• Cleaning of the main and arcing contacts
• Time delay check (600ms and 340ms) only RB EE system
• Verification of all bolted electrical connection
• All 32 EE systems (RB and RQD/F)
• The activity is scheduled for Sep.-Oct. 2013 and it will take ~1.5 months
• The work will be performed by IHEP team + AGH team supervised by
TE-MPE-EE
11
Recourses and Conclusions
Activity
Snubbers RQD/F
DQRB mechanical
modification
Water cooling station
relocation
Time estimation
2 EE sys. / 3 days
Total
24 days
~ 2 weeks
Executors
IHEP team (4 persons)
IHEP team (4 persons)
AGH team (3 persons)
AGH team (3 persons)
TE-MPE-EE staff
IHEP team (4 persons)
AGH team (3 persons)
IHEP team (4 persons)
AGH team (3 persons)
TE-MPE-EE staff
3 DQRBs / 1 day
~ 20 days
1 station / 2 days
~ 2 weeks
2 weeks
TE-MPE-EE staff
2013
1 week
TE-MPE-EE staff
IHEP team (4 persons)
TE-MPE-EE staff
2013
Thermostats in P7
Dump resistors
reconfiguration
3 EE sys / 1 day
Power relay replacement
of the holding coil
3 EE sys / 1 day
SUM_FLT Electronic
board modification
General
maintenance
1 EE sys / 1.5 days
~ 1.5 months
May-June 2013
Jul-13
July-Aug. 2013
Aug-13
Sep-13
Sep.-Oct. 2013
• The main contract with IHEP is ready for approval but not yet signed
• As a back up solution The AGH team can handle the work but some
training is needed in order to get more familiar with the EE systems. In
that scenario at least 30% more time must be added
• All technical details are determined and most of the equipment is already
available
• All issues are included in Katy’s general planning
• CERN supervision team is: Mathieu, Knud, Bozhidar
12
Thank You