Subcommittee 10
2015 Workgroup formed to address rewrite:
Current Status of API Bulletin E3
API Bulletin E3, 1st Edition, Environmental Guidance
Document: “Well Abandonment and Inactive Well Practices
for U.S. Exploration and Production Operations”, January
1993
Reaffirmed 2000
This new document will supersede API Bulletin E3, 1st Edition
Workgroup:
D Mueller, G Benge, C Gardner, E Cunningham, A Parlipiano, D Stiles,
A Garnier, J Heathman, J Edwards, L Galey, J Reid
The charge:
Rewrite Bulletin E3 as a Guideline Document:
Well Abandonment Practices API Bulletin E3 2nd Edition xxxx, 2016
An abandonment cementing and barrier placement guideline to reside with
SC 10
This will not replace upcoming Well Abandonment RP – Joe Shine WG 05
Rewrite will provide a guideline for the permanent and temporary
abandonment of active and inactive wells:
Provide a general approach and design considerations for well
abandonment
Placement and verification of cement plugs
Protection of useable water aquifers and isolation of hydrocarbon intervals
Does not discuss cement design
Does not address specific regulatory requirements
Not all inclusive. References to other API documents for detailed information
Summary of progress in the rewrite:
Rewrite of API Bulletin E3
SC 10 workgroup comprised of 9 Operators
Group met 4 times since summer meeting in San Francisco
Revision includes discussion of placement method(s), and use of cement and
mechanical devices to set abandonment plugs
Adds a clear definition of the term “workstring”
Modified existing and/or added new well bore diagrams for different abandonment
scenarios
Reference to Standard 65-2 and other prescriptive documents
Removal of Inactive Well Program (Appendix A)
Removal of Inactive Well Worksheets (Appendix A)
Removed Summary of Environmental Legislation and Regulations (Appendix B)
Rewriting Glossary to be consistent with new document
2016 Milestones
Completion of document by workgroup by end of Q1, 2016
Document goes to ballot by summer 2016