The MiniBooNE Horn

Download Report

Transcript The MiniBooNE Horn

The MiniBooNE Horn
Ioanis Kourbanis
For
The MiniBooNE Collaboration
NBI 14-19 March 2002
Outline








List of people
Horn characteristics
Horn Power Supply
Horn Striplines
Highlights of Horn Construction and Assembly
Horn Testing
Horn Changeover
Future Plans
NBI 14-19 March 2002
List of People
•
•
•
•
•
•
•
•
•
•
•
•
•
•
C. Anderson
L. Bartotzek (Bartoszek Engineering)
L. Bartelson
L. Bugel
C. Jensen
H. Le
B. Markel (Markel & Associates)
J. Misek
F. Nezrick
H. Pfeffer
R. Reilly
D. Snee
M. Sorel
E. Zimmerman
NBI 14-19 March 2002
Horn Characteristics



We are using one horn with a narrow neck and a conical inner
conductor (BNL Design) designed to run at a current of 170 KA.
The horn is made out of Al alloy 6061-T6 and is excited by a 143 sec
current pulse.
 Keep the voltage at the PS below 10 KV (use solid state SCR’s
instead of thyristors)
 Reduce the current pulse width as much as possible to avoid
excessive heating of the horn .
 Keep the voltage at the horn as low as possible (small inductance).
The horn will operate at an average rep rate of 5 Hz. Total average
power deposited in the horn is 2.4 KW.
NBI 14-19 March 2002
3-D Model of the Horn
NBI 14-19 March 2002
Horn Power Supply


The Power Supply consists of a Capacitor bank
(1,344 F) discharged through an inductive load
by an SCR switch. The system has a separate
circuit for energy recovery.
The circuit is divided into 16 parallel capacitors,
each with its own SCR switch.
NBI 14-19 March 2002
Horn PS Parameters
Pulse Amplitude
(KA)
Rep. Rate
(Hz)
Circuit Inductance
(microH)
Operating Voltage
(kV)
Average Power
(kW)
DESIGN
OPERATION
250
170
7.5
5.0
1.78
1.33
9.5
5.4
62
19
NBI 14-19 March 2002
Power Supply Schematic
NBI 14-19 March 2002
Power Supply View (Front)
NBI 14-19 March 2002
Power Supply View (Back)
NBI 14-19 March 2002
Horn Stripline




Balanced design (odd number of conductors) to
minimize forces.
The conductor spacing is 1 inch. Fluted alumina
insulators with a 2 inch creepage length were used
to separate the conductors.
The test stripline piece, along with a clamped
joint, were corona tested.
The inductance of the final stripline was
measured to be 18.5 nH/m.
NBI 14-19 March 2002
View of the Long Stripline Section
NBI 14-19 March 2002
View of a Stripline Joint
NBI 14-19 March 2002
View of the Small Stripline Section
NBI 14-19 March 2002
Construction and Assembly Highlights




Forged Outer Conductor
The water sprayers were vibration isolated from
the Horn Outer Conductor.
Solid connections from the striplines to the Horn.
The Horn Inner Conductor was welded at
Fermilab using a programmable TIG welding
machine.
NBI 14-19 March 2002
Outer Conductor after Forging
NBI 14-19 March 2002
Outer Conductor after Machining
NBI 14-19 March 2002
Outer Conductor after Welding
NBI 14-19 March 2002
Water Manifolds
NBI 14-19 March 2002
Water Truss
NBI 14-19 March 2002
Water Truss and Water Manifolds
NBI 14-19 March 2002
Water Truss Bellows Detail
NBI 14-19 March 2002
Water Connection Detail
NBI 14-19 March 2002
Outer Conductor with Water Truss
NBI 14-19 March 2002
Water Drain Connection
NBI 14-19 March 2002
Water Nozzle Detail
NBI 14-19 March 2002
Twist Transitions
NBI 14-19 March 2002
Inner Conductor Before Welding
NBI 14-19 March 2002
Hand Scraping before Welding
NBI 14-19 March 2002
Welding Sample
NBI 14-19 March 2002
Large Weld
NBI 14-19 March 2002
Small Diameter Weld
NBI 14-19 March 2002
Inspecting the Small Diameter Weld
NBI 14-19 March 2002
Radiography of Weld
NBI 14-19 March 2002
Radiography of Large Weld
NBI 14-19 March 2002
Moving the Inner Conductor from The
Welding Machine
NBI 14-19 March 2002
Inserting the Inner into the Outer Conductor
NBI 14-19 March 2002
Horn Testing





The horn was pulsed for the first time on 07/27/01.
The horn test was completed on 02/12/02 after completing 11M pulses
at full current.
We completed horn magnetic field measurements.
Completed a series of vibration measurements.
Things we were monitoring:
 Total current
 Current in the four striplines feeding the horn
 Total voltage
 Cooling water supply and return temperatures
 Horn temperatures
NBI 14-19 March 2002
Overview of MI-8 Test Area
NBI 14-19 March 2002
Horn module overview
NBI 14-19 March 2002
Stripline Configuration at the TSB
NBI 14-19 March 2002
Current and Voltage Profiles
NBI 14-19 March 2002
Horn Magnetic Field Measurement
NBI 14-19 March 2002
Horn Temperature Profiles with Different
Sprayer Configurations
NBI 14-19 March 2002
Correlation between Horn and Water Return
Temperatures
NBI 14-19 March 2002
Horn Vibration Spectrum
NBI 14-19 March 2002
Horn Axial Displacement vs. Time
NBI 14-19 March 2002
Horn Changeover





The horn module is expected to be highly radioactive (30
Rad/hr at 2 ft).
In order to reduce the Radiation Exposure to under 100
mR/hr at 1 ft, the shielding requirement is 5” of steel on all
sides.
Because of the crane lifting capacity, two separate coffins
(an inner and an outer ) will be used.
The inner coffin has 1.5’’ thick walls except from the top
cover and the front door (5” thick).
The outer coffin has 3.5” thick walls and is open at the top
and the front.
NBI 14-19 March 2002
Horn Changeover (2)




The radioactive horn module will be stored inside the two
coffins in the Target Service Building in the old Proton
Line.
Four coffins (two inner and two outer coffins) will be
needed for a changeover.
A detailed procedure outlining all the steps for a
changeover has been written and reviewed.
Total estimated time for a changeover is 2 weeks.
NBI 14-19 March 2002
Inner Coffin
NBI 14-19 March 2002
Outer Coffin
NBI 14-19 March 2002
Initial Configuration
NBI 14-19 March 2002
Inner and Outer Coffins
NBI 14-19 March 2002
Open Inner Coffin Door
NBI 14-19 March 2002
Position the Coffins next to the Horn Module
NBI 14-19 March 2002
Pull the Horn Module in the Coffin
NBI 14-19 March 2002
Close Inner Coffin Door
NBI 14-19 March 2002
Future Plans






We have started disassembling the Power Supply and the
Striplines.
The horn modules will be stored in the inner coffin.
Plan to install the horn in the target pile on May 7.
We estimate to be ready for a horn changeover test on May
15.
We should be ready for beam on June 15.
We have started ordering the large pieces for a spare horn.
NBI 14-19 March 2002