From Surviving System Black
Download
Report
Transcript From Surviving System Black
Frankfurt (Germany), 6-9 June 2011
The Cell Controller Pilot Project (CCPP):
From Surviving System Black-Out
to Market Support
Energinet.dk
Spirae Inc
Energynautics GmbH
SE
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
CCPP: Background
Blackout experience due to transmission
system failure
Large amount of Distributed Energy
Resources in Denmark
Further increasing share of renewable
energy sources in the future
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
CCPP: Objectives
Surviving transmission system black-out
by safely transitioning into island operation
TSO support: Virtual Power Plants
for active and reactive power independently
DNO Support: Advanced voltage control
Platform for market aggregators
of distributed generation resources
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
CCPP: The Pilot Cell
60 kV grid cell below one 150/60 kV transformer
13 each 60/10 kV substations with tap changer
controlled transformers
5 CHP plants / 15 synchronous generators, total
installed capacity of 32.5 MW
47 Danish-style wind turbines, total installed
capacity of 37 MW
Rural area, villages and small cities (>1000 km²)
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
CCPP: Project Status
Started in 2005
Field Tests with reduced-sized Cell in 2008
Field tests using the entire Cell in 2010
Grid-connected and island functions
Grid-connected functions
Final field tests using the entire Cell in 2011
Grid-connected and island functions
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
CC Functions: Market Operations
To be used by Power Balance Authorities
Group and dispatch of CHPs or Wind Turbines
Multiple Markets:
Day-ahead scheduling
Merit order dispatch based on price information
Up-regulation and down-regulation
Automatic dispatch validation against power
system/component limits
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
CC Functions: DNO Voltage Control
Conventional distribution systems use only
transformer tap changers for voltage control.
The Cell Controller uses reactive power
setpoints of distributed energy resources first,
where available.
Reduced wear on tap changers
Smoother voltage for consumers and generators
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
CC Functions: TSO Virtual Power Plants
Controlled load flow at single point of connection
Active Power VPP
Reactive Power VPP
Automatic asset dispatch to meet setpoint
Disables Market Operations
Uses assets dispatched by other means
Reduces voltage control to tap changer control
Consideration of local system/component limits
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
CC Functions: Emergency Island
Based on receipt of external trigger signal
Balance load and generation
Load/generation shedding if necessary
Open the Cell circuit breaker (within <5 seconds)
Automatic voltage & frequency control in island
Automatic load restoration
Resynchronization
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
Field Tests 2010: DNO Voltage Control
Blue: DNO Preferred Operating Voltage Ranges (and changes)
Red: Nominal Voltage Set Point and Actual Values
Holsted CHP
Generator Reactive
Power Production
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
Field Tests 2010: Reactive Power VPP
TSO operator request reactive power set point of -7 MVAr
Tap changer operations at different 60/10 kV substations
TSO reactive power import/export disabled
Measured reactive power
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
Field Tests 2010: Active Power VPP
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
Conclusions
All originally envisioned functions implemented
and tested in simulations and in the field
Grid-connected functions working in 2010
Minor improvements for 2011
Grid-connected functions comprehensively field
tested in May 2011 with success
Island functions to be field tested in June 2011
MARTENSEN – DE – Session 4 – 1221
Frankfurt (Germany), 6-9 June 2011
Outlook
Cell Controller Pilot Project is concluded with
final field tests 2011.
Possible further deployment of the Cell
Controller system on the island of Bornholm
Future distribution systems will provide
further/improved distributed control resources
that can be utilized by the Cell Controller.
MARTENSEN – DE – Session 4 – 1221