EDM Operation
1
LIETZ REDMINI2
EDM Operation
2
MOUNTING

The REDMINI mounts on the theodolite.
EDM Operation
3
SIGHTING

Obtain an approximate
siting using the gun sight

Sight the prism with the
siting telescope

Sight the center of the
prism accurately
EDM Operation
4
MEASURING

Turn the power on

Confirm that the REDMINI is operational

Press the MEAS. switch to start measurement

Press the MEAS. switch to end measurement

Turn the power off
EDM Operation
5
TURN THE POWER ON

Press the power switch
EDM Operation
6
TURN THE POWER ON

There will be a short audio tone and the
display will look like:

This display will last for about 2 seconds.
EDM Operation
7
TURN THE POWER ON

If the battery voltage is adequate the display
will change to:


If the batter voltage is too low the display will
change to:
EDM Operation
8
CONFIRM THAT REDMINI IS READY

When the center of the reflecting prism is
correctly sighted, the asterisk mark lights up
on the display indicating that the light
intensity is correct for a measurement.

The “F” indicates that the measurement will
be made in feet.
EDM Operation
9
START MEASUREMENT

Press the MEAS. switch to start measurement
EDM Operation
10
START MEASUREMENT

A short audio tone is heard when the REDMINI
starts the measurement

The triangle in the lower left corner flashes
during measurement

When the measurement is completed, a short
audio tone sounds and the value is displayed
EDM Operation
11
END MEASUREMENT

The REDMINI will
continue to take
measurements
until the MEAS.
switch is pressed
again

then the last
measurement is
displayed
EDM Operation
12
TURN THE POWER OFF

Press the power switch
EDM Operation
13