Integration of a wind farm into the utility grid
Download
Report
Transcript Integration of a wind farm into the utility grid
VERGNET S.A.
INTEGRATION OF A WIND FARM
INTO THE UTILITY GRID
Eric ANDRIEU, Electrical Design Department Manager
Pierre PESNEL, Export Manager
18 – 20 October 2006
Thank you
for welcoming us
in Jamaica !
What will we talk about?
Who is VERGNET today ?
Our experience in the Caribbeans
Grid connection & Protection
plan of wind farms
Scada System
THE VERGNET GROUP
Created in 1989
100% private
2 plants in France
More than 90% of turnover abroad
By history and culture, VERGNET’s
focuses in cyclonic and isolated areas.
A new product range, the GEV MP
(275 kW)
Vergnet in the Caribbean
Guadeloupe :
• 17 people, dedicated to O&M
• 10 wind farms / 5 locations
• > 20 MW
• 50 GWh / year
Martinique
• 4 wind turbines
• 1,1 MW
Vergnet in Guadeloupe
> 10 % of the island’s energy
Electric solutions with EDF
Maintenance « in the vicinity of the
wind Farm »
Vergnet in the Pacific
New Caledonia :
15 people, dedicated to O&M
7 wind farms / 4 locations
More than 25 MW installed power
50 GWh / year produced
Fidji Islands :
1 wind farm under construction
Commissionning: Q1/2007
37 WTG, 10 MW, very cyclonic
area
In the Pacific :
New projects in progress
The anti-cyclonic GEV MP – 275 kW
Original technological solutions
GEV MP
A light original architecture
55 m or 60 m hub height
26 to 32 m Two-Blades rotors
Pitch regulated
Teetering Hub
Down Wind
Guyed Tilting Tower
Very small foundations:
15m3 concrete
anchored on micro-piles
Asynchronous generator, 2 speeds
Flexible, then earthquake resistant
VERGNET GEV MP
Adaptation to Island’s contexts
Hurricane protection
The WTG can be tilted down into
protection position.
Same position is used for
assembly and maintenance.
Landscape integration
Adapted Logistics
The GEV MP is lighter than other
turbines of the same size
All parts fit in 20’ and 40’ containers
Installed with usual trucks and 25
tons cranes
Nacelle with blades: 8.7 tons
Tower : 12 tons
Very light Civil Work
Per Wind Turbine :
9 drillings, 6’’ diameter, for
the anchorages
Approx 15 m3 concrete
Easy maintenance
Maintenance performed from the
ground
Blade cleaning in the ground at each
maintenance
No need for a special crane to
change heavy components
Simple electrical works
Each WTG features a shelter, for
WTG control
LV/MV transformer
Cos Phi control
MV cables in trenches link the
WTGs to the dist. substation
An optic fibber links all WTGs to
the control room and the Scada
Grid Connection & Protection plan
What is an efficient grid connection ?
- Respect the power quality of the grid
- Respect the grid protection plan
- Allow control and clear monitoring
Grid Integration Analysis
- To assess the impact of connecting the wind farm to
the grid
- To define the setting of the MV protection at the PCC
Preliminary datas
• From Utility
- R = minimum network short-circuit resistance at the PCC
- X = minimum short-circuit reactance at the PCC
- Max permitted voltage fluctuation in steady state and switching
operation
- Max permitted frequency fluctuation
- Max permitted flicker type 1 & 2
• From Turbine Manufacturer :
DEWI report (Compliance with the IEC 61 400-21)
Flicker, Active and Reactive Power, Harmonics, etc…
Step 1
Check connection possibility at chosen location
- Impact on grid Steady state voltage fluctuation
- MV : +/- 7%
- LV : + 6% / - 10%
- Load flow analysis
Max admitted current in the existing grid
From those data, EDF :
- Request grid adaptation
- Gives budget offer
Step 2
Detailed analysis
- Transient Voltage Fluctuation
Drop voltage caused by the transformer connection
When the Wind farm produces P 0,2 and Q 0,2
- Flicker in continuous operation (type 1) and switching
operation (type 2)
- Type 1: Pst = Plt = c(fi,v) x Sn/Scc
- Type 2:
Pst = f (N10, Kf, Sn, Scc)
Plt = g (N120, Kf, Sn, Scc)
Step 2
Protection plan
Wind farm protection
General electrical protection of
the Wind farm
Isetting < 0,8 I_earth _fault (safety
condition)
Isetting > 5 to 8 Ib (to avoid untimely
tripping)
Electrical
fault in the
wind farm
Isetting >1,3 Im (to avoid untimely
tripping)
Isetting >1,2 I_short_circuit_tri_wtg
(to avoid untimely tripping)
Step 2
Protection plan
Grid protection
General electrical protection of
the Wind farm
Electrical
fault on the
public grid
- To avoid islanding network
(Umax-min, Fmax-min, Vo)
- To avoid wind farm production in
case of grid fault
- via Vo for earth fault
- via Umin for short circuit
Electrical DESIGN
The conclusions of the grid
integration analysis allow us
to design the electrical part
of the Wind farm :
• MV substation
• WTG parameters
(PLC)
• SCADA system
MV SUBSTATION
sequential connection to avoid drop voltage
WTG parameters (PLC)
Programming of the PLC to reduce type 2 flicker :
Pst = f (N10, Kf, Sn, Scc)
Plt = f (N120, Kf, Sn, Scc)
Parameters set according to EDF requirements.
SCADA
Supervisory Control And Data Acquisition
• Adjustment of U max, P max, Q max at PCC to meet EDF
requirements.
Communication
Remote access SCADA
Via the public phone line. The communication is based on remote
access (Windows access Virtual Private Network) . The
communication had been optimized to reduce the volume of data
(25 kbyte/s is required)
Dispatch permanent communication
Via permanent radio communication or equivalent.
Full duplex transmission of key data (metering – setting) :
-P, Q, U, CB position
Some SCADA screen shots
Park overview
Substation overview
Monitor (on line data of each GEV MP)
Metering GEV MP
Average power and wind speed report.
Daily energy report
Questions
?
Thank you for your attention