Interconnecting DER with Electric Power Systems
Download
Report
Transcript Interconnecting DER with Electric Power Systems
POWER SYSTEM
2002 CONFERENCE
-- IMPACT OF
DISTRIBUTED
GENERATION
Image
Interconnecting DER
With Electric Power
Systems
Image
ABB
Interconnecting DER with Electric Power Systems
Existing IEEE Standards
Current IEEE Standards Work
©ABB Ltd. Page 2
Standards Coordinating Committee 21:
IEEE Standard 929-2000
Recommended Practice for Utility Interface of
Photovoltaic (PV) Systems
Standards Coordinating Committee 23
IEEE Standard 1001-1988
Guide for Interfacing Dispersed Storage and
Generation Facilities with Electric Utility Systems
IEEE P-1547 Standard for Interconnecting Distributed Resources with
Electric Power Systems
ABB
Interconnecting DER with Electric Power Systems
Definitions:
Area EPS Facility
PHASE TO
GROUND
PHASE TO
PHASE
THREE PHASE
A
B
C
G
POINT OF
COMMON
COUPLING
(PCC)
PCC
DISTRIBUTED
RESOURCE
PCC
L
L
©ABB Ltd. Page 3
POINT OF
INTERCONNECTION
(PI)
DISTRIBUTED
RESOURCE
ABB
Interconnecting DER with Electric Power Systems
P-1547 Project Approved in March 1999
4 - 6 meetings of Working Group per year since then
Working Group Members
©ABB Ltd. Page 4
More than 200 names on Working Group Roster
100+ members attend each Working Group Meeting
ABB
Interconnecting DER with Electric Power Systems
Three Official IEEE Balloting Member Categories
©ABB Ltd. Page 5
User
The user is the person who will apply the standard when interconnecting
DER to the electric power system. For example, the utility, the DER
owner, etc.
Producer
The producer is the person who will apply the standard when producing
equipment that will be interconnected to the electric power system. For
example, equipment manufacturers, installers, etc.
General Interest
The general interest person is one who is interested, but not directly
involved in interconnecting DER to the electric power system. For
example, regulatory agencies, financial institutions, advocacy groups, etc.
ABB
Interconnecting DER with Electric Power Systems
Draft 7 circulated for ballot --- closing date of April 1, 2001
Vote Results:
VOTE COUNT --- DRAFT 7
©ABB Ltd. Page 6
Voter
Category Affirmative Negative Totals
User
31
23
54
Producer
General
Interest
37
12
49
30
15
45
Totals
98
50
148
66% Affirmative, not enough for approval (75% required)
ABB
Interconnecting DER with Electric Power Systems
Draft 8 circulated for ballot -- closing date of October 2, 2001
Vote Results
VOTE COUNT --- DRAFT8
Voter
Category Affirmative Negative Totals
User
25
33
58
Producer
General
Interest
43
6
49
35
14
49
103
53
156
©ABB Ltd. Page 7
Totals
66% Affirmative, not enough for approval (75% required)
ABB
Interconnecting DER with Electric Utility Systems
IEEE Standard 929
Aimed at Photovoltaic Generator Systems, using solid-state inverters for
interconnection
Usually low kilowatt capacity
Inverter inherently limits fault current
Inverter tends to shut down automatically upon overload or reverse power
IEEE Proposed Standard P-1547
©ABB Ltd. Page 8
Intended to address DER without regard to prime mover (wind, fuel cell, etc)
Attempts to address systems up to 10 Mw in size
Seeks to provide ‘universal’ solution
ABB
Interconnecting DER with Electric Power Systems
“User” Concerns
©ABB Ltd. Page 9
Safety of Personnel
Personnel must be able to work on the EPS and DER facility without
undue risk of injury or death
General public should not be exposed to hazardous conditions
Fault duty, including DER, should not exceed ratings of distribution system
equipment, including customer-owned equipment connected to the system
Equipment damage, downed conductors, vault fires, etc.
Normal load-carrying and interrupting capabilities, including DER, should not
be exceeded
Reduction of system reliability, premature failure of equipment
Protective relaying and control equipment, should not be subject to misoperation as a result of DER additions
More and longer interruptions, high/low voltage problems
ABB
Interconnecting DER with Electric Power Systems
Producer and General Interest Concerns
©ABB Ltd. Page 10
Interconnection costs must be minimal
Interconnection equipment should be some fraction of the cost of the DER
being connected.
Utility involvement should be minimized
Impact studies cost too much
Some utilities use interconnection standards as a means of ‘killing’
DER
Interconnection must be ‘simple’ so that it won’t discourage DER applications
Interconnection apparatus should be ‘maintenance free’ as much as possible
Interconnection operation should be ‘automatic’
ABB
Interconnecting DER with Electric Power Systems
Basic Problem:
Most Utility Electric Power Systems (EPS) were/are not
designed to accommodate active generation and energy
storage at the distribution level.
©ABB Ltd. Page 11
Basic Need:
Develop technology and operational concepts that will enable
realization of DR benefits while avoiding negative impacts on
system reliability and safety
ABB
Interconnecting DER with Electric Power Systems
Significant Problem Areas
©ABB Ltd. Page 12
Scaling
“My typical distribution feeder has a peak load of 4 Mw. Adding a few kW of
PV is a whole different problem than adding 400 kW.”
Islanding
Utility is still responsible for voltage and frequency of all its customer
connections. Creating an island where some utility customers are supplied
with un-controlled voltage or frequency is unacceptable
Safety
Personnel working on the distribution system MUST be protected from
backfeed or accidental energization
Protection System Design
Radial distribution line protection is designed and coordinated for ‘one way’
power flow. Bi-directional flow in some part or all of a feeder is a whole
new world of problems
Networked Distribution System
Consideration postponed to future updates
ABB
Interconnecting DER With Electric Power Systems
©ABB Ltd. Page 13
What’s Next?
Working Group meeting to discuss ballot results, possible resolution was held
January 30-February 1
Writing Group to meet and attempt to resolve negative ballots received on
Draft 8
New Draft of P-1547 to be circulated for ballot before mid-year
Still optimistic on submitting proposed standard to IEEE Standards Board
before the end of 2002
ABB