Whisper 200 Analysis and Remediation
Download
Report
Transcript Whisper 200 Analysis and Remediation
Phase IV Presentation
Group 7
Thomas Kudej
Marko Sutovic
Timothy Smith
Advisor
Professor Basu
Timothy Smith
Marko Sutovic
Thomas Kudej
Presentation Outline
Project Objective
Background Phase I-III
Phase IV
Monitoring System
Parts Ordered
Programming Needed
Power Transformation System
Height Increasing Base
Budget
Gantt Chart
Nugget Chart
Questions?
Project Objectives
To design a monitoring system to record data from the
wind turbine and use this data to improve on the power
generation .
Design and build a foundation to raise the height of the
turbine over any further obstacles and bring it closer to the
recommended height.
Use the monitoring system to observe vibrations
transmitted by the turbine into the roof slab.
Design the foundation in response to vibrations analysis
Analyze the data to study trends of a wind turbine in an
urban environment
Background
Previous design group placed
Whisper 200 on Babbio roof
They incorrectly assumed wind
readings from buoy on Hudson
river and other local weather
stations were similar to Babbio
roof conditions
Local wind measurements were
needed of potential locations
on campus for the Whisper 200
A repeatable experiment
was executed at 8
locations on Stevens
Campus
Measured wind speeds
and direction.
Repeated on three
different days
Sample was taken at
Babbio Location A
(original location) on Day
1 between 1:35pm and
1:45pm.
1:36:57 PM
1:37:24 PM
1:37:37 PM
1:38:13 PM
1:38:23 PM
1:38:31 PM
1:39:07 PM
1:39:20 PM
1:39:32 PM
1:39:58 PM
1:40:17 PM
1:40:39 PM
1:40:50 PM
1:41:02 PM
1:42:01 PM
1:42:14 PM
1:42:35 PM
1:43:01 PM
1:43:12 PM
1:43:34 PM
1:43:48 PM
1:43:57 PM
1:44:12 PM
1:44:29 PM
1:44:39 PM
1:44:47 PM
1:45:02 PM
1:45:16 PM
1:45:34 PM
1:45:50 PM
1:45:58 PM
1:46:07 PM
Background
Speed
12
10
8
6
4
2
0
Background
Sample was taken at CPA
Location B (optimal location)
on Day 1 between 3:00pm and
3:10pm.
Average Wind Velocity was
measured to be 4.0408m/s.
Wind Direction was
conclusively consistent.
After analysis, this location
was chosen as the most
optimal for the Whisper 200,
due to its constant wind
direction and reliable wind
velocity.
Background
Whisper 200 moved to CPA location B
Monitoring System
Live remote
monitoring
Vibration
Power
production
Wind behavior
Video feed
Store data to
create archive of
Whisper 200
performance
characteristics
Post results on
website
Monitoring System
Parts Ordered
2 Accelerometers
USB data logger
USB to Ethernet Microserver
Programming Needed
Labview
Sensors signal processing
Website
Easy display of data
Live video feed
Power Transformation System
Current system
Whisper Link – Rectifies the
3 phase AC out of the turbine
and supplies the inverter
with a DC output voltage.
Windy Boy Inverter converts
DC input into single phase
120V/60Hz AC into the
electrical grid
Windy Boy Grid Tie Inverter
Power Curve Operation
Turbine mode of operation draws power based upon
the DC voltage seen at the input terminal.
•Maximum power output 1800W
•When start voltage is reached, the
inverter waits 10 seconds
•If voltage remains above start
point , inverter will synchronize
the power and export it.
•If voltage drops below set point
,inverter will have a zero power
output for 120 seconds before
shutting down.
Issue with Inverter
Voltage start point set by manufacturer = 190Vdc
Currently the wind turbine needs an increase in the
amount of wind speed in order to reach this point.
Inverter Solution
Inverter can be adjusted with software provided by
manufacturer and purchased connecter cable.
Software allows for adjustments to the slope of the
power curve
Able to reprogram voltage start and max point in range
of 155 – 375 Vdc
By reducing start and max point, you reduce the
maximum power output
Possible extensions
Storage Battery system
When output DC voltage
does not reach inverter
start point and during periods
of low wind, discharge minor
generated voltage into
batteries
Batteries charge to capacity
then discharge into the inverter
Downsides
Logistics
Cost
Voltage losses
Possible Extensions
Minor battery system
Install 2-3 batteries
Store energy when Vdc start point is not met
Use stored power in batteries to boost the input DC
voltage past the start point when it is close
Downsides
Cost
Logistics
Feasibility