Network connection issues for offshore wind farms in UK waters
Download
Report
Transcript Network connection issues for offshore wind farms in UK waters
Some electrical connection
design issues for offshore
wind farms
Paul Gardner, Helen Snodin, & Nigel Scott
Garrad Hassan and Partners
[email protected]
Presentation Rationale
Most UK projects quite advanced
Grid connections and costs known
Issues of design choices
Unknowns ?
Electrical Design
Can be split into 3 key areas:
Offshore array
Transmission to shore
Grid connection
will concentrate on the latter two.
Some Electrical Design Issues
Subsea vs land cable
33kV vs 132kV transmission to shore
Export security
Parallel 132/33kV transformers
Teed vs looped vs busbar connections
Grid Code changes
Electrical Design Diagram
Onshore
Offshore
Existing 132kV
grid line
Wind turbine
Wind turbine
transformer
Other wind turbines
132/33kV
transformer
132kV switch
circuit breaker
33kV cable
onshore
33kV cable
to shore
33kV submarine cable
within array
132kV cable
Tee or loop
connection ?
Single or double
transformer
arrangement ?
Continue with
submarine cable
onshore ?
Offshore transformation
to 132kV or continue at
33kV ?
Arrangement of
offshore array ?
Subsea vs Land Cables
Offshore
33kV - use either EPR submarine cables or
XLPE cable with additional waterproofing
132kV - use XLPE cables
Better electrical insulator
Sealed in watertight lead sheath - not land cable !
Onshore
Subsea cables can be used but only worth
considering for short and simple routes.
Key issues are costs and practicability
33kV vs 132kV Transmission
to Shore
Item
Cable
Cable installation
Power losses
Substation
Power factor correction
O&M
Other costs / risks
Highest Cost
132kV
33kV
£
£
£
£
£
£
£
Export Security
Teed vs Loop vs Busbar connections
Capital cost vs improved export security against
grid faults,
operations and maintenance outages
E.g. 100MW at £0.035/kWh and 35% load factor
Cost of Lost Production
£1.2k
£29k
£206k
£412k
Time
1 hour
1 day
1 week
2 weeks
Export Security - Tee & Loop
Existing grid line
Circuit
breaker/switch
Wind farm
Tee connection
Loop connection
arrangement
arrangement
Export Security
Single or double 132/33kV transformers
One transformer = all eggs in one basket
Two transformers
Extra capital cost
Improved security against transformer failure
new transformer or repairs could take months
failure rates are low
reduced export depending on transformer rating
Higher O&M costs
Grid Code Changes
Compliance in full or in part mandatory
New Grid Code due in 2002
Possible requirements
Control of real and reactive power
Frequency response
Voltage regulation
Stability
Implications - more cost ?
Summary
Impossible to cover all the issues,
design choices and best practices
Hopefully raised awareness of one or
two issues
The answers are often project specific