Transcript Slide 1
Ancillary Services in Indian Context
NLDC
1
Outline
Definition
Drivers for Ancillary Services
Ancillary Services in Indian Context
NLDC
2
Definition
As per draft IEGC, 2010…..
“Ancillary services in power system (or grid) operation
means services necessary to support the power
system (or grid) operation in maintaining power
quality, reliability and security of the grid, e.g active
power support for load following, reactive power
support, black start etc”
NLDC
3
Drivers
Reliability and Security
Deregulated Power Systems
Changing Nature of Electricity Grid
Services to be obtained from Service Providers
Cannot be coupled with basic energy services
Use of UI surplus amount as per UI regulations –
March 2009
NLDC
4
Pillars of Market Design
Sally Hunt – ‘ Making Competition Work in Electricity’
NLDC
5
Ancillary Services in Indian Context
Proposed Ancillary Services in India
Frequency Control Ancillary Services (FCAS)
Network Control Ancillary Services (NCAS)
Power Flow Control Ancillary Services (PFCAS)
Voltage Control Ancillary Services (VCAS)
System Restart Ancillary Services (SRAS)
Compensation through UI surplus fund
Limited to Operational Expenditure
NLDC
6
Frequency Control Ancillary Services (FCAS)
Mis-matches between supply and demand
IEGC band – 49.2 to 50.3 Hz
Wide fluctuations in frequency
Primary Response : FGMO
Secondary Response : Absent by Design
Tertiary Response
Availability Based Tariff (ABT)
Use of Un-Requisitioned Surplus
Scheduled to the ‘POOL’
Merit order
Peaking Gas Stations
Pumped Storage Plants
NLDC
7
Network Control Ancillary Services (NCAS)
Power Flow Control Ancillary Services (PFCAS)
Control power-flow on interconnectors
Utilizing URS
Schedule to ‘POOL’
Based on both location and merit order
Voltage Control Ancillary Services (VCAS)
Provision in IEGC for VAr drawl
Synchronous condenser operation
Friction and windage losses
Auxiliary consumption
NLDC
8
System Restart Ancillary Services (SRAS)
Black Start of Power Stations
Provision for mock exercises
Might be linked to a fraction of fixed cost recovery
NLDC
9
Thank you !!
Email ID: [email protected]
NLDC