DC Decoupling / AC Grounding and Over
Download
Report
Transcript DC Decoupling / AC Grounding and Over
DC ISOLATION & OVER-VOLTAGE
PROTECTION ON CP SYSTEMS
Mike Tachick
Dairyland Electrical Industries
Typical Problems
AC grounding without affecting CP
Decoupling in code-required bonds
AC voltage mitigation
Over-voltage protection
Hazardous locations
Conflicting Requirements
Structures must be cathodically protected (CP)
CP systems require DC decoupling from ground
All electrical equipment must be AC grounded
The conflict:
DC Decoupling + AC Grounding
Reasons to DC Decouple From
Electrical System Ground
If not decoupled, then:
CP system attempts to protect grounding
system
CP coverage area reduced
CP current requirements increased
CP voltage may not be adequate
Isolation problems
Insulation strength/breakdown
FBE coating: 5kV
Asphalt coating: 2-3kV
Flange insulators: 5-10kV?
Monolithic insulators: 20-25kV
Over-Voltage Protection
From:
Lightning (primary concern)
Induced AC voltage
AC power system faults
Over-Voltage Protection Goal
Minimize voltage difference between points of
concern:
At worker contact points
Across insulated joints
From exposed pipelines to ground
Across electrical equipment
Step Potential
Touch Potential
Over-voltage Protection: Products and
Leads
Both the protection product and the leads
have voltage across them
Lead length can be far more significant than
the product conduction level
Effect of Lead Length
Leads develop extremely high inductive voltage
during lighting surges
Inductive voltage is proportional to lead length
Leads must be kept as short as possible
Not a significant effect seen with AC
Key Parameters of Lightning Waveform
1.0
Slope = di/dt
(Rate of rise,
Amps/µsec)
Crest Amperes
1/2 Crest Value
0
8
20
Time in microseconds
Lightning has very high di/dt (rate of change
of current)
Amplitude
AC and Lightning Compared
Time (milliseconds)
Alternating Current
Time (microseconds)
Lightning
Over-Voltage Protection: Best
Practices
Desired characteristics:
Lowest clamping voltage feasible
Designed for installation with minimal lead length
Fail-safe (fail “shorted” not “open”)
Provide over-voltage protection for both lightning
and AC fault current
Example: Insulated Joint
Example: Insulated Joint
Example: Insulated Joint
Insulated Joint Protection
Summary
Rate for:
AC fault current expected
Lightning surge current
Block CP current to DC voltage across joint
AC induction (low AC impedance to collapse
AC voltage) – rate for available current
Hazardous location classification
Grounding System Review
Secondary (user) grounding system
Primary (power co) grounding system
These systems are normally bonded
Grounding System Schematic
Primary
Secondary
Situation: Pipeline with Electrical
Equipment
Grounded electrical equipment affects CP
system
Code requires grounding conductor
Pipeline in service (service disruption
undesirable)
Decoupler characteristics
High impedance to DC current
Low impedance to AC current
Passes induced AC current
Rated for lightning and AC fault current
Fail-safe construction
Third-party listed to meet electrical codes
Grounding System After
Decoupling
Issues Regarding Decoupling
NEC grounding codes apply: 250.2,
250.4(A)(5), 250.6(E)
Decoupler must be certified (UL, CSA, etc.)
No bypass around decoupler
Rating for Equipment Decoupling
Rate for:
AC fault current/time in that circuit
Can rate by coordinating with ground wire
size
Decoupler must be certified (UL, etc)
Steady-state AC current if induction present
DC voltage difference across device
Hazardous area classification
Example: MOV
Decoupling Single Structures: When is it
Impractical?
Too many bonds in a station from CP system to
ground
Bonds can’t be reasonably located
Solution: Decouple the entire facility
Decoupling from Power Utility
Decoupling From the Power Utility
Separates user site/station from extensive utility
grounding system
Installed by the power utility
Decoupler then ties the two systems together
Decoupling from Power Utility
Primary
Decoupler
Secondary
Decoupling from utility
Decoupling from utility
Decoupling from utility
Decoupling from utility
Primary and secondary have AC continuity
but DC isolation
CP system must protect the entire secondary
grounding system
Rating for Utility Decoupling
Rate for:
Primary (utility) phase-to-ground fault
current/time
Ask utility for this value
Select decoupler that exceeds this value
Case study – station decoupling
Station
Before
After
A
870mV
1130
B
800
1175
C
950
1570
D
1140
1925
P/S readings at the station before and after decoupling from the
power company grounding system
Induced AC Voltage
Pipelines near power lines develop “induced
voltage”
Can vary from a few volts to several hundred volts
Voltages over 15V should be mitigated (NACE RP0177)
Mitigation: reduction to an acceptable level
Induced AC Mitigation Concept
Create a low impedance AC path to ground
Have no detrimental effect on the CP system
Provide safety during abnormal conditions
Example: Mitigating Induced AC
Problem:
Open-circuit induced AC on pipeline = 30 V
Short-circuit current = 10 A
Then, source impedance:
R(source) = 30/10 = 3 ohms
Solution:
Connect pipeline to ground through decoupler
Example: Mitigating Induced AC,
Continued
Typical device impedance:
X = 0.01 ohms
0.01 ohms << 3 ohm source
10A shorted = 10A with device
V(pipeline-to-ground) = I . X = 0.1 volts
Result: Induced AC on pipeline reduced from 30 V to
0.1 V
Mitigation of Induced AC
Rate for:
Induced max AC current
DC voltage to be blocked
AC fault current estimated to affect pipeline
Mitigation of Induced AC
Two general approaches:
Spot mitigation
Continuous mitigation
Spot Mitigation
Reduces pipeline potentials at a specific point (typ.
accessible locations
Commonly uses existing grounding systems
Needs decoupling
Mitigation example sites
Mitigation example sites
Mitigation example sites
Mitigation example sites
Continuous Mitigation
Reduces pipeline potentials at all locations
Provides fairly uniform over-voltage protection
Typically requires design by specialists
Continuous Mitigation
Gradient control wire choices:
Zinc ribbon
Copper wire
Not tower foundations!
Hazardous Locations
Many applications described are in Hazardous
Locations as defined by NEC Articles 500-505
Most products presently used in these applications
are:
Not certified
Not rated for hazardous locations use
Hazardous Location Definitions
Class I = explosive gases and vapors
- Division 1: present under
normal conditions (always
present)
- Division 2: present only
under abnormal conditions
Hazardous Locations
Division 1
Division 2
CFR 192.467
(e) “An insulating device may not be installed
where combustible atmosphere is
anticipated unless precautions are taken to
prevent arcing.”
CFR 192.467, continued
(f) “Where a pipeline is located in close proximity
to electric transmission tower footings
. . . it must be provided with protection against
damage due to fault current or lightning, and
protective measures must be taken at
insulating devices.”
CFR 192 link to NEC
CFR 192 incorporates the National Electrical
Code (NEC) “by reference”
This classifies hazardous locations
Defines product requirements and
installation methods
Guidance Documents (Haz Loc)
AGA XF0277 – gas facilities
API RP-500 – petroleum facilities
CFR 192.467 – gas pipeline regs
NEC section 500-505 - haz loc definitions,
requirements
CSA C22.2 No. 213 – product requirements
UL 1604 – product requirements
For further application questions…
Mike Tachick
Dairyland Electrical Industries
Phone:
Email:
Internet:
608-877-9900
[email protected]
www.dairyland.com