Project Overview
Download
Report
Transcript Project Overview
Project Overview
ENGR-1020-100
FALL 2007
WIND TURBINE
TEAM 1
JERRY BERNARDINI
Project Goals
Design and build a Picoturbine improved wind
turbine
Build the turbine with used hard drive magnets
The no-load voltage will be three times the
Picoturbine
The turbine will be weather proof
Project ready for testing by Thanksgiving
Project Team and Skills
Jerry Bernardini - Electrical Engineering Major
Electrical circuits
Tom Jones – Civil Engineering Major
Wood working
Billy Joel – Computer networking Major
Spread sheets and ideas
Clark Gable – Acting Major
Presentations and reports
Project Description
A purchased kit was built and tested
The kit parts used as part of a larger turbine
Magnets obtained from hard drives
Wind new coils
Test new magnet coil combination
Build wind capture section
Complete construction
Test
Competitive Analysis
Strengths
Weaknesses
Team-1
Balanced skill set , good math
skills, great idea people
Getting everyone to a meeting
Team-2
Seems like a smart team
Will build a HAWT
Seems disorganized
Team-3
Good team sprit
Good skill set
No obvious weaknesses
Team-4
Good ideas but secretive about
their plans
Have not been using Engineering
Journals
Technology Features
Moving Permanent magnets
No commutate needed
Coils wound to 400-turns with 20 Gauge wire
More voltage
Lower coil resistance
Wood turbine construction
Vibration reduction
Easy to modify
Team Resources
People
Four team members that show up for every
meeting
Equipment
Hand tools
Drill
Power saw
Skills
Electrical, wood working drafting
Outside Sources
Machine shop if needed
Work Locations
Team member basement and garage
Materials
Aluminum sheets available
Buy most wood
Team Procedures
Jerry is the leader for the first seven weeks
Frank is the leader for the last seven weeks
Highlight any procedural differences from regular
projects of this type
Discuss requirements, benefits, and issues of using
new procedures
E-mail during week
Meet before every class
Exchange Engineering Journal sketches and notes
Schedule
High-level schedule milestones
Phase 1
Picoturbine
Phase 2
Phase 3
Sep
Oct
Nov
Dec
Current Status
High-level overview of progress against schedule
On-track in what areas
Behind in what areas
Ahead in what areas
Unexpected delays or issues
Wire for new coils are delayed