Presentation - Outage Response Timelines NPRR111

Download Report

Transcript Presentation - Outage Response Timelines NPRR111

Outage Response Timelines
NPRR111
Woody Rickerson
Beth Garza
TPTF
April 22, 2008
A little history…
• NPRR111 was drafted to increase ERCOT’s response time to
45-day outages from 5 to 15 days.
• Concerns were raised that this change would interfere with
the CRR Auction timeline.
• Consolidated CRR and OS timelines were presented at the
April 2, 2008 TPTF meeting.
• Since then, ERCOT has developed several alternative
timelines for discussion.
• This discussion is complicated by Nodal protocol section
3.10.3 (4) which seems to require that the CRR Network
Model, including any outages be assembled at least 2 months
prior to the effective month.
ERCOT shall perform updates to CRR Network Model for CRR
auctions as described in Section 7, Congestion Revenue Rights, a
minimum of two months in advance.
April 22, 2008
2
TPTF / Outage Response Timelines
Combined CRR and OS timeline
April 22, 2008
3
TPTF / Outage Response Timelines
Option 1 – CRR pulls outage information as late as possible
April 22, 2008
4
TPTF / Outage Response Timelines
Option 1 – CRR pulls outage information as late as possible
Considerations:
• All outages submitted in the 90-day timeline would be included
in the CRR Network model
• 90-day outages would still have a 15-day approval window
• NPRR111 would have no effect on the CRR Network Model
• There is no requirement to enter outages 90-days in advance of
their start
• Creates extremely compressed timeline for the creation of CRR
Network Models. This will be particularly challenging during the
first six-months of monthly CRR allocations and auctions, and
subsequently if monthly true-up allocations are required.
April 22, 2008
5
TPTF / Outage Response Timelines
Option 2 – Move 90 day outages out to 100 days
April 22, 2008
6
TPTF / Outage Response Timelines
Option 2 – Move 90 day outages out to 100 days
Considerations:
• All outages submitted in the 100-day timeline would be included
in the CRR model
• 100-day timeline would still have a 15-day approval window
• No requirement to submit outages in 100-day timeline
• Difficult for TSPs to coordinate outages 100 days before their
start
• No changes to CRR process
• Requires a NPRR to change the 90-day timeline into a 100-day
timeline
April 22, 2008
7
TPTF / Outage Response Timelines
Option3 – Reduce 90-day approval time to 5 days
April 22, 2008
8
TPTF / Outage Response Timelines
Option3 – Reduce 90-day approval time to 5 days
Considerations:
• All outages approved in the 90-day timeline would be included in
the CRR model
• No Changes required in the CRR process
• No protocol requirement to submit outages in 90-day timeline
• 5-day approval window would require 7-day a week coverage
and more personnel from both ERCOTand TSPs
• Difficult to coordinate complicated outages in a 5-day analysis
window (90-days out) resulting in some outages being rejected
or moved into the 45-day approval timeline because of a lack of
information
• Requires a NPRR to change the 90-day timeline approval window
from 15-days to 5-day
April 22, 2008
9
TPTF / Outage Response Timelines
Option 4 – Create CRR monthly outage deadline
April 22, 2008
10
TPTF / Outage Response Timelines
Option 4 – Create CRR monthly outage deadline
Considerations:
• Provides the ability to define specific outage types to be
included in CRR model
• Simplifies the long-term Outage Approval Process
• Requires advance scheduling of outages by TSPs
• Advanced approval of CRR transmission outages still subject to
withdrawal due to automatic acceptance of Resource Outages
• Could require the rejection of CRR-type outages that are
submitted outside the CRR timeline
• Requires CRR team to operate with a compressed timeline
April 22, 2008
11
TPTF / Outage Response Timelines
Possible CRR-type Outage definitions
• All 345-kV lines and transformers
• All lines and transformers in West Load Zone outages during
October - March
• Any outage associated with the construction of new equipment
• Any continuous outage lasting more than 10 days
• Any reoccurring daily outages lasting more than 10 days
April 22, 2008
12
TPTF / Outage Response Timelines
Nodal Protocol and Operating Guide excerpts
April 22, 2008
13
TPTF / Outage Response Timelines
Nodal Protocols
3.10.3 CRR Network Model
(1)
(2)
(3)
(4)
(5)
ERCOT shall develop models for CRR auctions that contain, as much as practicable,
information consistent with the Network Operations Model. Names of Transmission Elements
in the Network Operations Model and the CRR Network Model must be identical for the same
physical equipment.
ERCOT shall verify that the names of Hub Buses and Electrical Buses used to describe the
same device in any Hub are identically named in both the Network Operations Model and the
CRR Network Model.
Each CRR Network Model must include:
(a) A complete one-line diagram with all Settlement Points (indicating the Settlement Point
that the Electrical Bus is a part of) and including all Hub Buses used to calculate Hub
prices (if applicable);
(b) Generation Resource locations;
(c) Transmission Elements;
(d) Transmission impedances;
(e) Transmission ratings;
(f) Contingency lists;
(g) Data inputs used in the calculation of Dynamic Ratings, and
(h) Other relevant assumptions and inputs used for the CRR Network Model.
ERCOT shall perform updates to CRR Network Model for CRR auctions as described in
Section 7, Congestion Revenue Rights, a minimum of two months in advance.
ERCOT shall make available to TSPs and/or DSPs and all appropriate Market Participants,
consistent with applicable policies regarding release of Critical Energy Infrastructure
Information (CEII), the CRR Network Model. ERCOT shall provide model information through
the use of the Electric Power Research Institute (EPRI) and NERC-sponsored “Common
Information Model” and web based XML communications.
April 22, 2008
14
TPTF / Outage Response Timelines
Nodal Protocols
7.5 CRR Auctions
(2)
7.5.1
Nature and Timing
The CRR Network Model must be based on, but is not the same as, the Network
Operations Model. The CRR Network Model must, to the extent practicable, include
the same topology, contingencies, and operating procedures as used in the Network
Operations Model as reasonably expected to be in place for each month. The
expected network topology used in the CRR Network Model for any month must
include all outages from the Outage Scheduler and identified by ERCOT staff as
expected to have a significant impact upon transfer capability during the month. These
outages included in the CRR Network Model shall be posted on the MIS Secure Area
consistent with model posting requirements by ERCOT with accompanying cause and
duration information, as indicated in the Outage Scheduler. Transmission system
upgrades and changes must be accounted for in the CRR Network Model for CRR
Auctions held after the month in which the element is placed into service.
(a) ERCOT shall use Dynamic Ratings in the CRR Network Model as required
under Section 3.10.8, Dynamic Ratings.
(b) The CRR Network Model must use the peak Load conditions of the month
being modeled.
(c) ERCOT’s criteria for determining if an Outage should be in the CRR Network
Model shall be in accordance with these Protocols and described in the
ERCOT Operating Guides.
April 22, 2008
15
TPTF / Outage Response Timelines
Nodal Operating Guides
5.5
System Modeling Information
(6)
Congestion Revenue Rights (CRR) Network Model Outage determination uses
network topology of the CRR Network Model identified by ERCOT Staff. This must
include Planned Outages of Transmission Elements approved by ERCOT at the time
the CRR Network Model is being built and that demonstrate significant impact to the
transfer capability during the effective period. ERCOT Staff will consider including
Outages in the CRR Network Model that are scheduled to occur in the relevant time
period and meet one or more of the following criteria:
(a) Consecutive or continuous approved Outages greater than or equal to five days;
(b) Approved Outages which include Transmission Elements included in the definition
of a Hub;
(c) Approved Outages which include Transmission Elements in a 345 kV
Transmission Facility;
(d) Approved Outages that require the use of a Block Load Transfer (BLT); and
(e) Any other approved Outage that has been determined by ERCOT Staff to carry a
substantial risk of causing significant congestion.
All Outages included in the CRR Network Model shall be posted on the Market
Information System (MIS) Secure Area consistent with the model posting requirements
and with accompanying cause and duration information, as indicated in the Outage
Scheduler in Protocol Section 7.5.1, Nature and Timing.
April 22, 2008
16
TPTF / Outage Response Timelines