IT INFRASTRUCTURE

Download Report

Transcript IT INFRASTRUCTURE

IT Infrastructure
Quality Control and Cost
Savings Through
Commissioning
Presented by: Bruce Torello
Rick Foster, RCDD
Commissa 2003
Commissioning
“the process of ensuring that the systems are
designed, installed, functionally tested and
capable of being operated and maintained to
perform in conformity with the design intent.
Commissioning begins with planning and
includes design, start-up, acceptance and
training and can applied throughout the life of
the building.”
ASHRAE – Guidelines 1996
Commissa 2003
Commissioning
“building commissioning” is the process for
achieving, verifying and documenting that
the performance of the building and its
systems meet the design intent and the
owner and occupant needs.”
Building Commissioning Guide:
U.S. General Services Administration
U.S. Department of Energy
July 1998
Commissa 2003
History of Commissioning
Origins in HVAC construction
Accepted practice in the construction process
Expanded to include other building utilities
Third party verification
Entire building commissioning
Commissa 2003
Why Commissioning ?
Unclear Designs
Low Bid contracting
– Quality Control
No established standards for
performance verification
Improper needs assessment
Conflicts between Codes & Standards
Commissa 2003
Why Commissioning ?
Inadequate documentation
Need to integrate the new and complex
building systems
Convergence
Reliability and Redundancy critical to
single IP networks
Commissa 2003
Why Commissioning ?
“The
design and integrity of the
IT infrastructure should be
evaluated during entire building
process. From initial design,
through the construction
process and including network
validation- not after the walls and
ceilings are complete”
Commissa 2003
When to Commission
Life Safety
Complexity of systems
Building size and use
Project type
Business risk - Mission Critical Facilities
O & M (Operations & Maintenance)
considerations
Bid process & economic responsibility
Public Sector funding
Commissa 2003
Design Intent
Determines the clients
goals and objectives are
met in the design phase
Establishes benchmark
and specifications
Becomes the baseline for
project scope
Mandates acceptance
criteria at the project
inception
Commissa 2003
Economics of Commissioning
Cost Saving range from 5-10% by
eliminating design related change orders
Deficiencies are identified and remedied
before completion when it is more
economical
Funding commissioning as part of the
project represents a 2-5% of project cost.
Commissa 2003
Economics of Commissioning
Existing Building Systems 1
Building Type
Commissioning
Costs
Annual
Savings
Simple
Payback
(Years)
Computer
Facilities/Office
$24,000
89,758
.03
High Rise
Office
$12,745
$8,145
1.6
Medical
Institution
$24,768
$65,534
.04
1 Gregerson,Joan, “Cost Effectiveness of Commissioning 44 Existing Buildings”, in Proceedings of the National Conference of
Building Commissioning
Commissa 2003
Process of Commissioning
Program Phase & Project Formulation
Design Phase
Construction Phase
Acceptance Phase & Construction Close Out
Post – Acceptance Phase
Commissa 2003
Process of Commissioning
Program Phase & Project Formulation
Identifying the TEAM
A/E Firm (Architect / Engineer)
IT representative
Commissioning Authority
GC or Construction Manager
Approvals
Funding & Budgets
Crucial decisions must be made early
Establish “Design Intent”
Commissa 2003
Process of Commissioning
Design Phase
Architectural Review
Needs assessment/inventory of IT requirements
Design Intent documentation submitted
IT, Facilities and Architectural review
Commissa 2003
Process of Commissioning
Construction Phase
Milestone monitoring
Pre-functional testing
Field inspections & progress reports
Change order process & approval authority
Modification of the design intent if required
Commissa 2003
Process of Commissioning
Acceptance Phase & Construction CloseOut
Functional performance testing
Site Audit
Warranty Audit
Final documentation submittals and all test reports
Commissa 2003
Process of Commissioning
Post – Acceptance Phase
O&M (Operations & Maintenance) documents
reviewed
MAC (Moves, Adds & Changes) procedures
IT requirements for MAC documentation and
maintainability
Commissa 2003
IT Infrastructure
What It Isn’t?
The IT Infrastructure is not just
cable and connectors !
Commissa 2003
IT Infrastructure - What it is
…all the necessary physical layer
components that will effect the
operational efficiency, network
performance and reliability of the
information system.
Commissa 2003
Open Architecture vs.
Proprietary Systems
Open Architecture
– Interoperability required by TIA 568B.1
– Lower cost
– Pick and choose products
Proprietary Systems
–
–
–
–
Matched and balanced for maximum performance
Warranties available
Limited product selection
Requires systems training
Commissa 2003
The intersection of
Technology and Facilities
IT Infrastructure Commissioning
Commissa 2003
IT Infrastructure Commissioning
Application of established commissioning
procedures to IT Infrastructure
requirements
Combination of IT expertise and
construction experience
Bridges the gap between IT needs and
architectural specifications
Ensures the reliability of the new
converged technologies (IP)
Commissa 2003
Benefits of IT Commissioning
Identifies the owners requirements in
accordance with the design intent
Cost savings by reducing change orders
due to errors and omissions
Quality Control Process
Acts as a “check & balance” for low bid
projects
IT Staff time re-directed to core business
Facility is operational – “the first time”
Commissa 2003
IT Commissioning Objectives
Network Connectivity
Power requirements
Code compliance
Standards verification
Fire & Security requirements
A/V integration
Building Automation and Control
integration
Commissa 2003
IT Commissioning Objectives
Proper space & pathway planning
Installation methods verification
Testing
Documentation and “As-Builts”
Network Operability
Convergence validation
Commissa 2003
Types of Commissioning
Continuous
Milestone Monitoring
Acceptance Phase
Network Operability
Commissa 2003
Case Study
University Science Building
– Two Buildings connected by a common atrium
120,000 sq. ft’
Combination Classroom/Lab/Office
1,800 Work Area Outlets – 6,000 cables
27 Telecommunications Rooms
SMF/MMF Backbone for Data
– 972 fiber connections
Copper Voice Backbone
– 8,100 pairs
Commissa 2003
Case Study
Cable Plant Design
Client Building Specifications
Manufacturer's Warranty
Certified Installer
Commissioning Plan
Commissa 2003
Case Study
Commissioning Process uncovered
multiple deficiencies in cable plant
and infrastructure components.
Contractor contractually required to
correct problems at no additional cost
Estimated savings over $50,000
Commissa 2003
Installation Deficiencies
Innerduct attached to conduit
Cables laying on ceiling tiles
Improper fiber termination method
Cables laying on fixtures
Summary COMMUNICATION INFRASTRUCTURE AUDIT
STANDARDS SUMMARY
ANSI/EIA/TIA
YALE
ITS
X
X
X
X
X
X
X
X
X
X
NO FIBER SERVICE LOOP
X
X
X
NO BONDING JUMPER BETWEEN
RACKS
X
X
X
X
X
X
X
X
IMPROPER FIRESTOPPING
NATIONAL ELECTRIC
SIEMON
CODE (NEC)
WARRANTY
X
BEND RADIUS AND BEND DELIMITER
EXCEEDED
NO BUSHINGS ON SLEEVES
X
X
BICSI
MANUFACTURER'S
CONSTRUCTIION
TDM INSTALLATION REQUIREMENTS
"T" DWGS
SLEEVE HEIGHT LESS THAN 4"
WORKING CLEARANCE (30")
NOT MAINTAINED
T7.02 NOTE 10
T7.02 NOTE 9
X
IMPROPER TENSION OF TY RAPS
X
X
X
X
X
X
X
X
X
X
CABLE CLEARANCE S FROM LIGHT
LESS THAN 2"
X
X
X
X
X
X
CABLES OR DUCT ATTACHED
TO CONDUIT
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
IMPROPER CABLE SUPPORT
SLEEVE FILL RATIO EXCEEDED
T7.02 NOTE 8
T7.03
X
POWER NOT INSTALLED ON RACKS
T7.06
FIBER TRAY SYSTEM NOT INSTALLED
T6.01
T6.02
ORIENTATION OF WALL PHONE
JACK INCORRECT
T7.03
HAND WRITTEN LABELS
X
X
X
X
CABLE SLACK AT WAO
X
X
X
X
X
Riser COMMUNICATION INFRASTRUCTURE AUDIT
RISER TEST SUMMARY
Copper Riser Test Results
NUMBER OF RECORDS
775 pairs
FAILURES
107 pairs
PROBLEM
CLOSET
TC L6-A
ROOM 666C
REVERSED BINDER 050/076 - 76/100
CLOSET
TC L3-A
ROOM 366C
REVERSAL ON 225 AND 325
ORANGE AND GREEN BINDER FLIPPED
CLOSET
TC L1-A
ROOM 166C
175 REVERSED PAIR
CLOSET
TC LL1-D NL06
1 REVERSED PAIR
2 & 3 OPEN
CLOSET
TC L2-D
N224
PAIR 52 & 53 OPEN
CLOSET
TC L3-D
N324
REVERSED PAIR 27
Commissa 2003
Fiber Riser Test Results
NUMBER OF RECORDS
115 Strands
30 Strands
27 Strands
57
Tested
Performance Faiure
Were Open
TOTAL FAILURES
PROBLEM
CLOSET
CLOSET
CLOSET
CLOSET
TC
TC
TC
TC
LL1-D
L6-C
L6-A
L5-B
CLOSET
CLOSET
TC L4-C
TC L4-B
S400B
S436C
CLOSET
CLOSET
CLOSET
CLOSET
CLOSET
CLOSET
CLOSET
TC
TC
TC
TC
TC
TC
TC
S336C
S366C
S200B
S136C
S166C
SL49
NL06
CLOSET
CLOSET
TC LL1-D
TC L2-D
N124
N224
CLOSET
CLOSET
TC L2-E
TC L3-E
N208
N 308
L3-B
L3-A
L2-C
L1-B
L1-A
LL1-D
LL1-D
NL06
S600B
S666C
S536C
SM PORTS 2&3 OPEN
SM PORTS 5&6 OPEN
SM PORTS 3&4 OPEN
MM BINDER GROUP REVERSED 1IN CLOSET IS
7 AT MDF
SM PORTS 3,5&6 OPEN
SM PORTS 1&2 FAILED
SM PORT 3 LIGHT ONLY FAIL
SM PORTS 4&6 OPEN
NOTE:
RACK 5 RIC #2 CABLE
IS SWAPPED BETWEEN
S436C AND S336C
SM PORTS 1&2 FAILED
SM 5 PORT OPEN
SM PORT 6 OPEN
SM PORT 3 OPEN
MM PORT 5 OPEN
SM PORT 6 OPEN
SM PORTS 2&3 OPEN
MM PORTS 3&4 OPEN
SM PORTS 1&2 OPEN
SM PORTS 1&2 OPEN
MM PORT 6 OPEN
SM PORT5 OPEN
MM PORT 2 OPEN
NOTE:
RIC LABELED
INCORRECTLY
DUE TO THE HIGH FAILURE RATE WE TESTED MORE THAN THE REQUIRED 10%
MDF RIC LABELING IS INCONSISTENT WITH CLOSET LABELING
Case Study Conclusions
Specifications were minimally enforced
Marginal workmanship issues were
resolved by the warranty and
commissioning
IT inspection reports were
overwhelming
Commission Report identified additional
deficiencies and subsequent corrective
action.
Commissioning ROI was Five to One
Commissa 2003
Information & Training
Resources
ASHRAE – American Society of
Heating, Refrigerating and AirConditioning Engineers.
(www.ashrae.org)
GSA & Department of Energy
www.gsa.org
BICSI – Building Industry Consulting
Service International (www.bicsi.org)
CSI – Construction Specifications
Institute (www.csi.org)
Commissa 2003
Information & Training
Resources
TIA/EIA – Telecommunications Industry
Association (www.tia.org)
NIBI – National Institute of Building Sciences
(www.nibs.org)
BCA – Building Commissioning Association
(www.bcxa.org)
PECI – Portland Energy Conservation
Inc.(www.peci.org)
Commissa 2003
Information & Training
Resources
Additional web sites
– Florida Design Initiative
www.fcn.state.fl.us/fdi
– University of Washington
www.weber.u.washington.edu
– Association of Higher Education Facilities
Officers www.appa.org
– Federal Energy Management Program
www.eren.doe.gov/femp/facbuild
Commissa 2003