Wat is informatica?
Download
Report
Transcript Wat is informatica?
Accept or Reject:
Can we get the work done in
time?
Marjan van den Akker
Joint work with
Han Hoogeveen
Outline of the talk
• Problem description
• Review Moore-Hogdson
• Stochastic processing times
– consequences
– four classes of instances
• Summary
Problem setting
•
•
•
•
n jobs become available at time 0
Known processing time
Known due date
Known reward for completing in time (currently 1)
Decision to make now: accept or reject
minimize number of tardy jobs
on a single machine
Moore-Hodgson
1. Number the jobs in EDD order
2. Let S denote the EDD schedule
3. Find the first job not on time in S (suppose
this is job j)
4. Remove from S the largest available job
from jobs 1,…,j
5. Continue with Step 3 for this new schedule S
until all jobs are on time
Solving the problem from scratch
Observations
• First the on time jobs
• On time jobs in EDD order
• Forget about the late jobs
Knowing the on time set is sufficient
Dominance rule
• Let E1 and E2 be two subsets of jobs 1,…,j
• All jobs in E1 and E2 are on time (feasible)
• Cardinality of E1 and E2 is equal
• The total processing time of the jobs in E2 is
more than the total processing time of the
jobs in E1
Then subset E2 can be discarded.
Proof (sketch)
Take an optimal schedule starting with E2
(remainder: jobs from j+1, …, n)
E2
remainder
time
0
E1
remainder
Use dynamic programming
• Find Ej*(k): feasible subset of jobs 1,…,j with
cardinality k and minimum total processing
time
• Use state variables fj(k) equal to p(Ej*(k))
• Define zj as maximum number of on time jobs
from jobs 1, …, j
• Initialization: fj(k)=0 for j=k=0 (and +
otherwise)
Recurrence relation
• Put fj+1 (0)=0
• fj+1(k)=min{fj(k),fj(k-1)+pj+1} (k=1,…,zj)
• If fj(z_j)+pj+1 dj+1
then zj+1=zj+1 and fj+1(zj+1)=fj(zj)+pj+1;
otherwise, zj+1=zj.
Relation with Moore-Hodgson
• The set Ej*(k-1) can be computed from
Ej*(k) by removing the largest job!
• Recurrence relation
fj+1(k)=min{fj(k),fj(k-1)+pj+1}
Equal to: remove the largest job
Moore-Hodgson
1. Number the jobs in EDD order
2. Compute the values fj(zj):
– If fj(z_j)+pj+1 dj+1
then zj+1=zj+1 and fj+1(zj+1)=fj(zj)+pj+1
i.e. Jj+1 is added
– else zj+1 = zj and
fj+1(zj+1) = min{fj(zj),fj(zj-1)+pj+1}
i.e. largest job is removed
Stochastic processing times
• Completion times are uncertain
• Decision about accept or reject must
be made before running the schedule
• When do you consider a job on time?
On time stochastically
• Work with a sequence of on time jobs
(instead of a set of completion times)
• Add a job to this sequence and compute the
probability that it is ready on time
• If this probability is large enough (at least
equal to the minimum success probability
msp) then accept it as on time
Classes of processing times
•
•
Gamma distribution
Negative binomial distribution
•
•
Equally disturbed processing times p_j
Normal distribution
Jobs must be independent
Class 1: Gamma distribution
• Parameters a_j and b (common)
• If x_1 and x_2 follow the gamma distribution
and are independent, then x_1+x_2 is
gamma distributed with parameters a_1+a_2
and b.
More gamma
• Define S as the set of the job j and all its
predecessors in the schedule
• Define p(S) as the sum of all processing times
of jobs in S
• Then C_j=p(S) follows a gamma distribution
with parameters a(S) and b.
Even more gamma
• Denote the msp of job j by y_j
• Job j is on time if the probability that C_j is
no more than d_j is at least y_j
• C_j depends on a(S) only
• Given d_j and y_j, you can compute the
maximum value of a(S) such that
P(Cj <= dj) is at least yj: call it D_j
Last of Gamma
• Treat D_j as ordinary due dates
• Treat a_j as ordinary deterministic processing
times
• Then the dominance rule still holds
• You can use Moore-Hodgson!
• Negative binomial distribution: similar
More complicated problems
Normally distributed processing times
pj
Var
dj
mspj
Job 1
12
1
20
0.5
Job 2
8
1
21
0.95
Optimum: first job 2 and then job 1
From now on: equal msp values EDD-order
Equal disturbances
• On time probability of job j depends on:
– Number of predecessors (on time jobs before j)
– Total processing time of its predecessors
• Dominance rule: given the cardinality of the on time
set, take the one with minimum total processing time
• Use dynamic programming with state variables fj(k)
that indicate the minimum total processing possible
(as before)
• Hence: Moore-Hodgson’s solves it!
Normal distribution (1)
• Parameters: expected processing time of job j
and variance of job j
• Reminder: expected value and variances of
X1+X2 are equal to the respective sums
• Necessary for computing the on time
probability of job j:
– Total processing time of predecessors
– Total variance of predecessors
Normal distribution (2)
• Dominance rule: if cardinality and total
processing time are equal, then take the set
with minimum total variance (msp > 0.5)
• Use state variables fj(k,P):
– k is cardinality of on time set
– P is total processing time of on time set
– fj(k,P) is minimum variance possible
Normal distribution: details
• Running time pseudo-polynomial
• Problem is NP-hard
• Role of total variance and total processing
time in the dominance rule and in the DP is
interchangeable
What to remember (optional)
• Moore-Hodgson = Dynamic Programming
• DP is applicable in a stochastic environment
– Stochastic on time: work with the minimum
success probability
– EDD sequence optimal for the on time set??
• Weighted case can be solved in a similar way
Known problem?
Yes: single machine, minimize
number of tardy jobs
Solvable in O(n log n) time by
Moore-Hodgson
Miscellaneous remarks
• DP computes more state variables than
necessary
• DP can be used for the weighted case:
– Use fj(W) with W is the total weight of the on time
set (instead of cardinality of the on time set)
• DP can be used for more problems
(to be shown next)
Negative binomial distribution
• Parameters s_j and p (common for all jobs)
• If independent, then C_j=p(S) follows a
negative binomial distribution with
parameters s(S) and p
• Same as gamma distribution