ESSNet on Standardisation
Mr. Csaba Ábry
E-mail: [email protected]
Hungarian Central Statistical Office
23-24 January 2014, Valencia
History of the project
• ESSNet ‘STAND-PREP’ in 2010
• Sponsorship on Standardisation in 2011-2012
• Launch of ESSNet on Standardisation: September 2012
– Framework Partnership Agreement (FPA) was signed in
September 2012
– Specific Grant Agreement 1 (SGA1)was launched in
December 2012, duration: 15 months
– End of SGA1 is in March 2014
– Specific Grant Agreement 2 (SGA2) was launched in
December 2013, duration: 15 months
– End of SGA2 app. March 2015
2
Aim of the FPA
• Continue the work elaborated by the Sponsorship
on Standardisation (connected to several but not
all recommendations of the Sponsorship )
• Goal: further elaboration of elements related to
ESS standardisation and move towards practical
implementation of the Sponsorship
recommendations
• Support the establishment of the Integrated
Statistical System within the ESS
3
ESSnet partners in the FPA
• Hungary (HCSO, Hungarian Central Statistical Office),
coordinator
• France (INSEE, Institut National de la Statistique et des
Études Économiques)
• Italy (ISTAT, Istituto Nazionale di Statistica)
• Latvia (CSB, Latvijas Statistika)
• Lithuania (SL, Lietuvos Statistikos Departamentas)
• The Netherlands (CBS, Centraal Bureau voor de
Statistiek)
• United Kingdom (ONS, Office for National Statistics)
4
Main topics of the projects SGA1 and
SGA2
• Inventory of normative documents (legal acts,
standards, other normative documents)
• Process of standardisation (life-cycle model,
documentation)
• Cost-benefit analysis
• Business architecture
• Test cases
5
Management issues
• Overlap with the work of the Sponsorship on
Standardisation
– Problem: ESSNet on Standardisation has to
continue the work of the Sponsorship on
Standardisation
• Overlap between SGA1 and SGA2
– Problem: Same human resources for both SGAs
• SWOT vs. Cost-benefit analysis
– Problem: Changes in direction at the half-time
6
Budgetary issues
• Budget of SGA1 – 250 000 euros
• Budget of SGA2 – 150 000 euros
Problem: low budget
7
Communication issues (1)
• In SGA1 no extra money for external
communication (informal communication)
• In May 2013 Forward-looking feedback workshop
was held for the Sponsorship on Standardisation,
(The Hague)
• In case of case studies we contacted the SDMX
Secretary and Eurostat
• In SGA2 we ask the DIME standardisation
Steering Group to coordinate the communication
between ESS-standardisation related initiatives
and projects (e.g. validation, feedbacks etc.)
8
Communication issues (2)
• In SGA2 we would like to communicate with the
initiatives engaged in ESS standardisation-related
activities (e.g. cost-benefit analysis, business
architecture, development and use of standards, etc.)
• In SGA2 the following external communication
channels will be used:
–
–
–
–
European Modernisation Workshop in Valencia
Q2014, Vienna
Joint workshop with DIME
Website for the deliverables of the project (beside CROS
portal)
9
Communication issues (3)
• In SGA2 we choose a case study for testing the
standard setting process with the help of
EUROSTAT and DIME Steering Group
10
Thank you for the attention!
Csaba Ábry
e-mail: [email protected]
ESSNet on Standardisation on CROS-portal
(http://www.cros-portal.eu/content/standardisation)
11