Project Management:
Principles and Practices
Level 2
Agenda
Introductions
Course Objectives
Unit 1: Leadership
Unit 2: Communication
Unit 3: Operating Guidelines
Unit 4: Procurement Management
Unit 5: Quality Management
Unit 6: Monitoring and Controlling
Unit 7: Close-out
Unit 8: Common Project Problems
Introductions
What is your Project Management
experience?
What type of projects will you be
involved in?
What would you like to get out of the
course?
Course Objectives
Understand different types of leadership, how to lead change
and organize people.
Establish project operating guidelines such as communication
plans, change management procedures and reporting
structures.
Evaluate different types of contracts and how they can benefit
your project.
Build and plan quality into your solution.
Learn how to monitor the execution of the plan and control the
project by balancing changing priorities and demands.
Understand how to properly close-out a project and learn what
went right and what went wrong.
Explore common project problems and learn how to avoid them.
Reference Material
Project Management
The Complete Idiot’s Guide
Unit 1
Leadership
Leadership
Chapter 18
Types of leadership
Leading change
Ways to organize people
Stage of team formation and leadership
Leading vs. Managing
Leading means that you command
respect and take responsibility for
guiding the project.
Managing indicates that you monitor
and control the project to ensure that
the work is accomplished.
Leadership tips
Listen and ask lots of questions
Provide reliable information for the team
Observe what is going on and take notes
Know enough to know that you don’t know everything
Be available
Make decisions when needed but know when to
defer decisions to stakeholders
Delegate work that needs to be delegated
Don’t micro-manage
Types of Leadership
Task-orientated leadership
Employee-oriented leadership
Reward-based leadership
Leading Change
Case for Change
1. Why are we doing this project from a
business perspective?
2. What will change when the project is
completed?
3. What will happen if we don’t complete this
project successfully?
4. What are the benefits of doing this project to
us and the business?
5. What will we need to do differently?
Organizing People
Chapter 14
Functional
Pure project
Matrix
Functional Organization
Organized around common activities or expertise such
accounting, customer service or information technology
Advantages
Familiarity of the team
Established administrative systems
Staff availability
Scheduling efficiency
Clear authority
Disadvantages
Project isolation
Limited resources
Bureaucratic procedures
Lack of project focus
Department orientation
Pure-Project Organization
The Project Manager has full authority to assign
priorities and direct the work of all the members of
the project team
Advantages
Clear project authority
Simplified project communications
Access to special expertise
Project focus and priority
Disadvantages
Duplication of efforts
Unclear loyalties and motivations
Intra-company rivalry
Matrix Organization
The Project Manager shares responsibility with the functional
managers for assigning the priorities and directing the work of
individuals assigned to the project
Advantages
Clear project focus
Flexible staffing
Adaptability to management needs and skills
Staff development opportunities
Adaptability to business changes
Disadvantages
Built-in conflicts
Resistance to termination
Complex command and authority relationships
Complex employee recognition systems
RACI Chart
R – Responsible
Activity
Bob
A – Accountable
Requirements
R
C – Consult
Design
I – Inform
Development
Sue
Jane
Jack
C
Fred
Allie
I
A
I
C
R
A
C
I
I
R
A
Testing
C
R
I
I
I
A
Training
A
I
C
C
C
R
Project Team
Chapter 14
Need to let the team members know
The reason they are on the team, what
they have to offer
Clear roles and responsibilities for each
person on the team
Standards that they will be held
accountable to
Responsibility Assignment Matrix
(RAM)
Phase
Bob
Requirements
A
Design
Sue
Jane
Jack
P
S
Fred
Allie
I
R
P
A
Development
A
I
P
A
I
Testing
A
S
A
A
P
Training
P
I
P=Primary
A=Assigned
R=Review Required
A
A
I=Input Required
S=Signature Required
Building a team
What kinds of experience do you need?
What kind of competency do they have?
What is their availability?
Do they have a personal interest in the
outcome of the project?
Will they work well in a team
environment?
Staffing Alternatives
Use your own staff & people from your
department
Staff from other departments
Contract with consultants, outside
agencies, or temporary agencies
Hire and train new staff
Dealing with Staffing
Challenges
Do the best you can with the people you
have, and document problems and
results.
If they do not have enough skills and
training takes too long, consider
contracting.
Compromise and negotiate for the team
members you really need.
Activity
Using the case study, create a RAM
(Responsibility Assignment Matrix) for
the project
Stages of Team Forming and
Leadership
Forming
Directive style of leadership
Gives structure
Clear responsibilities, lines of
communication
Stages of Team Forming and
Leadership
Storming
Selling or Influencing style of leadership
Team members may be questioning
Manage conflict
Stages of Team Forming and
Leadership
Norming
Participative style of leadership
Team members are supportive
Work as a group
Stages of Team Forming and
Leadership
Performing
Delegative style of leadership
Activity
Style of leadership survey
Unit 1 Review
Types of leadership
Leading change
Ways to organize people
Project teams
Stages of team formation and
leadership
Unit 2
Communication
Communication
Chapter 21
Communication Plan
Communication and Leadership
Communication Plan
Stakeholder analysis
Sensitivity analysis
Information needs
Media requirements
Delivery personnel and power base
Timing requirements
Common definitions
Feedback loops
Macro and micro barriers
Jargon and acronyms
Communication Plan
Stakeholder Analysis
Determine the stakeholder’s interest in the
project
Determines what information they will want
to receive
Sensitivity Analysis
Identifying sensitive areas amongst the
stakeholders
Communication Plan
Information Needs
Understand what each group is interested in and
level of detail
Media Requirements
Vehicles used to deliver the information
Town hall meetings
Presentations
Staff meetings
Written memos
Wall charts
Web portals
Types of Communication and their
Characteristics
Type of
communication
Group
Individual
Written Spoken
Formal
Memo/e-mail
√
√
Letters
√
√
√
Reports
√
√
√
Meetings
√
Presentations
√
Teleconference
√
Telephone
√
√
√
√
√
√
√
Informal
√
√
√
Communication Plan
Delivery Personnel and Power Bases
Power Base
Action
Expertise
Persuasion
+++
Admiration
Ask
++
Reward
Promise
+
Position of Authority Order
Coercion
Threat
Results
-
__
Communication Plan
Timing Requirements
Just-in-time information
Common Definition
Make sure everyone speaks the same
language
Feedback Loops
Ensures communication is received
correctly
Communication Plan
Macro and Micro Barriers
Geography, language, culture
Attitudes
Jargon and Acronyms
Clarify acronyms
Use same jargon as stakeholders
Communication & Leadership
Vertical Communication
Horizontal Communication
Diagonal Communication
The purpose of my message is……
Effective Messages
Draft the message and edit
Consider audience’s expectations, actions required,
and your expectations after the message is delivered
Justify the choice of delivery medium
Start with an introduction that identifies the issue,
context or opportunity of interest
Make required actions clear and specific
Be concise
Never surprise someone with information, ensure that
important information is understood before discussed
Communicate by Listening
Stop talking and let others tell you what
they want to say
Let people finish what they are saying
Eliminate distractions
Listen with purpose and intent
Restate what you hear people say
Activity
Develop a communication plan from the
case study
Unit 2 Review
Communication Plan
Communication and Leadership
Unit 3
Operating Guidelines
Chapters 24 & 20
Operating Guidelines
Change Management
Decision Making
Work Authorization
Reports
Change Management
Chapter 24
Change Control System
Formal documented procedures that define
how project deliverables and
documentation are controlled, changed
and approved.
Rules of change control
Establish change control policy in planning
phase and follow it.
Create a change control board (subset of
working committee) who evaluates changes
which impact stakeholders and the project
Establish an emergency decision-making
authority, in case decisions are needed
before the board can meet.
Maintain a change control log that tracks all
changes requests.
Change Control Request
Identification
What is the change
Impact of change
Who authorized it
6 areas of change
1.
The business reason the project was
undertaken
2.
The people who work on the project
3.
The budget
4.
The material and technical resources
5.
The time
6.
The quality requirements that were
acceptable for the deliverables
Balance
Project
Balance to keep the project within its approved cost,
schedule and quality
PM and core member may make these decisions
Business Case
Project cannot be balanced within cost, schedule and quality
goals
Stakeholders must approve
Enterprise
Choice between projects to balance resources
Business management decides with input from team
Balancing Choices
Reduce scope of tasks
Increase productivity by using in-house
experts
Use outside resources
Use overtime
Crash the schedule
Adjust the profit requirements for the project
Adjust the project goals
Changes Weighed
Communicate Change
Inform project team
Inform stakeholders using
communication plan
Log the change in the change log
Change and Conflict
Withdrawing
Smoothing
Compromising
Forcing
Confronting
Issue log
Keep track of any issues
Ensure they are documented and
resolved
Plan-Do-Check-Act Cycle
Decision Making
Chapter 20
Need to have a clear path of authority
indicating who makes what types of
decisions
Team decisions
Project Manager
Working Committee
Steering Committee
Project sponsor
Escalation Procedure
Work Authorization System (WAS)
Chapter 20
When should I start the work I’ve been
assigned?
A written method that sanctions the right
work is done in the right order.
Provides direction that allows a team
member to begin work on a specific
activity or work package
Reporting purpose
For every report identify
How often is the report produced?
What is contained in the report?
Who is responsible for producing it?
What is the objective of the report?
Who will follow up on action items?
Who is the intended audience?
Reporting
Chapter 20
Status Reports
Tasks completed since last report
Tasks in progress
Tasks planned with completion dates
Budget expenditure
Issues
Recommendations for project
improvements or changes
Questions or items that require approval or
input
Project Diary
Notes on progress
Problems
Issues (positive and negative)
Discussion points
Decisions made
Action items
Outcomes of meetings
Accomplishments
Conflicts
Extraordinary events
Activity
Create a Change Control System for your
project
How will changes be raised?
How will they be handled (who, when where, etc)?
How will they be communicated?
Determine decision making authority (who
can decide what)
Determine reporting structure (what type of
reports, when, to whom)
Unit 3 Review
Decision Making
Change Management
Work Authorization System
Reports
Unit 4
Procurement Management
Procurement Management
Chapter 15
Types of contracts
Fixed-price or lump sum
Cost-plus-fixed-fee
Time and materials
Working with procurement office
Types of Contracts
Fixed-price or lump sum
Total price for the goods or services
Risk is on the seller
Cost-plus-fixed-fee
Pay vendor for costs plus a fee
More risk on buyer but may add incentives
Time and materials
Combination of fixed-price and cost-reimbursable
Usually open-ended but a fee is established for
specific resources
Contracts - estimates
Always get an estimate
In writing
Minimum of 3 bids
Negotiate
Based on WBS what is the max and min
you expect to pay?
How will you evaluate the bids?
Single source or multiple vendors?
Review past performance
Working with the Purchasing
Department
May have/do all purchasing for/with you
Great expertise however, may introduce
overhead
Activity
What types of contracts will be
negotiated in the case study?
How would you go about establishing
them?
Unit 4 Review
Types of contracts
Contracting
Working with a procurement office
Unit 5
Quality Management
Quality Management
Chapter 25
Plan for Quality
Cost/Benefit Analysis
Benchmarking
Cause-and-Effect
Quality Assurance
Quality Control
Plan for Quality
Quality is conformance to requirements
Grade is the ranking applied to products that
have the same functional use but different
characteristics
Evaluate acceptance criteria
Functionality
Appearance
Accuracy of information
Reliability
Security
Cost/Benefit Analysis
Estimate of the costs and benefits of
various alternatives
Using financial measures (ROI or
payback period) determine which
alternative is the most desirable
Benchmarking
Compare your project to other similar
projects
Within your organization or PMI
Case-and-Effect Diagrams
Can help determine source of problems
Quality Assurance
Reviews
Peer reviews
Informal reviews
Formal reviews
Quality Control
Inspection
Test
Activity
How could you build quality into your
project?
What could be some benchmarks that
you could use?
How will quality be assured?
How will quality be controlled?
Unit 5 Review
Planning for quality
Cost/benefit analysis
Benchmarking
Cause-and-effect
Quality assurance
Quality control
Unit 6
Monitoring and Controlling
Monitoring and Controlling
Chapter 22
Purpose of monitoring
What to monitor
Earned Value Analysis
Reviews
Purpose of Monitoring
Communicate project status and
changes to team members
Manage expectations of stakeholders
regarding project status
Provide justification for project
adjustments
Document current project plans
compared to original
What to Monitor
Completion of work packages compared
to plan
Scope of work
Quality of work
Costs and expenditures
Attitudes of team
Cohesiveness and cooperation of team
Controlling
Use the project plan as a guide
Monitor and update plan regularly
Communicate
Get involved
Adapt project schedule, budget and work plan
as needed
Document progress and changes,
communicate them to the team
Project Status
Earned Value Analysis (EVA)
Budgeted Cost of Work Scheduled (BCWS)
Planned cost of the total amount of work scheduled to be
performed by the milestone
Actual Cost of Work Performed (ACWP)
Cost incurred to accomplish the work that has been done to
date
Budgeted Cost of Work Performed (BCWP)
The planned cost to complete the work that has been done
Schedule Variance (SV) = BCWP – BCWS
Cost Variance (CV) = BCWP - ACWP
Reviews
Project review meeting
Project audit
Activity
How will your project be controlled?
What will be reviewed in your project?
Unit 6 Review
Purpose of monitoring
What to monitor
How to control
Earned Value Analysis
Reviews
Unit 7
Close-out
Close-Out
Chapter 27
Closing the project
Lessons Learned
Post-Implementation Review
Final Report
Closing the Project
Final approval from stakeholders
Finalize contractual commitments
Transfer responsibilities to others
Reassign people in the project
Release non-human resources
Complete final accounting
Document results and recommendations for
the future
Lessons Learned
Focus areas
Project Management, Communications, Schedule
& Budget, Training, Quality, Issues, Human
Resources, Administration
What when well?
What didn’t?
What should be improved?
How?
Anything else?
Post-Implementation Review
Meeting with team
After celebration but before forgotten
What went well?
What could be improved?
Suggestions?
Final Report
Overview of project
Summary of Business Case
Major accomplishments
Achievements compared to Business Case objectives
Financial accounting
Analysis of quality against expectations
Evaluation of administration and management performance
Team’s performance
Special acknowledgments
Changes (approved and impact of changes)
Issues or tasks of further investigation
Recommendations for future projects
Post-implementation date
Activity
How will your project be closed out?
What type of post-implementation
review will you do?
Unit 7 Review
Closing the project
Lessons learned
Post-implementation review
Final report
Unit 8
Common Project
Problems
Chapter 26
Start Date Moves but End Date
Doesn’t
Communicate the issue to stakeholders
(verbally and in writing)
Re-evaluate scope
Re-evaluate schedule and resources
Not enough time
Prioritize and delegate
Eliminate work that isn’t necessary
Fast track (parallel activities) or crash
(add more people or reduce scope)
Overtime???
Changes, changes, changes
Have a documented Change Control
Process
Don’t start until plan is approved
Don’t agree to changes unless analyzed
and approved
Key person quits or is unavailable
Keep them happy
Responsibility matrix – cross train other
individuals
Ensure work is documented
Team has more enthusiasm than
talent
Conduct objective skills appraisal at the
beginning of the project
Watch for too much socializing
Training may be required
Mentoring
90% done
It may seem that 90% of the effort takes
30% of the time and the last 10% takes
200%
Investigate remaining work
Technical difficulties?
Additional tasks?
Ensure estimates are real and not what
you want to hear
Politics
Treat politics as any other conflict and
resolve
Take care of yourself
Remember that it is work
Scale back or step down
Course Review
Leadership
Operating Guidelines
Communication
Procurement Management
Quality Management
Monitoring and Controlling
Closing out a project
Activity
Conduct a post-implementation review
of this course
What went well?
What could be improved upon?
Suggestions?