L`Ambiance Plaza Collapse
Download
Report
Transcript L`Ambiance Plaza Collapse
L'Ambiance Plaza Collapse
Bridgeport, Connecticut
April 23, 1987
Group 15
Stephen Conlon
Brian Dowling
Kevin Brandon
Remi Monteiro
Introduction
L'Ambiance Plaza was planned to be a
sixteen-story building with thirteen
apartment levels topping three
parking levels.
It consisted of two rectangular towers
(The East Tower and The West
Tower), 63 ft by 112 ft each,
connected by an elevator.
Floor Plan
Construction
Seven-inch thick post tensioned, concrete slabs and
steel columns comprised its structural frame.
The lift-slab method of construction was utilized in the
construction of this building.
The floor post tensioned slabs for all sixteen levels
were constructed on the ground, one on top of the
other. Then packages of two or three slabs were lifted
into temporary position by a hydraulic lifting
apparatus and held into place by steel wedges.
Once the slabs were positioned correctly, they were
permanently attached to the steel columns.
Structural drawings specified that during construction
the shear walls, which provided lateral resistance for
the building, should be within 3 floors of the lifted
slabs.
Collapse
At the time of collapse, the building was a little more
than halfway completed.
The shear walls were about five levels below the lifted
slabs.
The workmen were tack welding wedges under the
ninth, tenth, and eleventh floor package to
temporarily hold them into position when they heard a
loud metallic sound followed by rumbling.
The entire structure collapsed, first the west tower
and then the east tower in 5 seconds.
28 construction workers died in the collapse.
An unusually prompt legal settlement prematurely
ended all investigations of the collapse. Consequently,
the exact cause of the collapse has never been
established.
Why it collapsed?
The building had a number of deficiencies; any one of which
could have triggered the collapse. Each one of these
following theories can explain where the first failure took
place.
Theory 1: The slabs’ lifting assembly failure caused the
collapse.
Theory 2: The instability of the wedges holding the twelfth
floor and roof package caused the collapse.
Theory 3: The improper design of the posttensioning
tendons caused the collapse.
Theory 4: Questionable weld details and substandard welds
could have caused the collapse.
Theory 5: The sensitivity of L’Ambiance Plaza to lateral
displacement caused its collapse
Conclusion
A two-judge panel mediated a universal
settlement between 100 parties closing the
L’Ambiance Plaza case. Twenty or more
separate parties were found guilty of
"widespread negligence, carelessness,
sloppy practices, and complacency."
Those injured and the families of those
killed in the collapse received $30 million.
Another $7.6 million was set aside to pay
for all of the claims and counter claims
between the designers and contractors of
L’Ambiance Plaza.
Conclusion
While buildings constructed by the lift-slab method are
stable once they are completed, if great care is not taken
during construction they can be dangerous.
The following measures can be taken to insure lateral
stability and safety during construction.
During all stages of construction, temporary lateral bracing
should be provided.
Concrete punching shear and connections redundancies should
be provided in the structure
Cribbing (temporary posts which support the concrete slab
until it is completely attached to the column) should be used.
Sway bracing (cables which keep the stack of floors from
shifting sideways) should be used. This was required, but not
used in L’Ambiance Plaza.
These measures could have saved the life of 28
construction workers.