Transcript TAL
LBT Q3 2007 Engineering
Review
TAL Telescope Alignment.
Highlights and Progress(Q3/2007)
Completed new alignment plans for rigid secondary and LBC
Procured alignment telescope accessories and mounting brackets in
preparation for Q4 alignment work.
Assessed Laser Tracker technology; selected vendor, awaiting
budget decision.
Determined that the blue hub is tilted to between 2 and 4 arcminutes from September engineering observations.
Confirmed that earlier assumptions on plate scale sensitivity to
mirror separation were out by a factor of ~40 (in reality much 8
microns instead of 350+ microns).
Proposed new single-pass null-test for adaptive secondaries.
Supporting Michael Andersen’s efforts in the AGW unit specification
document.
2
Open Issues
LBC Blue alignment can be improved. Possible to check hub
alignment to GR axis using A-Scope.
“Wall-eye” of PMs and other system flexures need to be
quantified and checked against available correction ranges of
optical elements. Again, the A-Scope set-up for LBC alignment
can give some useful measurements of that.
AGW support.
FPIA sensitivity to focus and other low-order aberrations
uncertain. Quantitative investigation underway with Zemaxmodelled CCD’s.
Awaiting budget decision on laser trackers, otherwise no large
optics purchases anticipated for Q4-Q1.
3
Progress
Q2: Finalize LBC alignment procedure and improve image quality to the
point that seeing limited images (on good nights) are achievable.
Alignment procedure finalized, alignment of LBC Red
currently scheduled for November, possibly some Blue
Hub alignment as well.
Q2: Procure alignment equipment
Alignment telescope mounts and accessories purchased.
Purchase of Laser Tracker in Q1 ‘08 if approved.
Q2: Finalize and “publish” up-to-date Zemax models of various LBT
modes
Work in progress, have working models of LBC Red, Blue
and Gregorian modes.
Q2: Continue with investigation of tolerances and compare results to
measured system performance
Work in progress.
4
Progress
Q2: Work with software on collimation/pointing etc.
No outstanding software support issues, supporting MA
for AGW work.
5
Planning
Schedule
Alignment of LBC Red currently scheduled for November,
possibly some Blue Hub alignment as well.
Purchase of Laser Tracker in Q1 ‘08 if approved.
Alignment of rigid secondary in Q1 ‘08.
Alignment of tertiary mirrors in Q4 ’07 (goal).
Assistance of MA ongoing.
FPIA investigation ongoing.
Publish global coordinate system for LBT (one exists already).
Publish various “final” Zemax models.
Resource
Assistance from Software, Engineering groups as well as various
Germans, Italians and John Hill.
6